By Frederick A. Nuamah: Kaaf University College Faculty of Engineering Department of Construction Technology
By Frederick A. Nuamah: Kaaf University College Faculty of Engineering Department of Construction Technology
NUAMAH
KAAF UNIVERSITY COLLEGE
FACULTY OF ENGINEERING
DEPARTMENT OF CONSTRUCTION TECHNOLOGY
Structure of the Construction Industry
Economics of the Construction Industry
Construction Cost, Price and Value
Design factors of Geometry
Estimating: Levels of Estimating, Introduction
to Estimating Procedure.
Introduction to basic construction resources:
Macmillan
Ferry, D.J. and Brandon, P.S. (1994) Cost
capital outlay.
Most construction are bespoke designed and
functions
Contractual relationship in the design and
build.
The CI plays a very vital role in the national
economy of countries worldwide. Its
importance stems from three of its
characteristics:
Size
Provision of predominantly investment
products
Government being the client for a large
(GDP)
Employs about 2.3% of the economically
of the purchaser.
CI is used by governments for national
construction.
Due to the high monetary value of projects
is;
1) explicit
2) consistent
3) takes account of methods of construction and
circumstances which may affect the execution
of the work on a project
A reliable estimate can only be achieved
when;
a) each operation or item is analysed into its
simplest elements, and
b) the cost calculated methodically on the basis
of factual information.
The estimate is a base document which
provides an important budget for cost control
during construction.
It is based on this that many assessments and
provided.
Preliminary estimate will be based either on the units
to
check the accuracy of previous estimates
To give advance warning of where
PROFIT
Much more subjective than either price or cost.
In the economic theory of value, an object
must be scarce relative to demand to have a
value.
Where there is an abundance of a particular
object and only a limited demand for it, then,
using the economic criteria, it has little or no
value attributed to it.
Value constitute a measure, therefore, of the
relationship between supply and demand
An increase in the value of an object can
therefore be obtained either through an increase
in demand or a decrease in supply
Aristotle identified seven (7) classes of value that
are still relevant to our modern society.
These classifications of value can be summarised
as;
Economic
Moral value
Aesthetic
Social
Political
Religious
Judicial
Economic value may be seen as the more
objective consideration
This is because its measureable in terms of
money
The remainder are seen as being more subjective
Maximum value is assumed to be found when a
development
The type of project generally determines the size of the
site
The cost of the project is also affected by the location
of the site
Problems of access, materials deliveries, close
provision
The construction cost also varies in different part of the
country
The location of the building on the site will also affect
counterparts
The reasons been the effect of the economic theory of
economies of scale
Smaller projects take a proportionately longer time per
unit to design
A further reason for the lower unit cost is the lower wall-to-
floor ratio
For a given plan shape, a larger plan area will always result
in a lower ratio
Example:
A building 30m x 30m x 4m high has a wall-to-floor ratio of
0.533
A similar project offering nine times this area,
90m x 90m x 4m high, has a wall-to-floor ratio of 0.178
It might be noted at this point that just as size does not
change directly with cost, neither does the wall-to-floor ratio
There is a correlation of cost with wall-to-floor ratio
than with size
Manufacturers will always give larger discounts for
larger orders
Theoretical pricing data from price books will also
floor ratio
On the other hand, the more complex the shape the
expensive
The storey heights of buildings are largely determined by
the needs of the user
A greater storey height than normal may be necessary to
assembly