Lecture 19-Selection, Installation & Commissioning
Lecture 19-Selection, Installation & Commissioning
Commissioning of
Instruments
2
Contents
• Need for instrumentation
• Selection of Instruments
• Installation
• Testing and pre-Commissioning
• Commissioning
3
1. Considerations:
• Process requirements
• Operators’ requirement
• Benefits to the plant from the proposed
instrumentation and control
• The way in which operator would like to interact
with plant process measurement, control and
monitoring instruments
• The location and environment of the control
room with respect to the plant process
6
• Reliability:
▫ The probability that the system will operate to an
agreed level of performance for specified period,
subject to specified environmental conditions.
The agreed level of performance means an accuracy of
±1.5%.
If the system is giving a measurement error outside
these limits, then it is considered to have failed, even
though it is otherwise working normally.
▫ A measurement system that has just been checked
and calibrated should have a reliability of 1 when first
placed in service
8
• Unreliability:
▫ The probability that the system will fail to operate
to an agreed level of performance, for a specified
period, subject to specified environmental
conditions.
▫ A system that has just been checked and
calibrated should have an unreliability of zero,
when placed first in service.
9
• Element selection:
▫ Only elements or systems with well-established
failure rate data/models should be used.
• Environment:
▫ The environment in which the element (or system)
is to be located must first be defined.
▫ The system should consist of components which
can withstand that environment.
• Minimum complexity:
▫ The number of elements in the system should be
the minimum required for the system to perform
its function.
10
• Diversity:
▫ Faults can occur which either cause more than one
element in each system, or a given element in each of
the several identical systems, to fail simultaneously,
this is referred to as “common mode failure”.
▫ To avoid this problem, a given function is carried out
by two systems in parallel, but each system is made
of different elements with different operating
principles.
• Maintenance:
▫ Mean down time should be as small as possible in
order to minimize the financial loss caused by the
element being out of action
11
Considerations:
• Storage and protection:
▫ Unpacking
▫ Minimize handling
▫ Suitable covering
▫ Air-conditioning
▫ Prevention from mechanical abuse
• Mounting and Accessibility:
▫ Vertically plumbed
▫ Accessible for observation and maintenance
▫ As close as possible to the process taping points
▫ Corrosion prevention Covering and painting
14
• Air Supplies:
▫ Clean, dry and oil-free
▫ Properly sized
▫ Self-draining and should have drainage/blow off
facilities
15
• Pneumatic signals:
▫ PVC outer sheath should be provided to copper tubing
▫ Should be run on a cable tray for its entire length
• Impulse lines:
“The impulse lines contain process fluids which run
between the instrument connection and the process
tapping point”
• Cable types:
▫ Solid conductors should be used to avoid
degradation of signals
▫ Mechanical protection
▫ PVC outer sheath (on open cable trays)
▫ Lead sheath (below ground in sand-filled
trenches)
17
• Cable segregation:
▫ Only signals of same type should be contained
within any one multi-core cable
▫ Cables for high-intensity systems such as
emergency shutdown systems should take totally
independent routes or should be positively
segregated from other cables
▫ Instrument cables should be run well clear of
electrical power cables and should also, as far as
possible, avoid noise generating equipment like
motors.
Testing
&
Pre-Commissioning
• Pre-Installation testing
• Piping and cable testing
• Loop testing (pre-commissioning)
20
Pre-Installation Testing
• Testing of each instrument for correct calibration and
operation prior to its being installed in the field.
Loop Testing
• The purpose of loop testing is to ensure that all
components in a loop are in full operational order when
interconnected and are in a steady state for plant
commissioning
Considerations
• Air supplies are available and that all power
supplies are fully functional, including any
emergency standby supplies