Colapse of PSC Girder - JPanda
Colapse of PSC Girder - JPanda
Er.Jagdish Panda
Ex.-Engineer-in-Chief Cum
Secretary Works Department, Orissa.
Introduction
• Existing Bridge - @ 284/0 Km of NH-5
• Second River Bridge - @ 30m D/S of Existing Bridge under NHDP connecting Chennai to
Kolkata
• Structural Components :
(a) 3-lane bridge
(b) Well foundation
(c) PSC superstructure with 5 Beams of size 0.8m width (Bottom) and 1.2m width (at Top);
(d) Depth of the Girder = 3.275m (including Slab)
(e) Length of the Girder = 48.77m
(f) No of Span = 11
142.0
1200
500 1500 500 11250 500
200 225 THK. IN-SITU
DECK SLAB IN M30
1100
WEARING COAT
2.5% 1200 UNIFORM 62 THK 3 200
1100
450
2.5 %
200
250
5 250
3275
2 325
325
2825
IN-SIDE
DIAPHARAM
3.275
4
250
1 200
250
800
200 800
PSC GRADE
ALL DIMENSIONS ARE IN MM
.
Incidence of Collapse
3- Concrete core samples- three sets, each set having three numbers
6- Few blocks of concrete which have come out of girders and piers
Steel Reinforcing Bars- 8mm, 10mm and 12 mm HYSD bars from Collapsed
girder taken
• NHAI provided NDT results conducted by M/s S.M. Consultants. Also conducted Ultra
sonic Pulse velocity Test and Rebound Hammer Tests on pier Caps of Pier No # P8 and
P9.
• Compressive strength by Rebound Hammer found >/= 32 Mpa (-/+ 25 % by IS:13311
(part-2) which is not indicate presence of internal micro-cracking,flaws,heterogeneity
across the cross-section.
• Actual value of Pulse Velocity is a function of no. of parameters , hence assessment of
quality of concrete was satisfactory to a general extent only.
Table 2 : Test results of cores taken from the collapsed PSC girders
Steel Reinforcement :
Table3 :Test results of steel bars taken from the collapsed PSC girders
Sl. Mass Cross- 0.2% 0.2% Ultimate Ultimate
• Stipulated IS:1786-1995 Requirement of No. (kg/m) section Proof Proof tensile tensile
al area stress stress strength strength Elongation
0.2% Proof Stress = 415 Mpa O.K.
(mm2) (N/mm)2 (average) (N/mm)2 (average)
(N/mm)2 N/mm)2
• Ultimate tensile strength = 10% more than A- Diameter : 8 mm
0.2% proof stress ( Not Less than 485 8/1 0.417 53.12 440 544 15.00%
Mpa) O.K. 8/2 0.403 51.34 449 451 556 550.33 20.00%
8/3 0.404 51.46 466 551 16.25%
• Elongation of 8mm,10mm and 12 mm size B- Diameter : 10 mm
Bars found in the collapsed girder was 10/1 0.642 81.78 445 631 16.94%
more than required 14.5%; which was O.K. 10/2 0.641 81.66 474 435.33 639 603.67 16.13%
in the view point of ductility requirement of 10/3 0.727 92.61 387 541 17.14%
steel.
C- Diameter : 12 mm
12/1 0.917 116.8 435 532 23.33%
12/2 0.916 116.7 429 434.67 533 538.67 25.00%
12/3 0.919 117.1 440 551 24.17%
INFERENCE OF I.I.T. AFTER INVESTIGATION
Bearings:
Shrinkage Strains :
• Prestressing was done either on 10th/11th day, it is not clear whether the
shrinkage of concrete was fully completed at that time.
INFERENCE OF I.I.T. AFTER INVESTIGATION
Thunderstorms:
• On June 26th, 2008 between 15:50-16:00 Hrs, a strong wind blew from sea
side which swirled around PSC girder.
• During this Storm, 3 completed Girders and 1 under-construction girder
affected.
• Weather Report of Gopalpur says : Wind Speed =8 KMPH @ 8:30 Hrs &
14KMPH @ 17:30 Hrs. No wind speed measured available at 15:20 Hrs to
16:45 Hrs.
• Girder may failed due to any one reason due to wind:
• The wind blow was very short in duration but severe in nature and could not be captured by
the satellite imagery of the particular place. Water level in the river bed also rose up due to
suction effect.
• Had not the new bridge been located with a gap of 22 m D/s only (girder to girder) from the
old bridge the wind with a speed of 102.538 Km/hr would not have swirled in between the two
bridges and oblique venturian flow would not have occurred and hit the first cast girder of the
new bridge.
• As such the girder would not have slanted against the second and the second unto the third
resulting in collapse of the girder. The wind would have travelled to the upstream of the river.
• This further corroborates the fact that the two girders between Pier No. 7 & 8 cast exactly
under similar conditions prior to 21.06.2008 after first stage of prestressing which is nearer to
the centre of the river (more exposed to sea front) without cross bracing stood in tact after
this collapse and still standing to the test of time.
For Details, Please Contact:
Mobile No: 9438663174