5-Prefabrication Group 103
5-Prefabrication Group 103
Construction Technology
& Materials II
Prefabrication /
Precast Concrete /
Modular Construction
Edmond Wong
Prefabrication
Manufacture of different sections or
components that can be assembled later on
the site to form part a building
Usually fabricated in the factory
On-site or off-site
E.g. steel sections, door frame, curtain wall,
plasterboard, dry wall, cladding
Precast concrete – very popular (will be
discussed in detail)
2
Steel Truss – Exhibition &
Convention Plaza
3
Prefabricated
Curtain Wall
Panel
4
Precast Concrete - Advantages
1)Demand on Skilled Labour
Semi-skilled labour required on site for installation
of precast elements
Lower labour cost (wage gap: HK Vs. China)
Aging skilled labour force in HK
2) Reliable Quality Control
QC in factory – accurate, reliable
Substandard quality discard the products before
installation
RFID tag embedded in building products (e.g.
precast units)
5
Traceability of Products
(Logistic, source of defective product)
RFID – radio frequency identification
6
7
8
Defective
Precast Slab
in Public
Housing (Sep
2016)
trace the
source and
production
batch
9
3) Consistent & Higher Quality
Indoor working environment (shielded from
heat and rain)
Use of robot / machinery (consistent
workmanship) e.g. troweling
Vertical elements cast horizontally (e.g.
façade) better compaction
Vibration table (e.g. slab) – compaction
Curing chamber – controlled environment:
temperature, humidity, pressure
10
Vibration table - compaction
11
Curing Chamber
12
Trowelling - finishing
13
3) Consistent & Higher Quality
Window frame cast BEFORE concreting
lower risk of water leakage
Waterproofing layer applied to floor slab
in precast toilet lower risk of water
leakage
External finishes (e.g. tiles) fixed on the
ground level (rather than working at height
on a scaffold!)
14
Window frame fixed before concreting
15
16
Source: www.hiphing.com.hk
17
4) Reduce No. of Separate Operations
Some elements (e.g. façade, toilet) involve a lot
of trades/sub-contractors
Different companies conflicts
E.g. Trades involved in toilet: plastering,
painting, waterproofing, stonework, joiners,
suspended ceiling, plumbing/drainage,
electricity, gas
Precast factory : under the same
management; well-planned
18
5) Better Continuity of Operation
Production line smooth operation, not
affected by weather, not affected by delay of
a particular trade
Must guarantee steady supply of precast
components/elements (logistic)
19
6) Faster Construction
No need to erect and strike formwork on site
No need to wait for the concrete to develop
strength
Progress not affected by weather
Avoid labour shortage affecting progress
20
7) Environmentally Friendly (Lean Construction)
Factory production Vs. Site production: reduce
wastage on materials
Good quality minimum defective works
lower demand on future repair and maintenance
works
Noise and air pollution– away from domestic
area
Replace timber formwork
Recycling (e.g. reinforcement, formwork)
Accurate ordering of material – avoid over-
ordering causing wastage
21
7) Environmentally Friendly (cont’d)
Smooth concrete surface reduce /
eliminate finishes (direct painting or
tiling without plastering)
Hollow units save materials
Hollow units reduce dead load
saving in structural components e.g.
foundation, columns
22
Hollow Precast Floor Slab
23
8) Prestressed Concrete
Fully utilize the strength of materials
(concrete and steel rebar)
Pre-tensioning to be carried out in the factory
(more difficult in site)
Thinner slab, no/shallow beam design
save materials save foundation cost,
reduce building height (thus less wind load)
E.g. Cambridge House in Quarry Bay used
U-shape pre-tension beam
24
Prestressed Beam and Flat-slab Design
25
9) Safer
Minimize work at height
tidier site – housekeeping
More machine/robot to substitute workers
Minimize weather exposure (heat, rain)
27
2) Coordination Between Design & Construction
Construction details different for in-situ and
precast construction early decision by
developers
Contractor is normally absent during design stage
and cannot advise on buildability
Procurement procedures: early award of window
supplier/contractor
Building services and finishes need to be
confirmed at early stage (freeze design)
28
29
3) Joints (more discussion later)
Precast units have a lot of joints
Movement on building – cracks easily developed
at joints water leakage, cracks
Error in joint design or construction will result
water leakage; for structural precast elements
affect structural integrity, building stability!
Monolithic joint (bonding with insitu concrete)
better structural integrity, lower risk of crack
Dry joint – performance affected by
workmanship and durability of joint materials
30
Monolithic Joints on 2 sides
and at top
31
32
4) Insufficient Time
Contractor needs sufficient lead time
(say, 4 months), to liaise with precast
factory to prepare for the production,
e.g. prepare drawings and sample
approval, the mould/formwork,
arrange trial production + testing;
speed of production
Allow approval time – architect, E&M
consultant, Buildings Department
33
34
5) On-site Or Off-Site Production
On-site lower transportation cost,
need more space on site; lower
dimensional limits; quality
inspection; high labour cost
Off-site cheaper labour cost in
China but additional transportation
cost; weight and dimensional limited
by road traffic; possibility of
interrupted supply
Possibility of transportation by sea?
35
On-Site Casting Yard
36
6) Repetitive Design (e.g. Public Housing)
Repetitive economy of scale
Hotel development identical rooms
Public housing standard and repetitive
design
Private development
different layout design from project to project
uniqueness of project
Different layout from flat to flat suit customers’
need/affordability
37
Example of standard design
38
7) Powerful Hoisting Plant
Heavy duty tower crane more
expensive
Modular construction (3D/volumetric
precast) e.g. precast toilet
39
8) Ample Storage Space Required
Storage of precast units needs a lot of space
(more feasible for public housing)
Urban site (just-in-time delivery?)
40
Factors to be Considered
4 Stages:
1. Design and Decision Stage
2. Factory Production Stage
3. Movement and Transportation Stage
4. Site Assembly Stage
41
42
1) Design & Decision Stage
Financial feasible (GFA exemption)?
Technical feasible (structural / non-
structural) ?
How repetitive? public housing
(Harmony block) – standard design
Symmetrical is NOT repetitive
Joining methods: dry joints (bolt & nut,
dowel or weld), monolithic concrete
43
Symmetrical (e.g. flat D vs E)
44
1,2,3 Bedroom – suit customers’ need
45
2) Factory Production Stage
Finalise design for panel size
(dimensional, weight factors), joint (type,
location), lifting and handling method,
mould manufacturing production line, etc.
Trial production + testing (e.g. water
tightness) before mass production
Modify design (e.g. joints) if water leakage
is found
46
47
48
49
2) Factory Production Stage
Speed of construction delivery
schedule production rate number
of moulds and size of workforce,
quantity of concrete
Set up quality control procedures
Products clearly marked (or with
RFID) easy to locate if defect is
found later
50
Location
of Panel
Clearly
Identified
51
3) Movement & Transportation Stage
Prevent damage during storage or
transportation (protection of edges/corners)
Only be hoisted at the designated lifting
inserts, with specially-designed hoisting
frames/beams
Elements stacked and stored according to the
installation sequence
52
Proper storage – avoid excessive
stress
Designated Hoisting Hooks (Lifting Inserts)
Stacked according to
53 installation sequence
Tailor-made lifting beam and frame
54
Requirements on Facade Lifting Beam
55
3) Movement & Transportation Stage
Maximize the space utilization of lorry, by
mounting frame
Supporting frames used to secure the position
of elements (prevent overturning during
transportation)
Internal access road clear for delivery
Trial drive by vehicle – limitations on road
width, height, corner turns, etc.
Avoid disruption to traffic (timing)
56
Maximize Space Utilization
57
58
59
3) Movement & Transportation Stage
May need to apply for traffic permits
By sea / road / both?
Road Traffic (Traffic Control) Regulations
Road Traffic (Construction and Maintenance
of Vehicles) Regulations
Dimensional limitations - Max. 4.6m tall;
2.5m wide; 24-44 tonnes
Just-in-time delivery?
60
4) Site Assembly Stage
set-up full scale Mock-up for
demonstration and necessary tests (e.g.
water tightness test)
Full-scale facade units fitted on site
Site storage (occupy large areas) – site layouts;
tower crane lifting capacity
Adequate temporary support and bracing
precast units are very heavy
Align and plumb the units carefully before final
fixing
61
62
Mounting Frames – Site Storage
63
Dangerous
Goods Storage Steel Moulds
Storage 6.8 ton @ Dia =
Tower Crane 40m
Dangerous Good
Storage(HH)
10.4 ton @ Dia =
28m
Electrician Storage
12 ton @ Dia =
24m
Mobile
Toilet
Chemical Waste
S/C Storage
Rest Hut
Offices
(60P)
Waste Water
Treatment Plant
Guard House
Kitchen and Toilet Setting Out Mock Out
Site Office
Alignment
65
66
Major Precast Concrete Elements
1. Façades
2. Semi-Precast External Walls
3. Staircases
4. Sub-Slabs
5. Toilet cubicles
6. Beams
7. Balcony
8. Dry wall
9. Pile 67
Facades
Commonly used in public housing e.g. Harmony
Old joint: infill panel (leave an opening then fit
the panel inside the opening) water leakage
New joint: monolithic joint (in-situ concrete) +
dry joint
Monolithic joint - lower risk of water seepage
Joints on 2 sides (left & right) + top joint –
monolithic
Bottom dry joint – neoprene strip/joint filler +
non-shrinkage grout (liquid form to fill up the
gap)
68
1st generation: Infill Panel – Weak Join
69
Monolithic (2
sides + top;
Bottom – dry
joint 70
Precast Facades
Aluminum window frame fixed before
concreting better waterproof performance
Cast horizontally better compaction,
economy in formwork
Autoclaving and steam curing better quality
External finishes applied before installation
eliminate scaffolding cheaper and safer
Watertightness test e.g. ASTM E331-00
71
Cast Horizontally (source: www.hiphing.com.hk)
72
Source: www.hiphing.com.hk
73
Aluminum
Window
Frame
Installed
74
Semi-Precast External Wall (other side of
the panel has already been tiled)
75
76
77
Semi-Precast External Wall
A semi-finished concrete panel with its external
face already tiled (hence, may eliminate
scaffolding)
Precast concrete panel used as external face wall
formwork (permanent formwork)
Also called ‘Lost Form’ (because the precast unit
is ‘lost’ after concrete is cast)
Construction sequence: fix precast Lost Form
install reinforcement/conduits fix internal face
wall formwork concreting to wall
78
Semi-Precast External Wall
Advantages :
monolithic joint– lower risk of water leakage
and cracks
Joints – invisible, fewer
flexible layout design – length and profile of
wall
Can act as structural wall
Lighter – smaller crane; longer panel size
concealed services conduits can be installed
in-situ: flexible to change
79
Wall Reinforcement and Concealed Conduits Fixed
Lost form temporary supported by raking strut
80
81
Precast Staircases
Traditional timber staircase –
time consuming because irregular shape;
congested – difficult to place concrete;
easily damaged due to traffic of workers
Precast staircase – immediately available for
transportation once fixed
Bonded to structure by dowel bars or
monolithic concrete
Semi-precast staircase – permanent formwork
with reinforcement already fixed
82
Convention
al Staircase
83
Precast Stair (www.hiphing.com.hk)
84
85
86
Photo – dowel bars & Slots
87
88
89
90
Semi-Precast Slab
Also known as ‘Sub-Slab’
Used as permanent formwork
Supported by falseworks
Fix concealed conduits and top layer
reinforcement on top of sub-slab
Pour top layer of concrete to form in-situ
monolithic joints (with walls/facades and beams)
Good soffit finishes but have possibility of
cracks
91
Construction Sequences
92
93
94
Fix Top Reinforcement Bar
95
96
97
Precast Toilet Cubicles
HSBC headquarters – the 1st building in HK
used the precast toilet cubicles
Made in Japan and shipped to HK
Becomes more popular in public housing
Ready to use once the electricity, plumbing
and drainage connected
98
Precast Toilet Cubicles
Toilet fixtures and finishes takes a lot of
time and labour
Involves a lot of trades and works: P&D,
gas supply, electricity, plastering, tiling,
screeding, marble fixing, painting
Needs to protect finished products because
involves too many trades and workers
Waterproofing in factory better quality
99
100
101
Precast Beams/Columns
(structural)
Used in HK Jockey Club HQ, KCR Hunghom
extension, KMB Lai Chi Kok depot, PolyU
Hunghom Bay campus etc.
Structural joints are required to ensure
continuity of rebars
Closer supervision and quality control because
affect building stability
102
103
104
105
Precast Balcony
balcony is a green feature and promoted by the
Govt.
Cantilever structure structural integrity must
bond to the structure with monolithic concrete
additional top reinforcement
concrete poured with the slab to form monolithic
joint
if the final balcony wall/railing need to be fixed in-
situ (e.g. glass wall), temporary railing required for
safety consideration
106
107
108
109
Precast Partition Wall (Dry
Wall)
Traditional – brick, block walls (wet trade –
cement/sand mortar as bond)
Wet trade – generate a lot of wastes, untidy
(unsafe)
Dry wall – fixed by metal cleats with cartridge
Electrical conduits already cast in, connected to
protruded conduits from slab
Good surface finish – no or thinner coat of
plastering
Use hollow or light weight concrete to reduce the
dead load of dry wall
110
Placed by Tower Crane
(before overhead slab is cast)
111
112
113
Lightweight Concrete Wall Panels
114
Traditional
Block Wall
115
116
Precast Piles
Daido piles
Used as foundation in public housing
Pre-tensioning in factory – stronger bending
strength
Cheaper than bored pile but with vibration and
noise
117
Precast
Concrete Piles
118
Precast Refuse Chute
119
Modular Integrated Construction (MiC)
https://www.bd.gov.hk/en/resources/codes-and-references/m
odular-integrated-construction/
Idea brought out in Chief Executive’s 2018 Policy
Address
BD’s definition: “Modular Integrated Construction (MiC)
refers to a construction whereby free-standing integrated
modules (completed with finishes, fixtures and fittings) are
manufactured in a prefabrication factory and then transported
to site for installation in a building”
GFA concession – 6% of MiC floor area (PNAP APP-
161; May 2019)
A PNAP ADV-36 (2017) sets out the requirements of MiC
https://www.bd.gov.hk/doc/en/resources/codes-and-references/practice-notes-and
-circular-letters/pnap/ADV/ADV036.pdf
120
6 modules to form a 3-bedroom
apartment
121
122
Double Wall/Slab in MiC modules
123
124
125
Modular Construction –
HKU, Science Park
126
127
Usage of Precast – Public Vs. Private
128
Prefabricated External Wall in
Private Development
Precast concrete unpopular in private
development before because (1) less repetition;
(2) lower flexibility to change; (3) takes longer
time during design stage
Prefabricated external wall ‘suddenly’ becomes
popular in 2001
Government encourages green buildings
Joint Practice Note No. 2 (Second Package of
Incentives to Promote Green and Innovative Buildings)
https://www.bd.gov.hk/doc/en/resources/codes-and-references/pra
ctice-notes-and-circular-letters/joint/JPN02.pdf
129
Prefabricated External Wall in Private
Development
Areas of non-structural prefabricated external
wall could be exempted from Plot Ratio and
Site Coverage calculation
Developers can build more floor area for sale
Extra revenues cover additional costs and loss
of flexibility
130
131
Abstract from a Sales Brochure
: Exempted GFA > 1,500 sq ft
132
GFA Exemption – Cap at 10%
Public concern about ‘inflated’ floor area
Public consultation document issued in 2009 “Building Design
to Foster a Quality and Sustainable Built Environment”
Govt. decided to set a cap of 10% to GFA concession
(Buildings’ Dept. Practice Note APP-151)
https://www.bd.gov.hk/doc/en/resources/codes-and-references/practice-notes-and-circular-
letters/pnap/APP/APP151.pdf
Precast facade and other features (e.g. utility platform, club
house facilities, etc.) are included
The building design also need to be assessed by HK-BEAM;
pass accreditation entitle the GFA exemption
Green Building Certification Label
https://www.hkgbc.org.hk/eng/beamplus-certlabel.aspx
133
134
Joints in Precast Concrete
Construction
Functional Requirements of Joints
exclude wind and rain
allow for structural, thermal and moisture
movement
durable
easily maintained
maintain thermal and sound insulation
properties of the surrounding cladding
easily assembled
136
Types of Joints
1. WET JOINT
Monolithic joint (in-situ concrete to bond
precast element with structure)
2. DRY JOINT
Single-Stage Joint
Filled Joint
Gasket Joint
Multi-Stage Joint
Drained Joint
137
Monolithic joint – washed
surface to expose aggregate
138
Wet Joint in Lost Form
139
Wet Joint in Lost Form
140
Filled Joint
– Z shaped
between
facades of
upper and
141
lower floors
142
Bottom Dry Joint
143
n -si t u s la b
o n d with i
t – b
Top Join
144
145
146
Joints – Precast Concrete
Filled Joint Gasket Joint Drained Joint Monolithic Joint
148
Filled
Joint
149
Filled Joint
Adhesion of sealant to seal off joints
Easy to apply but not very reliable
Common failure – poor adhesion (remove dirt,
grease, oil before apply sealant)
Vulnerable to movement and weather attack
Applied flush or set-back (avoid weathering)
Failed if under excessive compression or
elongation
150
Gasket Joint
151
Gasket
Joint
152
Gasket Joint
Working mechanism : pressure exerted on the
gaskets to provide a weathertight seal
Rubber gaskets: compressible, high elastic
recovery, good resistance to weather attack,
impermeable to water and moisture
Accurate dimensional control affect
pressure
Minor deformation or unevenness joint
failed because insufficient pressure
Excessive pressure may also damage the
joint material
153
Drained
Joint
154
155
Drained Joint
Neoprene baffle to divide the joint into 2 parts
Outer part: baffle to stop water to pass through
and drain the water away with the aid of
flashing
Inner part: air barrier to reduce the wind
pressure difference (pressure equalization)
Additional compressive joint material may be
added to enhance the waterproof performance of
the joint
156
Metazeal – Air Seal (Compressive Joint Material)
157
Air
Seal
Flashing
158
Air
Seal
159
Air
Seal
Baffle
(U-shaped)
160
Horizontal & Vertical Joints of
4 facade units
161
Joints in Structural Precast Elements
Major concern for structural elements: integrity
and continuity of structural elements like rebars
Splice sleeves are used to connect the rebars
Air space inside the sleeves will then be filled
up by cement grout
Structural precast elements are not popular in
HK because of concern of quality control and
there is no GFA exemption
162
Joints in Structural Precast Elements
the HK Housing Dept. had
a pioneer projects, Kwai
Chung Flatted Factory
Redevelopment, where up
to 60% of the concrete
elements were precast,
including structural
elements
They named it as
‘Enhanced Precast and
Prefabrication System Volumetric (3D)
(EPPS)’ bathroom-cum-kitchen
unit
163
Ove
rflo
w
Gro
ut i
n
164
165