Monte Carlo Simulation
Monte Carlo Simulation
SIMULATION
• Alternative to PERT technique.
• Use to evaluate the risks of not achieving
deadlines.
• Basis of this technique involves
– Calculating activity completion times for a
project network a large no: of times.
– Selecting estimated activity times randomly
from a set of estimates for each activity.
25
20
15 Activity start
date
10 Activity end
date
5
0
56 59 62 65 68 71 74 77 80
• For calculation, we may have to carry out
the forward pass through the network
many times before obtaining a
representative selection of possible
completion times.
• Many packages for carrying out Monte
Carlo Simulation
• Exchange data with project-scheduling applications
• Interface to standard spreadsheet software
Critical chain concepts
• When the project is actually being executed
,the project mgr will be forced to focus on
the activities where the actual durations
exceed the target.
• Activities which are completed before the
target data are likely to be overlooked.
Weeks that activities were early or late
35
Percentage of activities
30
25
20
15
10
0
-6w -5w -4w -3w -2w -1w 0w 1w 2w 3w 4w 5w 6w
weeks
Gantt chart – plan using ‘expected times’ & starting all activities as late as possible
– In the Gantt chart, all the most likely durations
have been used & every activity is scheduled
to start as late as possible as long as the
project is completed by 1st March.
• To cope with activity overruns, a project buffer is
inserted at the end of the project before the target
completion date. This buffer is the equivalent of
50% of the length of the ‘comfort zone’ that has
been removed from the critical chain.
– Longest chain of activities in the project, taking account
of task & resource dependencies.
Different from critical path, only take account of
task dependencies.
Resource dependency-one activity has to wait for
a resource which is being used by another
activity to become available.
If an activity is late it will push the project
completion date further into the project buffer.
• Buffers are also inserted into the project
schedule where a subsidiary chain of activities
feeds into the critical chain.
– Feeding buffer -50% of the length of the
‘comfort zone’ removed from the subsidiary or
feeding chain.
3rd Quarter 4th Quarter 1st Quarter 2nd Quarter 3rd Quarter
ID i
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul