Gravity Dam
Gravity Dam
CONTENTS
INTRODUCTION
HISTORY OF DAM
GRAVITY DAM
SITE SELECTION OF GRAVITY DAM
MERITS AND DEMERITS OF GRAVITY DAM
FORCES ACTING ON GRAVITY DAM
CAUSES OF FAILURE OF GRAVITY DAM
PRECAUTIONS AGAINST FAILURE
REFERENCES
CONCLUSION
INTRODUCTION
A Dam is a hydraulic structure constructed across a river or a stream to retain
the water on its upstream side.
It is suitable in hilly region where a deep gorge section available for
the storage reservoir.
B.C.
Romans used concrete and mortars around 100 AD.
Due to large size and amount of building material need to
MERITS;
Maintenance of gravity is less.
Spillway can be provided in the body of the dam itself.
Section can be made thinner to economize in cost.
If the good foundations are available this dams can be
constructed to greater height.
DEMERITS;
Initial cost is high.
Time is more for construction.
It requires elaborate construction plant, skilled labour.
FORCES ACTING ON GRAVITY DAM
1. Water pressure
2. Weight of the dam
3. Uplift pressure
4. Silt pressure
5. Wind pressure
6. Wave pressure
7. Ice pressure
WATER PRESSURE
WIND PRESSURE
It generally not considered while designing section of dam,
but if area exposed to wind then it may be taken as
100kg/m^2 or 150kg/m^2
WAVE PRESSURE
Waves are generated on the
surface of the reservoir by the
blowing winds, which cause
pressure towards the downstream
side.
Waves pressure depends upon the
wave height.
Pw = 2.4 γw . Hw
It acts at hw/2 above the still water
surface.
ICE PRESSURE
▶ The ice may be formed on the water surface of the
reservoir in cold countries, may sometimes melt and
expand.
▶ The dam face has to resist the thrust exerted by the
expending ice.
▶ The magnitude of this force varies from 250 to 1500
KN/m2 depending upon the temperature variations.
CAUSES OF FAILURE OF DAM
1. BY OVER TURNING:
The solid gravity dam may fail may fail by overturning at its toe when the
total horizontal force acting on the dam greater than the vertical force.
2. BY SLIDING:
The total horizontal force acting on a dam tend to slide the entire dam
its base or along any horizontal section of the dam.
3. BY OVER STRESSING:
If the permissible working compressive stress of concrete or masonry
exceeds due to some adverse condition, then the dam may fail by crushing
due to overstressing of the concrete or masonry.
4. BY CRACKING:
Due to some reasons, the tension is developed in the dam section, crack
will form in the body of the dam and ultimately this will cause the failure of
the dam.
PRECAUTION AGAINST FAILURE
1. To avoid over turning, the resultant of all forces acting on the dam
should
dam.
remain with in the middle-third of the base of the width
2. In the dam, the sliding should be fully resisted when condition for
no sliding exist in the dam section.
condition for no sliding is given by tan
P= Total horizontal force Total vertical force
3. In the dam section, the compressive stresses of concrete or
masonry should not exceed the permissible working stress to avoid
failure due to crushing.
4. There should be no tension in the dam section to avoid the
formation cracks. This condition may be achieved by middle-third
rule. The factor of safety considered 4 to 5.
CONCLUSION
Compare to the any other dams the gravity life
span is long.
The maintenance cost is less.
Gravity dams are used for the multi purpose
better than the any other.
Compare to earthen dam, in the gravity dam
spillway are provided at the full supply level to
allow the surplus water from upstream to the
downstream.
THANK YOU