Prince2 Practitioner
Prince2 Practitioner
Practitioner
2017 Version
The PRINCE2 Accredited TrainingThe PRINCE2 Accredited Training Organization logo is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PRINCE2® is a
registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.
HOUSEKEEPING
• Fire exits
• Toilets
• Breaks
PRINCE2 Practitioner – Course agenda
Day 1 Day 2 Day3
• Introductions • Themes: • PRINCE2 processes
• PRINCE2 recap • Change • SB
• P2P exam technique • Progress • CP
• Principles • PRINCE2 processes • Personal revision
• Tailoring • SU • Practitioner exam
• Themes: • DP
• Business case • IP
• Organization • CS
• Quality • MP
• Plan
• Risk
PRINCE2
PRACTITIONER EXAM
The practitioner examination is to
PRINCE2 assess whether the candidate can
Practitioner demonstrate sufficient ability to
examination apply and tailor the PRINCE2
project management method.
Exam content:
• Principles
• Themes
• Processes
PRINCE2 Practitioner examination
Key Features: Standard multiple choice The exam will be begin at 1pm
• 68 multiple choice • 35 questions on Day 3:
questions Register via the
• 4 options - 1 correct answer
• Based on a 2 page PeopleCert.org website
scenario
Use the links emailed or
• 150 minutes Matching
provided by your instructor
• Pass mark – 38 marks • 11 x 3 question items
Foundation certificate (or
(about 55%) • Link items from a list to responses similar) must be uploaded
• Open book - Managing in a second list before official results released
Successful Projects with
PRINCE2
• 1 correct response for each
question item
• Responses may be used more than
once
Flag question for later Completed question (turns orange) Timer/clock
Previous question Next question
Current question
QUESTION
Number of
questions
Scenario
Additional Info
Click to expand Scenario Selected answer Scenario + Additional
+ Additional Info (turns orange) Possible answers Info in a pop-up
window
Matching Question
Practitioner Exam Title here
QUESTION INSTRUCTIONS
QUESTION 1
QUESTION 1
QUESTION 2
QUESTION 3
Text in quotes is taken directly from AXELOS PRINCE2® 2017 material. Other text is based on AXELOS PRINCE2® material. Material is
reproduced under licence from AXELOS. All rights reserved.
Tailoring
Text in quotes is taken directly from AXELOS PRINCE2® 2017 material. Other text is based on AXELOS PRINCE2® material. Material is
reproduced under licence from AXELOS. All rights reserved.
Purpose
PRODUCT Composition
DESCRIPTION Derivation
• Agile:
• Benefits tolerance
• Incremental delivery
Activity 1:
Business Case
Management
Complete the ‘Business Case’ activity on the
Learner Workbook.
Sample exam Q&A #1
• Principles
• Business case
• Questions 1-13
• See workbook guidance
7: ORGANIZATION
7.2 Management
products
“Sets out the project management team structure and “Describes the means and frequency of
roles.” communication to stakeholders both internal and
external to the project.”
A.5 Procedure
Communication Techniques
management Records
approach
Reporting
Timing
Roles
7.2 Project
management
team roles
7.3 Scaling the “Roles can be combined but
project should not be eliminated.”
management
team structure • Executive
• Senior User
• Project Manager
• Team Manager
7.3.7 Creating
an effective
project board Authority Credibility
Ability to Availability
delegate
Activity 2:
Designing The Project
Management Team
• Organization
• Quality
• Questions 14-23
• See workbook guidance
9: PLANS
9.1.2 Types of Corporate, programme or customer’s plan
High-level
plan
Project plan
Detailed
As necessary
Team plans Optional
A.16 Plan •
•
Description
Prerequisites
• External dependencies
• Planning assumptions
• Delivery approach(es)
• Lessons incorporated
• Monitoring and control
• Budgets
• Tolerances
• Product descriptions
• Schedule
9.3 Approach to
planning
9.3.1.2 Write project product description Project plan only
Defining and
analysing the Create product breakdown structure
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
9.3.1.2 Product flow diagram
• Defines the sequence of
development
• Identifies dependencies
between products
• Involve team in creating the
PFD
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
Activities 4&5:
Plans
3
10.3 Guidance •
•
Alignment with policies
Risk management procedure
for effective • Understand the Project Board’s attitude to risk
management • Project size, scale and complexity, and risk impact
• Project delivery approach
• Commercial considerations
• Risk budget
10.4.1.1
Risk context Quality Organizations
expectations
Risk context
Corporate
Assumptions policies
Activities 6&7:
Risk
Complete both the ‘Risk’ activities on the
Learner Workbook.
Exercise 10: Risk responses - answer
Risk response T/O Type
An alternative producer is on stand-by if the external producer maintains his reputation for Threat
Contingency
turning up late, if at all
The recently refurbished recording studio will provide further studio-time and resources free of Threat Transfer
charge if technical issues delay the recording
Sales should be higher now that a well-known artist has agreed to cameo in a promotional video Opp Enhance
about the making of the album
The album will not be released on download as the record company does not have suitable Threat
Avoid
copyright infringement protection which may lead to illegal downloads
Cost savings may be possible if the graphic design company will provide services 'at cost' in Opp Share
return for a small percentage of the sales revenue
Sample exam Q&A #3
• Plans
• Risk
• Questions 24-33
• See workbook guidance
11: CHANGE
11. Management products
A.3 Change control approach A.12 Issue register A.13 Issue report Note:
• Change control procedure • Identifier • Identifier No formal PRINCE2
definition for:
• Issue management • Type • Type
procedure • A.6 Configuration
• Date raised • Date raised
item record
• Tools and techniques • Raised by • Raised by • A18 Product status
• Records • Issue report author • Issue report author account
• Reporting • Description • Description
• Timing • Priority • Impact analysis
• Responsibilities • Severity • Recommendation
• Scales (priority/severity) • Status • Priority
• Closure date • Severity
• Decision
• Closure date
11.3 Effective
change control
• Tailoring – programme or customer requirements
• Project size, scale and complexity
• Managing product baselines (document and
configuration management)
• Delivery approach
• Delegated Change Authority
• Change budget
11.4 Change control procedure
Project Board/Change Authority
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
Activity 8&9:
Change
Other
• A.7 Daily log
• A.14 Lessons log
• A.26 Work package
12.2.1 Tolerances
Types of tolerances:
Corporate, programme management or customer
Work package
Work package
tolerances
progress/issues
Team Manager
Activity 10:
Progress
Complete the ‘Progress’ activity on the Learner
Workbook.
12.2.3 Raising Review progress
Stage exceptions:
Project Manager - Exception report (Exception Plan)
• Change
• Progress
• Questions 34-43
• See workbook guidance
13. PRINCE2
PROCESSES
13.1
The PRINCE2
journey
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
13.3 Process structure
Purpose
Objective
Context
Activities
• Inputs/outputs
• Responsibilities
Tailoring guidelines
13.4 Tailoring the processes
• Reflect the organization’s method
(supplier or client)
• Combine activities
• Split activities
• Reassign roles
• Combine, split or amend management
products
• Add more activities
14. STARTING UP A
PROJECT PROCESS
14.3 Process
overview
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
14.3 Activities
Daily log
Structure and
role
Lessons log descriptions
Project product
description
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
A.19 Project brief
• Project definition Project definition:
• Outline business case • Background
• Project product description • Objectives
• Project approach • Desired outcomes
• Project management team • Scope and exclusions
structure • Constraints and assumptions
• Role descriptions • Project tolerances
• References • User(s) and other parties
• interfaces
Activity Producer
14. Primary Appoint the Executive Corporate/
Simple Agile
projects approach
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
15. Primary Activity
Authorize initiation
Approver
Project Board
responsibilities Authorize the project Project Board
Corp/Pgm
Authorize a stage or exception plan Project Board
Give ad hoc direction (responsible) Project Board
Authorize project closure Project Board
Simple Agile
projects delivery
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
16.3 Activities – Initiating a project
Agree tailoring requirements Create the issue
register
Create the quality register
Create the risk Prepare risk management Prepare quality management Prepare change control approach
register approach
approach
Prepare communication
management approach And product
Such as project tolerances, stage
boundaries, reporting, updated team descriptions, using
roles product based
planning
Set up project controls Create project plan
Project Manager
(Records and logs maintained by Project Support)
A.20 Project initiation documentation (PID)
• Project definition
• Project approach
• Business case
Approaches
• PM team structure and role
• Quality
descriptions
• Change control
• Management approaches
• Risk
• Project plan
• Communication
• Project controls
• Tailoring of PRINCE2
16.4.2-5 • Risk
Defining the How
• Change control
• Quality
approaches • Communication
16.4.6 Project controls
• Communications
• Management stages
• Issues and changes
• Tolerances and escalation
• Delegated authority
• Monitoring
“At such an early stage in the project, there may not
be enough information; tailoring needs will emerge
16.5 Tailoring as the initiation work progresses … start simple and
guidelines then elaborate if needed.”
Simple Agile
projects delivery
• Starting up a project
• Directing a project
• Initiating a project
• Questions 44-55
• See workbook guidance
17. CONTROLLING A
STAGE PROCESS
17.3 Process
overview
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
17.3 Activities – Controlling a stage
In a regular
highlight
Using an exception Escalate issues and report
report Report highlights
risks
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
• Date
• Team manager/individual
A.26 • WP description
Work package •
•
Techniques, processes, procedures
Development interfaces
• Operations interfaces
• Change control requirements
• Joint agreements
• Tolerances
• Constraints
• Reporting
• Problems/escalation
• Extracts or references
• Approval method
“Central to the ultimate success of a project is the
17.5 Tailoring day-to-day control of the work that is being
conducted.”
guidelines
Simple Agile
projects delivery
Agree the
work package
Simple Agile
projects delivery
• Questions 56-62
• See workbook guidance
19. MANAGING A
STAGE BOUNDARY
PROCESS
19.3 Process
overview
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
Activities Update benefits
management
approach
Create an
exception
Report plan
management stage Update business Produce exception
end case plan
Plan next
Create product
management stage descriptions
104
Provide the project board with sufficient
information to:
• Review current • Review updated plan
19.5 Tailoring • Confirm continued
stage
guidelines • Approve next stage business justification
Simple Agile
projects delivery
Copyright © AXELOS Limited 2017. Reproduced under licence from AXELOS Limited. All rights reserved.
20.3 Activities Obtain acceptance
record
108
A.8 End project report
• PM report
• Review of business case
• Review of project objectives
• Review of team performance
• Review of products Products Review
• Lessons • Quality records
• Approval records
• Off-specifications
• Project product handover
• Summary of follow-on action
recommendations
“Provide a fixed point at which acceptance for the
20.5 Tailoring project product is confirmed … objectives set out in
guidelines the PID have been achieved, or the project has
nothing more to contribute.”
Simple Agile
projects delivery
• Questions 63-68
• See workbook guidance
PRINCE2
PRACTITIONER
EXAM
Paper based exam tips
• Read Scenario (10 mins max)
• Annotate scenario & question paper
• Read question carefully
• Read 4 possible answers (d, c, b, a)
• Eliminate obvious incorrect answers
• Select correct answer – mark for review if
necessary
• Take care when changing answers
• Manage time (2 mins per mark)
• Return answer sheet and question paper
Digital exam tips
• Have a blank sheet of paper to write notes on
• Read the scenario (10 mins max)
• Allow 2 mins per question
• Read each question carefully
• Read 4 possible answers (d, c, b, a)
• Eliminate obvious incorrect answers
• Select correct answer – mark for review if
necessary
• Take care when changing answers
• Use navigation tools to review questions
before ending the exam
PRINCE2® Practitioner
2017 Version
The PRINCE2 Accredited TrainingThe PRINCE2 Accredited Training Organization logo is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. PRINCE2® is a
registered trade mark of AXELOS Limited, used under permission of AXELOS Limited. The Swirl logo™ is a trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.