Rajat Mishra Asst. Professor Civil Engineering Department
Rajat Mishra Asst. Professor Civil Engineering Department
Rajat Mishra
Asst. Professor
Civil Engineering Department
3.3.1 Introduction: The sprinkler system is ideal
in areas where water is scarce.
A Sprinkler system conveys water through pipes
and applies it with a minimum amount of losses.
Water is applied in form of sprays sometimes
simulating natural rainfall.
The difference is that this rainfall can be controlled
in duration and intensity.
If well planned, designed and operated, it can be
used in sloping land to reduce erosion where other
systems are not possible.
Components of a Sprinkler Irrigation
System
Types of Conventional Sprinkler Systems
a) Fully portable system: The laterals, mains,
sub-mains and the pumping plant are all portable.
The system is designed to be moved from one
field to another or other pumping sites that are in
the same field.
b) Semi-portable system: Water source and
pumping plant are fixed in locations.
Other components can be moved.
The system cannot be moved from field to field or
from farm to farm except when more than one fixed
pumping plant is used.
c) Fully permanent system: Permanent laterals,
mains, sub-mains as well as fixed pumping plant.
Sometimes laterals and mainlines may be buried.
The sprinkler may be permanently located or moved
along the lateral.
Itcan be used on permanent irrigation fields and for
relatively high value crops e.g. Orchards and
vineyards.
Labour savings throughout the life of the system may
later offset high installation cost.
Design of Sprinkler Irrigation System
Fine Sand 12 to 25
Sandy Loam 12
Silt Loam 10
Clay Loam/Clay 5 to 8
Effects of Wind
In case of Wind:
Reduce the spacing between Sprinklers:
See table 6 in Text.
Allign Sprinkler Laterals across
prevailing wind directions
Build Extra Capacity
Select Rotary Sprinklers with a low
trajectory angle.
System Layout
Layout is determined by the Physical Features of
the Site e.g. Field Shape and Size, Obstacles, and
topography and the type of Equipment chosen.
Where there are several possibilities of preparing
the layout, a cost criteria can be applied to the
alternatives.
Laterals should be as long as site dimensions,
pressure and pipe diameter restrictions will allow.
Laterals
of 75 mm to 100 mm diameter can easily
be moved.
Etc. - See text for other considerations
Pipework Design
0.2 Pa PeL
Pf for laterals laid uphill
F
0.2 Pa PeL
Pf for laterals laid downhill
F
Pressure at Head of Lateral
The Pressure requirements (PL)where the Lateral joins the
Mainline or Submain are determined as follows:
PL = Pa + 0.75 Pf + Pr For laterals laid on Flat land
PL = Pa + 0.75 (Pf Pe) + Pr For Laterals on gradient.
The factor 0.75 is to provide for average operating pressure
(Pa) at the centre of the Lateral rather than at the distal end.
Pr is the height of the riser.
Diagram of Pressure at Head of Lateral
Selecting Pipe Sizes of Submains and MainLines