0% found this document useful (0 votes)
194 views

Lecture 19-Selection, Installation & Commissioning

The document discusses the selection, installation, testing, and commissioning of instruments for an industrial plant. It covers considerations for selecting reliable instruments, installing them properly, testing piping and wiring, and finally commissioning the overall system. The goal is to have instruments and controls that safely and reliably meet the plant's operational requirements.

Uploaded by

Abdul Rehman
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
194 views

Lecture 19-Selection, Installation & Commissioning

The document discusses the selection, installation, testing, and commissioning of instruments for an industrial plant. It covers considerations for selecting reliable instruments, installing them properly, testing piping and wiring, and finally commissioning the overall system. The goal is to have instruments and controls that safely and reliably meet the plant's operational requirements.

Uploaded by

Abdul Rehman
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 29

Selection, Installation &

Commissioning of
Instruments
2

Contents
• Need for instrumentation
• Selection of Instruments
• Installation
• Testing and pre-Commissioning
• Commissioning
3

Need for Instrumentation


The primary objectives of instrumentation and
control schemes are:

1. Safe plant operation & long-term


reliability
2. Product quality & Production rate
3. Cost
Selection of Instruments
1. Considerations
2. Reliability of measurement
system
3. Total life-time operating cost
5

1. Considerations:
• Process requirements
• Operators’ requirement
• Benefits to the plant from the proposed
instrumentation and control
• The way in which operator would like to interact
with plant process measurement, control and
monitoring instruments
• The location and environment of the control
room with respect to the plant process
6

• The working culture of the operator and


maintenance staff and their level of awareness
• The existing maintenance facilities and
availability of test equipment
• The cost of instruments in terms of return-on-
investment (ROI) to the plant
• Time required to complete the installation
• Any preferred existing make (which is working
satisfactorily) by the plant maintenance
engineers to reduce inventory on spaces
7

2. Reliability of Measurement system:

• Reliability:
▫ The probability that the system will operate to an
agreed level of performance for specified period,
subject to specified environmental conditions.
 The agreed level of performance means an accuracy of
±1.5%.
 If the system is giving a measurement error outside
these limits, then it is considered to have failed, even
though it is otherwise working normally.
▫ A measurement system that has just been checked
and calibrated should have a reliability of 1 when first
placed in service
8

• Unreliability:
▫ The probability that the system will fail to operate
to an agreed level of performance, for a specified
period, subject to specified environmental
conditions.
▫ A system that has just been checked and
calibrated should have an unreliability of zero,
when placed first in service.
9

• Element selection:
▫ Only elements or systems with well-established
failure rate data/models should be used.
• Environment:
▫ The environment in which the element (or system)
is to be located must first be defined.
▫ The system should consist of components which
can withstand that environment.
• Minimum complexity:
▫ The number of elements in the system should be
the minimum required for the system to perform
its function.
10

• Diversity:
▫ Faults can occur which either cause more than one
element in each system, or a given element in each of
the several identical systems, to fail simultaneously,
this is referred to as “common mode failure”.
▫ To avoid this problem, a given function is carried out
by two systems in parallel, but each system is made
of different elements with different operating
principles.
• Maintenance:
▫ Mean down time should be as small as possible in
order to minimize the financial loss caused by the
element being out of action
11

3. Total lifetime operating cost:


Total lifetime operating cost (TLOC) of a measurement
system is the total cost penalty, incurred by the user,
during the lifetime of the system.

TLOC = Initial cost of the system (purchase, delivery


and commissioning)
+ cost of failures and maintenance over lifetime of the
system
+ cost of measurement error over lifetime of the system

 The best system is one with the minimum TLOC.


Installation
13

Considerations:
• Storage and protection:
▫ Unpacking
▫ Minimize handling
▫ Suitable covering
▫ Air-conditioning
▫ Prevention from mechanical abuse
• Mounting and Accessibility:
▫ Vertically plumbed
▫ Accessible for observation and maintenance
▫ As close as possible to the process taping points
▫ Corrosion prevention  Covering and painting
14

• Instrument piping system:


▫ As short in length as possible
▫ Clearance for access
▫ Avoid hot environment or potential fire-risk areas
▫ Minimum number of joints
▫ Adequate support to avoid vibrations

• Air Supplies:
▫ Clean, dry and oil-free
▫ Properly sized
▫ Self-draining and should have drainage/blow off
facilities
15

• Pneumatic signals:
▫ PVC outer sheath should be provided to copper tubing
▫ Should be run on a cable tray for its entire length

• Impulse lines:
“The impulse lines contain process fluids which run
between the instrument connection and the process
tapping point”

 Should be as short as possible


 Self-draining and self-venting
 Vent plugs/valves and drain plugs/valves be used
 Provision for isolation and de-pressurizing of system
and instrument for maintenance
16

• Cable types:
▫ Solid conductors should be used to avoid
degradation of signals
▫ Mechanical protection
▫ PVC outer sheath (on open cable trays)
▫ Lead sheath (below ground in sand-filled
trenches)
17

• Cabling and cable routes:


▫ As short as possible
▫ Should not cause any obstruction for access
▫ Avoid hot environment and potential fire-risk
areas
▫ Avoid areas where there is spillage or escaping
vapors/gases
▫ Should be supported the entire length
▫ Avoid cable joints
▫ Cables should be properly earthed
18

• Cable segregation:
▫ Only signals of same type should be contained
within any one multi-core cable
▫ Cables for high-intensity systems such as
emergency shutdown systems should take totally
independent routes or should be positively
segregated from other cables
▫ Instrument cables should be run well clear of
electrical power cables and should also, as far as
possible, avoid noise generating equipment like
motors.
Testing
&
Pre-Commissioning
• Pre-Installation testing
• Piping and cable testing
• Loop testing (pre-commissioning)
20

Pre-Installation Testing
• Testing of each instrument for correct calibration and
operation prior to its being installed in the field.

• Test instrument should have a standard of accuracy


better than the manufacturer’s stated accuracy for
the instruments being tested and should be regularly
classified.

• Instruments should be checked at five points, i.e. 0%,


25%, 50%, 75% and 100% for both rising and falling
signals.
21

• After testing, the instruments should be drained of any


testing fluids and blown through with dry, clean air.

• Electronic instruments should be energized for 24-


hour warm-up period prior to calibration test.

• Control valve should be tested in situ after the pipe-


work fabrication has been finished.

• Control valves should be checked for correct stroking at


0%, 50% and 100% open and close.
22

Piping & Cable Testing

• All air lines (pneumatic lines) should be blown


through with clean, dry air prior to final
connection to instruments and they should also
be pressure tested for a timed interval to ensure
that they are leak-free.

• The testing should be done in the form of a


continuity test from the field end to its
destination (e.g., the control room)
23

• Impulse lines (process piping) should also be


flushed thoroughly and hydrostatically tested
prior to connection of the instruments.

• All isolation valves should be checked for tight


shut-off.

• On completion of the hydrostatic tests, all piping


should be drained and thoroughly dried out
prior to reconnecting to any instruments.
24

• All instrument cables should be checked for


continuity and isolation.

• Where cables are installed below ground, testing


should be carried out before the trenches are
back filled.

• As a pre-requisite to cable testing, it should be


ensured that all cables and cables ends are
properly identified.
25

Loop Testing
• The purpose of loop testing is to ensure that all
components in a loop are in full operational order when
interconnected and are in a steady state for plant
commissioning

• Alarms and shutdown systems must also be


systematically tested. All systems should be checked for
fail-safe operation

• All ancillary work should be completed, such as setting


zeros, filling liquid seals, and fitting of accessories such as
charts, inks, etc.
Plant Commissioning
27

• Commissioning is the bringing on-stream of a


process and the tuning of all instruments and
controls to suit the process operational
requirements

• A plant, or section there of is considered to be


ready for commissioning when all instrument
installations are mechanically complete and all
testing, including loop testing, have been
conducted.
28

Considerations
• Air supplies are available and that all power
supplies are fully functional, including any
emergency standby supplies

• Ancillary devices are operational, such as


protective heating systems, air conditioning, etc.

• Control valve lubricators (when fitted) should be


charged with the correct lubricants
Thank You

You might also like