Performance Chapter 3
Performance Chapter 3
2
Time related Performance management
Project planning
Planning aims at formulation of a time-based plan of action for
coordinating various activities and resources to achieve specified
objectives.
Planning is the process of developing the project plan. The plan
outlines how the project is to be directed to achieve the assigned goals.
It specifies a predetermined and committed future course of action,
based on discussions and decisions made on the current knowledge and
estimation of future trends.
3
Types of project plans
Planning the entire project from its inception to completion
requires a vast coverage, varied skills, and different types of
plans. The nature of plan encountered in a typical construction
projects are;
Project plan
4
• Planning follows a systematic approach. Various planning techniques are
employed to systematize and transform the mental thought process into a
concrete project plan.
Project Planning Process
Planning data collection Where to look for data? Studying the relevant documents
Planning time What is to be done? Define scope of the work
What are the activities involved? Breakdown project into activities
How it can be done? Developing network plans
When it is to be done? Scheduling work
Where it is to be done? Charting site layout
5
3.1 Project Time Management
6
Contd…
• These work tasks represent the necessary framework to permit
scheduling of construction activities, along with estimating the
resources required by the individual work tasks, and any necessary
precedence's or required sequence among the tasks.
• Execution of an activity requires time and resources, including
manpower and equipment.
• The time required to perform an activity is called the duration of
the activity.
• The beginning and the end of activities are signposts or milestones,
indicating the progress of the project.
7
B. Defining Precedence Relationships among Activities
• Once work activities have been defined, the
relationships among the activities can be specified.
• Numerous natural sequences exist for construction
activities due to requirements for structural integrity,
regulations, and other technical requirements.
• Diagrammatically, precedence relationships can be
illustrated by a network or graph in which the
activities are represented by arrows.
8
Example : Precedence Definition for Site Preparation and Foundation Work
9
TABLE: Precedence Relations for a Nine-Activity Project Example
10
Contd…
• With the previous information, the next problem is to represent
the activities in a network diagram and to determine all the
precedence relationships among the activities.
• The following diagrams show the representation of the
activities on arrow.
11
Activity-on-Branch Representation of a Nine Activity Project
C. Estimating Activity Duration
12
Contd…
13
Contd…
• Simply put, the time required (T) to complete an
activity can be calculated using the following
relationship, provided care is taken to ensure
proper units for all the quantities.
• T = Q / (RxP)
• For example, the time taken to paint 100 m2 (Q)
using 2 painters (R) and assuming each painter
can do 5 m2 in an hour (P), is simply 10 hours (T).
14
D. Fundamental Scheduling Procedures
Scheduling means putting the plan on a calendar time scale.
• In addition to assigning dates to project activities, project
scheduling is intended to match the resources of equipment,
materials and labor with project work tasks over time.
• Good scheduling:
– facilitate the timely procurement of necessary resources.
– Insure the completion of a project as soon as possible.
– can eliminate problems due to production bottlenecks
15
• Poor scheduling can result in considerable waste as
laborers and equipment wait for the availability of
needed resources or the completion of preceding
tasks.
17
Schedule control process
18
Inputs to Schedule Control
• Project schedule:
– The approved project schedule, called the schedule baseline
(which must be feasible technically and in terms of resources),
– provides the basis for measuring and reporting schedule
performance
• Performance reports:
– It provides information on schedule performance, such as
which planned dates have been met and which have not.
• Change requests:
– Changes may require extending the schedule or may allow
accelerating it.
19
Tools and Techniques for Schedule Control
20
Outputs from Schedule Control
• Schedule updates:
– A schedule update is any modification to the schedule
information that is used to manage the project.
– Schedule updates may or may not require adjustments to
other aspects of the project plan.
– Revisions are a special category of schedule updates.
– Revisions are changes to the schedule start and finish
dates in the approved project schedule.
21
• Corrective action:
– Corrective action is anything done to bring expected
future schedule performance in line with the project
plan.
– Corrective action in the area of time management
often involves expediting: special actions taken to
ensure completion of an activity on time or with the
least possible delay.
• Lessons learned:
– The causes of variances, the reasoning behind the
corrective action chosen, and other types of lessons
learned from schedule control should be documented.
22
Generally the project time control aims at timely execution of work as per
the work program and applications of corrective measures in case of
deviations.
The time control process involves the monitoring of time status by
updating the project network and time schedules,
reviewing durations of balance activities,
computing deviations and evaluating the implication of deviations on
project time objective by time-analyzing the project network.
It includes formulating remedial measures including what-if analysis,
time crashing, re-planning, re-forecasting and re-mobilizing resources
under changed situations with a view to accomplish the time objective
23
ha nk
T
yo u