Class Activity: Individual Assignment

This document describes a material requirements planning (MRP) problem involving multiple products and components. It provides information on the product structure, lead times, lot sizes, scheduled receipts, on-hand inventory, and a demand for the end product. The individual is asked to construct a product structure tree showing the different levels, and a gross material requirements plan showing requirements, order releases, and order receipts based on the given information.

Uploaded by

Budy s Raharja
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
145 views

Class Activity: Individual Assignment

This document describes a material requirements planning (MRP) problem involving multiple products and components. It provides information on the product structure, lead times, lot sizes, scheduled receipts, on-hand inventory, and a demand for the end product. The individual is asked to construct a product structure tree showing the different levels, and a gross material requirements plan showing requirements, order releases, and order receipts based on the given information.

Uploaded by

Budy s Raharja
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Class Activity

Individual Assignment
MATERIAL REQUIREMENTS
PLANNING

Budiman Slamet Raharja


29120503
2
Question 1
• The information of demand for subassembly product A is made of two units of B and
one unit of C. Each C is composed of three units of B, one unit of D, and four units of E.
Each B is made of three units of D and one unit of F. Each D is made of one unit of E.
Items C has a lead time of one week; Items A, B, E, and F have two week lead times; and
Item D has a lead time of three weeks. Lot for lot lot sizing is used for items C, E and F;
lot for size 20, 40 and 160 are used for items A, B and D, respectively. Items A, B, D, and
E have on hand (beginning) inventories of 5, 10, 100 and 100 respectively; all other
items have zero beginning inventories. We are schedule to received 10 units of A in
Week 3, 20 units of B in week 7, 40 units of F in Week 5, and 60 units of E in Week 2;
there are no other schedule receipts. There is 20 units of A are required in Week 10.
• Construct a product structure tree and identify all levels.
• Construct a gross material requirement plan showing gross and requirement and order
release and order receipt dates using the on hand inventory data.
Answer
• Construct a product structure tree and identify all levels.

LEVEL

A 0

B (2) C (1) 1

D (3) F (1) B (3) D (1) E (4) 2


Construct a product structure tree and identify all levels.

B (2) C (1)

D (3) F (1) B (3) E (4)

D (1)

E (1)
D (3)
F (1) E (1)

E (1)
Answer
• Construct a product structure tree and identify all levels.

Lead Time : Good Received Shedule :


C : 1 Week Week 2 : 60 Units E
D : 3 Week Week 3 : 10 Units A
A, B E and F : 2 Week Week 5 : 40 Units F
Week 7 : 20 Units B
Lot for Lot
C,E and F
20;40 and 160 Used for item A, B and D

On Hand Inventory 20 Units A Required In Week 10


A:5
B : 100
D : 100
E : 100
Answer
Construct a gross material requirement plan showing gross and
requirement and order release and order receipt dates using the on
hand inventory data.