0% found this document useful (0 votes)
83 views

5-Prefabrication Group 103

This document discusses prefabrication and precast concrete construction. It begins by defining prefabrication as the manufacture of building sections or components off-site that are assembled on-site. Precast concrete is highlighted as a common prefabrication method. The document then provides details on the advantages of precast construction including improved quality control, consistency, faster construction, and environmental benefits. Potential limitations are also reviewed such as reduced flexibility and coordination challenges. Key considerations for precast construction are outlined for the design/decision, factory production, transportation, and site assembly stages.

Uploaded by

jimmy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views

5-Prefabrication Group 103

This document discusses prefabrication and precast concrete construction. It begins by defining prefabrication as the manufacture of building sections or components off-site that are assembled on-site. Precast concrete is highlighted as a common prefabrication method. The document then provides details on the advantages of precast construction including improved quality control, consistency, faster construction, and environmental benefits. Potential limitations are also reviewed such as reduced flexibility and coordination challenges. Key considerations for precast construction are outlined for the design/decision, factory production, transportation, and site assembly stages.

Uploaded by

jimmy
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 165

SEHS 3284

Construction Technology
& Materials II

Prefabrication /
Precast Concrete /
Modular Construction

Edmond Wong
Prefabrication

Manufacture of different sections or
components that can be assembled later on
the site to form part a building

Usually fabricated in the factory

On-site or off-site

E.g. steel sections, door frame, curtain wall,
plasterboard, dry wall, cladding

Precast concrete – very popular (will be
discussed in detail)
2
Steel Truss – Exhibition &
Convention Plaza
3
Prefabricated
Curtain Wall
Panel

4
Precast Concrete - Advantages
1)Demand on Skilled Labour

Semi-skilled labour required on site for installation
of precast elements

Lower labour cost (wage gap: HK Vs. China)

Aging skilled labour force in HK
2) Reliable Quality Control

QC in factory – accurate, reliable

Substandard quality discard the products before
installation

RFID tag embedded in building products (e.g.
precast units)
5
Traceability of Products
(Logistic, source of defective product)
RFID – radio frequency identification

6
7
8
Defective
Precast Slab
in Public
Housing (Sep
2016) 
trace the
source and
production
batch

9
3) Consistent & Higher Quality

Indoor working environment (shielded from
heat and rain)

Use of robot / machinery (consistent
workmanship) e.g. troweling

Vertical elements cast horizontally (e.g.
façade)  better compaction

Vibration table (e.g. slab) – compaction

Curing chamber – controlled environment:
temperature, humidity, pressure
10
Vibration table - compaction

11
Curing Chamber

12
Trowelling - finishing

13
3) Consistent & Higher Quality

Window frame cast BEFORE concreting
 lower risk of water leakage

Waterproofing layer applied to floor slab
in precast toilet  lower risk of water
leakage

External finishes (e.g. tiles) fixed on the
ground level (rather than working at height
on a scaffold!)

14
Window frame fixed before concreting

15
16
Source: www.hiphing.com.hk
17
4) Reduce No. of Separate Operations

Some elements (e.g. façade, toilet) involve a lot
of trades/sub-contractors

Different companies  conflicts

E.g. Trades involved in toilet: plastering,
painting, waterproofing, stonework, joiners,
suspended ceiling, plumbing/drainage,
electricity, gas

Precast factory : under the same
management; well-planned

18
5) Better Continuity of Operation

Production line  smooth operation, not
affected by weather, not affected by delay of
a particular trade

Must guarantee steady supply of precast
components/elements (logistic)

19
6) Faster Construction

No need to erect and strike formwork on site

No need to wait for the concrete to develop
strength

Progress not affected by weather

Avoid labour shortage affecting progress

20
7) Environmentally Friendly (Lean Construction)

Factory production Vs. Site production: reduce
wastage on materials

Good quality  minimum defective works 
lower demand on future repair and maintenance
works

Noise and air pollution– away from domestic
area

Replace timber formwork

Recycling (e.g. reinforcement, formwork)

Accurate ordering of material – avoid over-
ordering causing wastage
21
7) Environmentally Friendly (cont’d)

Smooth concrete surface  reduce /
eliminate finishes (direct painting or
tiling without plastering)

Hollow units  save materials

Hollow units  reduce dead load 
saving in structural components e.g.
foundation, columns

22
Hollow Precast Floor Slab

23
8) Prestressed Concrete

Fully utilize the strength of materials
(concrete and steel rebar)

Pre-tensioning to be carried out in the factory
(more difficult in site)

Thinner slab, no/shallow beam design 
save materials  save foundation cost,
reduce building height (thus less wind load)

E.g. Cambridge House in Quarry Bay used
U-shape pre-tension beam

24
Prestressed Beam and Flat-slab Design

25
9) Safer

Minimize work at height

tidier site – housekeeping

More machine/robot to substitute workers

Minimize weather exposure (heat, rain)

10) Higher Productivity



Use of machinery, e.g. vibration table for
compaction

Reduce demand on tower crane (lifting
reinforcement, concrete, formwork)
26
Precast Concrete - Limitations
1) Lack of Flexibility (to change layout)

Difficult and expensive to change layout
design once committed i.e. freeze design

In-situ construction  more flexible (last-
minute change) WHY CHANGE?

DEVELOPERS NEEDS DESIGN
FLEXIBLITY to suit change of market,
customers’ taste/affordability, Govt. policy,
esp. in volatile market

27
2) Coordination Between Design & Construction

Construction details different for in-situ and
precast construction  early decision by
developers

Contractor is normally absent during design stage
and cannot advise on buildability

Procurement procedures: early award of window
supplier/contractor

Building services and finishes need to be
confirmed at early stage (freeze design)
28
29
3) Joints (more discussion later)

Precast units have a lot of joints

Movement on building – cracks easily developed
at joints  water leakage, cracks

Error in joint design or construction will result
water leakage; for structural precast elements 
affect structural integrity, building stability!

Monolithic joint (bonding with insitu concrete)
 better structural integrity, lower risk of crack

Dry joint – performance affected by
workmanship and durability of joint materials

30
Monolithic Joints on 2 sides
and at top
31
32
4) Insufficient Time

Contractor needs sufficient lead time
(say, 4 months), to liaise with precast
factory to prepare for the production,

e.g. prepare drawings and sample
approval, the mould/formwork,
arrange trial production + testing;
speed of production

Allow approval time – architect, E&M
consultant, Buildings Department
33
34
5) On-site Or Off-Site Production

On-site  lower transportation cost,
need more space on site; lower
dimensional limits; quality
inspection; high labour cost

Off-site  cheaper labour cost in
China but additional transportation
cost; weight and dimensional limited
by road traffic; possibility of
interrupted supply

Possibility of transportation by sea?
35
On-Site Casting Yard

36
6) Repetitive Design (e.g. Public Housing)

Repetitive  economy of scale

Hotel development  identical rooms

Public housing  standard and repetitive
design

Private development

different layout design from project to project 
uniqueness of project

Different layout from flat to flat  suit customers’
need/affordability

37
Example of standard design

38
7) Powerful Hoisting Plant

Heavy duty tower crane  more
expensive

Modular construction (3D/volumetric
precast) e.g. precast toilet

39
8) Ample Storage Space Required

Storage of precast units needs a lot of space
(more feasible for public housing)

Urban site (just-in-time delivery?)

40
Factors to be Considered

4 Stages:
1. Design and Decision Stage
2. Factory Production Stage
3. Movement and Transportation Stage
4. Site Assembly Stage

41
42
1) Design & Decision Stage

Financial feasible (GFA exemption)?

Technical feasible (structural / non-
structural) ?

How repetitive? public housing
(Harmony block) – standard design

Symmetrical is NOT repetitive

Joining methods: dry joints (bolt & nut,
dowel or weld), monolithic concrete
43
Symmetrical (e.g. flat D vs E)

44
1,2,3 Bedroom – suit customers’ need

45
2) Factory Production Stage

Finalise design for panel size
(dimensional, weight factors), joint (type,
location), lifting and handling method,
mould manufacturing production line, etc.

Trial production + testing (e.g. water
tightness) before mass production

Modify design (e.g. joints) if water leakage
is found

46
47
48
49
2) Factory Production Stage

Speed of construction  delivery
schedule  production rate  number
of moulds and size of workforce,
quantity of concrete

Set up quality control procedures

Products clearly marked (or with
RFID)  easy to locate if defect is
found later
50
Location
of Panel
Clearly
Identified

51
3) Movement & Transportation Stage

Prevent damage during storage or
transportation (protection of edges/corners)

Only be hoisted at the designated lifting
inserts, with specially-designed hoisting
frames/beams

Elements stacked and stored according to the
installation sequence

52
Proper storage – avoid excessive
stress
Designated Hoisting Hooks (Lifting Inserts)

Stacked according to
53 installation sequence
Tailor-made lifting beam and frame

54
Requirements on Facade Lifting Beam

55
3) Movement & Transportation Stage

Maximize the space utilization of lorry, by
mounting frame

Supporting frames used to secure the position
of elements (prevent overturning during
transportation)

Internal access road clear for delivery

Trial drive by vehicle – limitations on road
width, height, corner turns, etc.

Avoid disruption to traffic (timing)
56
Maximize Space Utilization

57
58
59
3) Movement & Transportation Stage

May need to apply for traffic permits

By sea / road / both?

Road Traffic (Traffic Control) Regulations

Road Traffic (Construction and Maintenance
of Vehicles) Regulations

Dimensional limitations - Max. 4.6m tall;
2.5m wide; 24-44 tonnes

Just-in-time delivery?
60
4) Site Assembly Stage

set-up full scale Mock-up for
demonstration and necessary tests (e.g.
water tightness test)

Full-scale facade units fitted on site

Site storage (occupy large areas) – site layouts;
tower crane lifting capacity

Adequate temporary support and bracing 
precast units are very heavy

Align and plumb the units carefully before final
fixing
61
62
Mounting Frames – Site Storage

63
Dangerous
Goods Storage Steel Moulds
Storage 6.8 ton @ Dia =
Tower Crane 40m
Dangerous Good
Storage(HH)
10.4 ton @ Dia =
28m

Electrician Storage
12 ton @ Dia =
24m

S/C BEDNING YARD


Offices

Jump Lift at Lift


Shaft

Mobile
Toilet

Chemical Waste
S/C Storage
Rest Hut
Offices
(60P)
Waste Water
Treatment Plant

Concrete Curing Facility

Wheel Wash Machine


Site Entrance

Guard House
Kitchen and Toilet Setting Out Mock Out

Site Office
Alignment

65
66
Major Precast Concrete Elements
1. Façades
2. Semi-Precast External Walls
3. Staircases
4. Sub-Slabs
5. Toilet cubicles
6. Beams
7. Balcony
8. Dry wall
9. Pile 67
Facades

Commonly used in public housing e.g. Harmony

Old joint: infill panel (leave an opening then fit
the panel inside the opening)  water leakage

New joint: monolithic joint (in-situ concrete) +
dry joint

Monolithic joint - lower risk of water seepage

Joints on 2 sides (left & right) + top joint –
monolithic

Bottom dry joint – neoprene strip/joint filler +
non-shrinkage grout (liquid form to fill up the
gap)
68
1st generation: Infill Panel – Weak Join

69
Monolithic (2
sides + top;
Bottom – dry
joint 70
Precast Facades

Aluminum window frame fixed before
concreting  better waterproof performance

Cast horizontally  better compaction,
economy in formwork

Autoclaving and steam curing  better quality

External finishes applied before installation 
eliminate scaffolding  cheaper and safer

Watertightness test e.g. ASTM E331-00

71
Cast Horizontally (source: www.hiphing.com.hk)

72
Source: www.hiphing.com.hk
73
Aluminum
Window
Frame
Installed

74
Semi-Precast External Wall (other side of
the panel has already been tiled)

75
76
77
Semi-Precast External Wall

A semi-finished concrete panel with its external
face already tiled (hence, may eliminate
scaffolding)

Precast concrete panel used as external face wall
formwork (permanent formwork)

Also called ‘Lost Form’ (because the precast unit
is ‘lost’ after concrete is cast)

Construction sequence: fix precast Lost Form 
install reinforcement/conduits  fix internal face
wall formwork  concreting to wall
78
Semi-Precast External Wall

Advantages :

monolithic joint– lower risk of water leakage
and cracks

Joints – invisible, fewer

flexible layout design – length and profile of
wall

Can act as structural wall

Lighter – smaller crane; longer panel size

concealed services conduits can be installed
in-situ: flexible to change
79
Wall Reinforcement and Concealed Conduits Fixed
Lost form temporary supported by raking strut

80
81
Precast Staircases

Traditional timber staircase –

time consuming because irregular shape;

congested – difficult to place concrete;

easily damaged due to traffic of workers

Precast staircase – immediately available for
transportation once fixed

Bonded to structure by dowel bars or
monolithic concrete

Semi-precast staircase – permanent formwork
with reinforcement already fixed
82
Convention
al Staircase

83
Precast Stair (www.hiphing.com.hk)

84
85
86
Photo – dowel bars & Slots

87
88
89
90
Semi-Precast Slab

Also known as ‘Sub-Slab’

Used as permanent formwork

Supported by falseworks

Fix concealed conduits and top layer
reinforcement on top of sub-slab

Pour top layer of concrete to form in-situ
monolithic joints (with walls/facades and beams)

Good soffit finishes but have possibility of
cracks

91
Construction Sequences

92
93
94
Fix Top Reinforcement Bar

95
96
97
Precast Toilet Cubicles


HSBC headquarters – the 1st building in HK
used the precast toilet cubicles

Made in Japan and shipped to HK

Becomes more popular in public housing

Ready to use once the electricity, plumbing
and drainage connected

98
Precast Toilet Cubicles

Toilet fixtures and finishes takes a lot of
time and labour

Involves a lot of trades and works: P&D,
gas supply, electricity, plastering, tiling,
screeding, marble fixing, painting

Needs to protect finished products because
involves too many trades and workers

Waterproofing in factory  better quality

99
100
101
Precast Beams/Columns
(structural)

Used in HK Jockey Club HQ, KCR Hunghom
extension, KMB Lai Chi Kok depot, PolyU
Hunghom Bay campus etc.

Structural joints are required to ensure
continuity of rebars

Closer supervision and quality control because
affect building stability

102
103
104
105
Precast Balcony

balcony is a green feature and promoted by the
Govt.

Cantilever structure  structural integrity  must
bond to the structure with monolithic concrete

additional top reinforcement

concrete poured with the slab to form monolithic
joint

if the final balcony wall/railing need to be fixed in-
situ (e.g. glass wall), temporary railing required for
safety consideration
106
107
108
109
Precast Partition Wall (Dry
Wall)

Traditional – brick, block walls (wet trade –
cement/sand mortar as bond)

Wet trade – generate a lot of wastes, untidy
(unsafe)

Dry wall – fixed by metal cleats with cartridge

Electrical conduits already cast in, connected to
protruded conduits from slab

Good surface finish – no or thinner coat of
plastering

Use hollow or light weight concrete to reduce the
dead load of dry wall
110
Placed by Tower Crane
(before overhead slab is cast)

111
112
113
Lightweight Concrete Wall Panels

114
Traditional
Block Wall

115
116
Precast Piles

Daido piles

Used as foundation in public housing

Pre-tensioning in factory – stronger bending
strength

Cheaper than bored pile but with vibration and
noise

117
Precast
Concrete Piles

118
Precast Refuse Chute

119
Modular Integrated Construction (MiC)
https://www.bd.gov.hk/en/resources/codes-and-references/m
odular-integrated-construction/

Idea brought out in Chief Executive’s 2018 Policy
Address

BD’s definition: “Modular Integrated Construction (MiC)
refers to a construction whereby free-standing integrated
modules (completed with finishes, fixtures and fittings) are
manufactured in a prefabrication factory and then transported
to site for installation in a building”

GFA concession – 6% of MiC floor area (PNAP APP-
161; May 2019)

A PNAP ADV-36 (2017) sets out the requirements of MiC

https://www.bd.gov.hk/doc/en/resources/codes-and-references/practice-notes-and
-circular-letters/pnap/ADV/ADV036.pdf

120
6 modules to form a 3-bedroom
apartment

121
122
Double Wall/Slab in MiC modules

123
124
125
Modular Construction –
HKU, Science Park

126
127
Usage of Precast – Public Vs. Private

128
Prefabricated External Wall in
Private Development

Precast concrete unpopular in private
development before because (1) less repetition;
(2) lower flexibility to change; (3) takes longer
time during design stage

Prefabricated external wall ‘suddenly’ becomes
popular in 2001

Government encourages green buildings

Joint Practice Note No. 2 (Second Package of
Incentives to Promote Green and Innovative Buildings)
https://www.bd.gov.hk/doc/en/resources/codes-and-references/pra
ctice-notes-and-circular-letters/joint/JPN02.pdf
129
Prefabricated External Wall in Private
Development

Areas of non-structural prefabricated external
wall could be exempted from Plot Ratio and
Site Coverage calculation

Developers can build more floor area for sale

Extra revenues cover additional costs and loss
of flexibility

130
131
Abstract from a Sales Brochure
: Exempted GFA > 1,500 sq ft
132
GFA Exemption – Cap at 10%

Public concern about ‘inflated’ floor area

Public consultation document issued in 2009 “Building Design
to Foster a Quality and Sustainable Built Environment”

Govt. decided to set a cap of 10% to GFA concession
(Buildings’ Dept. Practice Note APP-151)
https://www.bd.gov.hk/doc/en/resources/codes-and-references/practice-notes-and-circular-
letters/pnap/APP/APP151.pdf

Precast facade and other features (e.g. utility platform, club
house facilities, etc.) are included

The building design also need to be assessed by HK-BEAM;
pass accreditation  entitle the GFA exemption

Green Building Certification Label
https://www.hkgbc.org.hk/eng/beamplus-certlabel.aspx

133
134
Joints in Precast Concrete
Construction
Functional Requirements of Joints

exclude wind and rain

allow for structural, thermal and moisture
movement

durable

easily maintained

maintain thermal and sound insulation
properties of the surrounding cladding

easily assembled

136
Types of Joints
1. WET JOINT

Monolithic joint (in-situ concrete to bond
precast element with structure)

2. DRY JOINT

Single-Stage Joint

Filled Joint

Gasket Joint

Multi-Stage Joint

Drained Joint

137
Monolithic joint – washed
surface to expose aggregate

138
Wet Joint in Lost Form

139
Wet Joint in Lost Form

140
Filled Joint
– Z shaped
between
facades of
upper and
141
lower floors
142
Bottom Dry Joint
143
n -si t u s la b
o n d with i
t – b
Top Join

Monolithic Joint – in-situ wall


bonded with precast facades
Non
-shr
ink
g rou
t to
fill
t he
Bot
t om
join
t

144
145
146
Joints – Precast Concrete
Filled Joint Gasket Joint Drained Joint Monolithic Joint

Mechanism Adhesion (of Pressure exerted on 1) Physical barrier In-situ concrete


sealant) gasket (baffle) bonding
2) Cavity
Constructio Dry joint Dry joint Dry joint Wet joint
n method
Complexity Simple, single- Simple, single- More complex; 2 Simple but need
/ Easiness stage stage stages rebar fixing +
formworking +
concreting

Speed Fast Fast Fairly fast Slow


Possible Adhesion failure Movement / poor Workmanship – Poor
defects (unclean surface, dimensional control installing workmanship
excess / deformation will components (baffle,
movement) affect pressure flashing, air seal)
weather attack
Reliability Low Low 147 Higher Highest
Filled Joint

148
Filled
Joint

149
Filled Joint

Adhesion of sealant to seal off joints

Easy to apply but not very reliable

Common failure – poor adhesion (remove dirt,
grease, oil before apply sealant)

Vulnerable to movement and weather attack

Applied flush or set-back (avoid weathering)

Failed if under excessive compression or
elongation
150
Gasket Joint

151
Gasket
Joint

152
Gasket Joint

Working mechanism : pressure exerted on the
gaskets to provide a weathertight seal

Rubber gaskets: compressible, high elastic
recovery, good resistance to weather attack,
impermeable to water and moisture

Accurate dimensional control  affect
pressure

Minor deformation or unevenness  joint
failed because insufficient pressure

Excessive pressure may also damage the
joint material
153
Drained
Joint

154
155
Drained Joint

Neoprene baffle to divide the joint into 2 parts

Outer part: baffle to stop water to pass through
and drain the water away with the aid of
flashing

Inner part: air barrier to reduce the wind
pressure difference (pressure equalization)

Additional compressive joint material may be
added to enhance the waterproof performance of
the joint
156
Metazeal – Air Seal (Compressive Joint Material)

157
Air
Seal

Flashing

158
Air
Seal

159
Air
Seal

Baffle
(U-shaped)

160
Horizontal & Vertical Joints of
4 facade units

161
Joints in Structural Precast Elements

Major concern for structural elements: integrity
and continuity of structural elements like rebars

Splice sleeves are used to connect the rebars

Air space inside the sleeves will then be filled
up by cement grout

Structural precast elements are not popular in
HK because of concern of quality control and
there is no GFA exemption

162
Joints in Structural Precast Elements

the HK Housing Dept. had
a pioneer projects, Kwai
Chung Flatted Factory
Redevelopment, where up
to 60% of the concrete
elements were precast,
including structural
elements

They named it as
‘Enhanced Precast and
Prefabrication System Volumetric (3D)
(EPPS)’ bathroom-cum-kitchen
unit
163
Ove
rflo
w
Gro
ut i
n

164
165

You might also like