Resource Allocation: By:-Anubha Jain Kshitij Pareek
Resource Allocation: By:-Anubha Jain Kshitij Pareek
By :-
Anubha Jain
Kshitij Pareek
What is resource
allocation ?
Evaluation stage
Inadequate project study
Wrong selection of location
Start up stage
Defects in erection and installtations
Failures of certain equipments and parts
Steps in crashing
Step I:-
Prepare the network diagram, find the normal critical
path and determine critical activities.
Step II:-
Calculate cost slope,for different activities with the
help of formulae .
Step III:-
Identify those activities on critical path which can be
crashed.
Contd……
Step IV:-
Crash the least expensive activity i.e. the activity with
least slope
Step V:-
By crashing the activity of critical path if other paths
also become critical ,a situation of parallel critical
path is obtained which implies that the duration of
the project can further be reduced through
simultaneous crashing of the activities in the
parallel critical paths
Contd…….
Step VI:-
Calculate the total cost.
General rules for crashing
Crash only critical activities on the critical path
1
c
4
a 3,60 3,60 No
b
e
b 6,80 7,30 Yes
3 c 4,90 5,50 Yes
d 5,50 6,30 Yes
e 2,100 4,40 Yes
Contd….
Paths Normal duration Crash duration
1-2-4 9 8
1-2-3-4 12 7
1-3-4 11 8
Activitiy cost
1-2 -
2-3 40
3-4 30
Since the lowest cost is 30 therefore activity
3-4 will be crashed by 1 day.
Contd….
Activity Normal duration
1-2-4 9
1-2-3-4 12 , 11
1-3-4 11 , 10
______________________________________________
Therefore,
Activity Duration
1-2-4 9
1-2-3-4 12,11,10,9
1-3-4 11,10,9
Contd.....
Possible cost options,
Crashing cost=20+40+50
=110
Contd….
Path Duration
1-2-4 9,8
1-2-3-4 12,11,10,9,8
1-3-4 11,10,9,8
Contd….
Total crashing cost=30+30+40+110
=rs.210
Thank you