Quantity Servey Unit I - III
Quantity Servey Unit I - III
Annamalai University
UNIT I to III
Construction
Annamalai University
While the project is underway , the Quantity Surveyor
Conflict can arise and the Quantity Surveyor Steps in to act as a liaison
between conflicted members of the construction process
and function shift. This objective now is to monitor the building and
make sure that operational costs are kept inside the budget.
the responsibilities are to make sure the project adheres to local
and national tax laws.
Insurance claims and cost of replacement are dealt with by the
Quantity Surveyor. Accurate estimates of damages and costs of
destroyed or damaged goods are also provided.
Basic Roles And Responsibilities
Prepare , submit and collect claims for payment
Perform liaison with main contractors, sub contractors and other parties
involved the projects
Recognize the preliminary and detailed estimating methods and focusing on the
elements for construction projects
Annamalai University
Quantity Survey
Introduction to Engineering project including project cycle, &
bidding documents.
Quantities surveying and calculation of different areas.
Methods of measurement of the works.
Pricing & cost analysis.
Payment certificate.
Application on Engineering project
Annamalai University
The Engineering Project
Project
Annamalai University
Types of construction Engineering Projects
Building construction
Roads Construction
Water Systems
Sewerage and Storm water systems
Annamalai University
Project Cycle
Implementation
& supervision
Annamalai University
Main stages in construction project
3- Preliminary design
5- Tender documents.
Annamalai University
Construction Project Cycle
P e r c e n t C o m p le te Full
Ope rations
M ajor Contracts
Le t
Proje ct "GO"
De cis ion
Annamalai University
Tender Documents
Annamalai University
The Project Parties
The Employer /Owner
The consultant: who appointed by the employer to do the design
and bidding documents and supervise the construction work.
The contractor: who was approved by the employer to implement
the works according to the submitted bid.
Annamalai University
Other Parties
Municipalities, ministries,
suppliers, technicians
Subcontracts, workers,
Insurance companies
Banks and other financing agencies.
Annamalai University
Construction Project Teams
- design
- Implementation / construction
- supervision
Annamalai University
Construction Project Teams
Annamalai University
Quantity Surveyor
He the person who is responsible on estimating the quantities from the design
drawings, and measurement of the quantities in the site during the project
implementation, and preparing the current and final payments.
Quantity Surveys (Take off)
It is the quantity of works/material take off , required for the completion of
project implementation, and listed as items in table of quantities.
1. Description and preparation of the bill of quantities and its items required for
the tender.
Preparation of the BOQ from the design drawing which part of bidding documents.
Preparation of the reports about the conformity of the quantities items with contract documents.
Prepare the eng. Measurement for the quantities of the finished works.
Prepare the detailed reports describing the situation of the items quantities, (plus or minus the contract
Required Skills
1- Conventional measurement
Depends on experience, and type of project.
Doesn't govern by theories or engineering basics.
Not considered as scientific method.
Doesn't subtract the opening as windows or doors from the block, plastering, painting
works and computing whole wall.
Another example : as the every 3 steps in stair = 1 m3
2- Engineering measurement
It is calculating all the works finished after subtracting all opening.
Example Measurement Unit
Earth work,
Cont.
earthling system Works have details Lump-sum
(electrical),, difficult to be (L.S)
calculated
As pipes Works have specific M.R
length and width
Windows, doors, Works have 3 dim. No.
fixed
as plastering, painting, Works with specific M2
thickness,
Footings, columns, stairs, Variable dimensions M3
As steel Have specific width Ton / kg
Workers wages, equipment, Labor / equipment Day / hrs
Types of construction works
1. Building construction 2. Roads construction
3. Water Booster P.S and piping, 4. Sewage and storm water P.S and piping.
5. Electrical construction
Measurement of works/Windows
Item Unit Method of measurement
windows No. The exact dimensions should be specified in the design drawings.
Sometimes carpentry works measured in m2 or m length according to the item described
in BOQ.
Dimension
SN Description Unit Quantity length width heigth Unit rate Total amount
Measurement of works / Earth Work
Item Unit Method of measurement
Site leveling Lump It takes into consideration all site leveling including the excavation, fill, till reach
sum 0+B.M according to design drawing.
Excavation m3 Measured by 2 methods :
(cut) 1- footings areas according to blinding area * depth of excavation according to
drawings.
2- external dimensions of the building *depth of footings
Fill (backfill) m3 = excavation – concrete work for footings and columns under ground level.
= ground plan *depth of ground beams – (concrete for ground beams and ground
floors)
Bill of Quantities
The results in the quantities book, are recorded in the BOQ table.
It is preferable to add 5-10% percentage on the quantities for contingency to avoid any
errors or any.
No. Item description Unit Quantity Unit price Total amount
($ or NIS …) ($ or NIS …)
2 CONCRETE WORKS
3- BLOCK WORK
4- CARPENTRY
5- METAL WORK
6- FINISHING WORKS
7- PLUMBING WORKS
8- ELECTRICAL WORKS
9- MISCELLANEOUS
Item description
Based on drawings, specification.
It should be accurate and reflect the drawings and specifications,
Description should include :
1- description of the works
2- unit
3- determine the method of measurement.
Drawings, details
Specifications
1- Earth work
The unit price should include :-
Excavation in any kind of soil, rock, etc., starting at reduced level (bottom of G.B. blinding) down to
bottom of foundation blinding including compacting backfill around foundations and shall be applied on
layers, 200 mm thick, watered and compacted to 95 % (98%) according to modified AASHTO Density Test
T-80.for the excavated foundation and removal of surplus material from site to an approved dumping area
complete as per specifications.
Site Leveling. (Excavation of all Site including External Works). Cut and / or fill in any kind of soil,
concrete, or asphalt; to the required Levels approved by the Engineer (Reduced Level). Including scraping
of top. Any damage to the external walls, fence, etc. should be maintained without any compensations..
Test of the soil (4 points at least), Safety around the site, Work according to engineer instruction and
specifications
Concrete work
Concrete works include:
All formworks and shuttering in any form, shape and size. Making chamfered and curved edges,
allowing for and making grooves and sleeves and the like; removal of forms and cleaning of all
exposed tie wires and rods; making good the harmed surfaces and
Incurred costs on Concrete Mix Designs, Sample taking, testing and providing test results
certificates, storing and saving of samples, and preparation of bar bending schedules and
workshops.
Supplying reinforcement of any grade, size and length as detailed in the drawings, storing on
site including cutting, bending and fixing in position and providing all tying wires, spacers,
shop drawings, testing and bar bending schedules
Concrete work (cont’d)
Painting of exposed surfaces of underground reinforced concrete elements with
slabs.
Steel bars used for alignment and fixing of reinforcement works, and extra steel
Measurement shall be only for the seen surfaces of elements, overlapping and
Supplying and fixing of the required steel reinforcement as per drawings and
specifications.
Block works
Rates of Block works include
All works of the bill shall be of Concrete blocks of high quality standards and as per
specifications.
Vertical and horizontal joints., Cement and mortar, Galvanized angles and ties., Closed end
blocks at all ends, door and window jambs, reveals and the like.
Concrete filling including reinforcing steel to cavities at quoins and door and window
openings.
concrete infill and transporting, placing compacting, curing, surface finishing, protection,
Block works (cont’d)
Block work shall be bonded to concrete columns, wall and the like with concrete infill B250. block must be
stopped in graded shape (10-15 cm from the concrete face) one 8 mm bar must cast in columns during
casting with 40 cm length fixed every 42 cm horizontally, in addition to two vertical 10 mm bars.
Material, workmanship, Galvanized mesh, or plastic mesh, False ceiling from galvanized mesh and
plastering (fixing mesh , covering it by 3-coats of rough plaster)
reinforcement of the joints between different material as the joints between the wall and columns.
Tilling works
Rate shall include preparation of surfaces under tiles, special tile peace’s for edges and the like, tile
surface finishing, Plastic spacers. Pointing and cleaning and all incidental as per specifications.
Supply, Install and Terrazzo Tiles, include, bedding and jointing in cement and sand mortar, pointing
with white cement, required sand fill, and polishing, workmanship, and all incidental as per
specifications
Isolation works for kitchen and bathroom (layer of fiber glass, and bitumen layers)
Marble includes connections, joints, mortar, and any other needed work.
Supply and install a layer of cement and sand under marble and porcelain , ceramic, according to
specification and engineer instruction.
The Contractor rates shall include for supply of all materials, workmanship, samples, surface
preparation , protection of painted surfaces , application to all heights as required of
works, repair of all damaged surface, as per specification.
Sizes of doors and other items mentioned in the Bills of Quantities shall allow for tolerance to
suit the structural openings shown in the Drawings.
Wooden doors and pair of doors shall be measured in square meter for each structural opening,
unless stated otherwise in the Bills of Quantities. Rates for carpentry and joinery work shall
Shop and coordinated drawings.
Plugging concrete, block work, and stone work , and making good.
The contractor intended to order main and final distribution panel boards according to
approved manufacturer drawings.
The contractor should install and construct all works according to drawings , specification
tender documents, and requirement of Electrical Co.
Rates shall include all fittings , fixtures , appliances and pipe laying Supply of material,
workmanship, installation, testing and commissioning.
Rates to include also all peaces and fittings, including by passes , floats, cleaning outlets ,
automatic vents, vents and stack covers, valves and non return valves and the like needed to
complete works as per specifications.
Excavation and cutting for all pipe laying works, bedding back filling and all works connected
with pipe laying.
All ties, sleeves, joints, tie bolts and rods, brackets and the like.
Rates to include Workshops, Coordinated and as- built drawings as approved by the Engineer
Pricing & price analysis
Before construction three types of pricing :
1- cost estimate
2- pricing
3- cost analysis
Preparation of prices
contractor engineer
Insurances
Profit (7-10%)
Productivity of labor
It is necessary to calculate the productivity for the work teams either
worker or technicians / equipments to calculate wages, for workers /
subcontractors.
Estimate the percentage of the specified work from the total project work . (work
item/total work *100%)
Misce. 20
total 420 50
(200$)
Miscellaneous works
1m2 block (40*20*20) = 12.5 block
1m2 tiling (25*25) = 16
1 sack of cement = 1 m2 plastering
1 sack cement = built 100 blocks
Estimation of Concrete price
1 m3 concrete consist of :
350 kg cement
It is important for the contractor as well as for the owner. For the
contractor, he gets the value of works done, and save to him liquidity
for the owner , he become aware of the progress, achieved (actual) and
1- preparation
by contractor
Review and
approved by the
consultant/
supervisor engineer
Types of payment certificates
1- interim payment certificate
2- final statement / final payment certificates
It is request for payment, contains quantity survey for the accomplished works ,
and other supporting details submitted by contractor over the progress period of
the project, .
The amount of each request should not be less than 10% of the contract value or
according to contract conditions
Contents of the payment certificate
1- Financial Payment Certificate: it is a survey of the accomplished works (actual done), multiplied by its
value according to the contract.
2- Measurements :
1- summary, describing the commencement date, project end date, in addition to other data as
contract value, variation order, percentage of the accomplished works, value of the current
payment, and due payment, any amount to be deducted for retention, Percentage of retention
stated in the Contract Data to the total of the above, and Retention Money (if any) stated in the
Contract Data; any amounts to be added and deducted for the advance payment , the deduction
of amounts certified in all previous Payment Certificates.
Payment Certificate
2- total price of the accomplished works, and percentage of the work done
in relation to total project.
It is called the final payment / certificate after the primary taking over the
project.
1- after taking over the project, final request for payment is prepared,
the contractor signed the request for payment and the measurement sheet, and
Copy of the bid submitted from the contractor after considering the prices
Deduction of the works that mentioned in the taking over or any liquidated
damages.
List of measurements
Footing table
F4, C4 F3, C3 F2, C2 F1, C1
Length of steel Bars :
Concrete cover = 5 cm
For F1:
Length of steel in longitudinal direction:
The total length for all steel in longitudinal direction = length of 1 bar *number of bars in the
direction = 1.88*11=20.57 m
Total length for all steel in the short direction = 9 *1.68 = 15.12 m
1 Reinforce
ment steel
for
footings :
F1 Kg Φ12 In long 1.88*11+1 0.888 31.693 4 126.77
direction .68*9 =
= 1.88 35.69 m
In short
direction
= 1.68
For column neck:
C1 = 25*60, 6φ14
For C1 = 25*60
3. It is used for framing the tenders for the works and to check contractor’s work
during and after the its execution for the purpose of making payments to the
contractor.
overall cost.
SITE CONDITIONS AFFECTING THE OVERALL COST (-ctd-)
4 = Good judgment with regard to different localities, different jobs and different workmen.
5 = Selection of a good method for preparing an estimate.
Note conditions of streets leading to railway yards and to material dealers, and
2 = Detailed estimate.
a) Contractor's estimate
b) Engineer's estimate
c) Progress estimate
I = Rough cost estimate
Estimation of cost before construction from plans or architectural drawings
of the project scheme, when even detailed or structural design has not been
carried out, is called Rough cost estimate.
These estimates are used for obtaining Administrative Approval from the
concerning Authorities.
Unit cost is worked out for projects similar to the project under consideration
multiplied with total quantity of the present work in the same units.
For example, in case of a building, plinth area (sq. ft.) of the proposed
building is worked out, which is then multiplied by the cost per unit
area (Rs. /ft2) of similar building actually constructed in the near past in
nearly the same site conditions, to find out the rough cost estimate of
the building.
1. Cost per square foot of covered area (plinth area) is the most
commonly adopted criterion for preparing rough cost estimate for most of
the residential buildings.
2. For public buildings, cost. Per person (cost per capita) is used. For
example,
4. For water tank/reservoir, cost may be worked out on the basis of capacity in
gallons of water stored.
5. For roads and railways, cost may be found out per mile/kilometer of
length.
Calculate the total rough cost estimate and cost per Flat for a multi-storey (4-storeyed) block
The mistakes, if any, in the rough cost estimate are eliminated in the detailed estimate.
Detailed estimates are submitted to the competent authorities for obtaining technical sanction.
The whole project is sub-divided into different items of work or activities. The quantity for each
item is then calculated separately from the drawings as accurately as possible. The procedure is
known as "taking out of quantities".
The quantities for each item may be estimated and shown in the pattern which is called "Bill of
quantities."
The unit, in which each item of the wok is to be calculated, should be according to the prevailing
practice as followed in various departments of the country.
BILL OF QUANTITIES
Description No Measurements Quantity Total Remarks
Sr. No
of item Quantity
Length Breadth Height
At the end, a total of all items of the work are made to get the total estimated
cost.
The rates are usually as per Schedule of Rates for the locality plus a premium to
allow for rise in labor and material rates over and above the schedule of rates.
A percentage, usually 5% is also provided on the total estimated cost for the
work to allow for the possible contingencies due to unforeseen items or
expenditure or other causes, besides 2% establishment charges.
DETAILED ESTIMATE
Besides drawings and details of measurements and calculation of quantities (Bill of
Quantities), the following documents are also usually submitted with the detailed estimate
for obtaining Technical Sanction:
1. A report explaining History, necessity, scope and main features of the project, its design, and
estimate, etc.
2. Specifications lying down the nature and class of work and material to be used in various
parts of the work.
3. The abstract of cost (priced Bill of Quantities) showing the total quantities under each sub-
head, rate per unit of measurement, and cost.
4. Calculation sheets showing calculations for important parts of the structure. In fact, in
estimating the art and skill lies only in the computation of details without any omissions, of
all parts of the building or work.
1- CONTRACTOR ESTIMATE
be bid.
2- ENGINEER’S ESTIMATE
for the purposes of financing the work and for checking bids and
These are made by the Engineer at regular intervals for the completed parts of the
project during the progress of the work for determining the amounts of partial
payments to be made to the contractor.
On large contracts, such estimates are commonly made each month and, hence,
It is likely that a few Items, though unimportant in nature, might have been
overlooked and which may result in raising the estimate of the project.
Hence, a certain allowance usually 5 to 10% of the total cost, is made in the
estimation which will take care of all these items that are unforeseen or are
overlooked and are known as "Contingencies".
METHODS OF DETAILED ESTIMATE
The dimensions, length, breadth and height or depth are to be taken out from
Junctions of walls, corners and the meeting points of walls require special
attention.
The walls running in one direction are termed as "long walls” and the walls
running in the transverse direction, as "Short waLls", without keeping in mind
which wall is lesser in length and which wall is greater in length.
Lengths of long walls are measured or found "Out-to out" and those of short
walls as "In-to-in".
Different quantities are calculated by multiplying the length by the breadth and
the height of the wall.
For symmetrical footing on either side, the center line remains same for
super structure, foundation and plinth. So, the simple method is to find
out the centre-to-centre lengths of long walls and short walls from the
plan.
For the length of the first footing or first step of the brick wall, subtract
two offsets (2x6"=12") in foundation concrete from the length of the
trench or concrete.
For the second footing subtract from the length of the 1st
footing two offsets (2x2.25"= 4.5"), for 3rd footing subtract
from the length of the 2nd footing 2 offsets (4.5") and in
this way deal with the long walls up to the super-structure.
Foundation
Trench
CENTRE LINE METHOD
In this method, total length of Centre lines of walls, long and short, has to be
found out.
Find the total length of Centre lines of walls of same type, having same type of
foundations and footings and then find the quantities by multiplying the total
centre length by the respective breadth and the height.
In this method, the length will remain the same for excavation in foundations,
for concrete in foundations, for all footings, and for superstructure (with slight
difference when there are cross walls or number of junctions).
This method is quicker but requires special attention and considerations at the
junctions, meeting points of partition or cross walls.
CENTRE LINE METHOD
For rectangular, circular polygonal (hexagonal, octagonal etc)
buildings having no inter or cross walls, this method is quite
simple.
Thus in the case of a building with one partition wall or cross wall
having two junctions, deduct one breadth of the respective item of
work from the total centre length.
CENTRE LINE METHOD
For buildings having different types of walls, each set of walls shall have to be dealt
separately.
Find the total centre length of all walls of one type and proceed in the same manner as
described above. Similarly find the total centre length of walls of second type and deal this
separately, and so on.
Suppose the outer walls (main walls) are of A type and inner cross walls are of B type.
Then all A type walls shall be taken jointly first, and then all B type walls shall be taken
together separately.
In such cases, no deduction of any kind need be made for A type walls, but when B type
walls are taken, for each junction deduction of half breadth of A type walls (main Walls)
shall have to be made from the total centre length of B type walls.
CENTRE LINE METHOD