Lecture 4 Project Control and Site Monitoring Update
Lecture 4 Project Control and Site Monitoring Update
Site Monitoring
1
Overview
2
An essential part of Building Control's function is
to ensure that construction works on site
comply to the Building Regulations and other
associated legislation.
3
Building work must be inspected to check that the
Building Regulations have been complied with.
6
Inspections of certain stages of work
The inspection will cover :-
7
Site inspections
9
Foundations excavation
11
Oversite
12
Damp Proof Course
13
Laying of drains
14
Drains test
16
Completion
ARCHITECT/ EXTERNAL
G2 SETTING OUT
ENGINEER (PSP) G13 WATER SUPPLY ENGINEER (SP)
SYSTEM
G3 FOUNDATIONS ENGINEER (SP)
SEWERAGE
G4 STRUCTURAL ENGINEER (SP) G14 ENGINEER (SP)
RETICULATION
INTERNAL
SEWERAGE
G5 WATER ENGINEER (SP)
G15 TREATMENT ENGINEER (SP)
PLUMBING
PLANT
INTERNAL
EXTERNAL
G6 SANITARY ENGINEER (SP)
ELECTRICAL
PLUMBING G16 ENGINEER (SP)
SUPPLY
INTERNAL SYSTEM
G7 ENGINEER (SP)
ELECTRICAL
G17 ROAD & DRAIN ENGINEER (SP)
FIRE-FIGHTING ARCHITECT /
G8 STREET
(PASSIVE) ENGINEER (PSP) G18 ENGINEER (SP)
LIGHTING
FIRE-FIGHTING
G9 ENGINEER (SP) EXTERNAL
(ACTIVE) G19 ENGINEER (SP)
MAIN DRAIN
MECHANICAL
G10 ENGINEER (SP) TELECOMUNI-
VENTILATION G20 ENGINEER (SP)
CATION
LIFT/
COMMON ISSUES DURING
BUILDING CONSTRUCTION
PERIOD INVOLVING LOCAL
AUTHORITY
Common issues during building
construction period involving Local
Authority
To ensure the construction work done according to the approved building plan
Nuisance to environment
›Excessive Noise level
›Working hour
›Excessive Light
›Road / access safety and cleanliness
›Water pollution/ effluent
›Ground vibration/movement
›Working outside land boundary
› Vector control (aedes mosquito)
› Food handling and cooking
› Worker’s temporary housing
› Construction materials outside land boundary
• Failure to building (sec 258, UBBL)
• Temporary permit for temporary structure (Sec18, UBBL)
Monitoring of Development
24
Monitoring Construction Site
Site environmental impact
› Noise control – produced by various activities in construction site such as
piling, digging, hacking etc
› Air pollution – to control dust, debris that comes from construction or
demolition project
› Mud from lorries going out of site – make a “wash trough” for cleaning the
tyres
Construction waste – Site Waste Management Plan for successful waste
management practices in construction project. Apply 3R concept – Recycle,
Reuse, Reduce
Construction Safety and healthy
› 3 requirements :
i)Personal Protective Equipment : to minimize exposure to serious injuries and
illness towards employee. F.e google, glove, safety helmet etc
ii) Law and regulation : OSHA 1994, Malaysia Standard
iii) Safety sign, tool or equipment
Energy and water used in carry out construction activities
25
Reducing the Site Environmental Impact
26
Explain methods of protecting slope, gradient etc.
27
Noise control on site
29
Select products and materials with minimal or no
packaging, if possible.
30
Health and Safety
Those responsible for the site must ensure that safe access is
provided for Building Control Surveyors to undertake site
inspection duties in accordance with Health & Safety legislation.
31
Health and Safety
Plant and Machinery
The working conditions in construction site are in most cases such as despite
all preventive measures in project planning and work design, certain PPE is
needed to control the hazard faces by workers.
i) Head protection
ii)Foot and leg protection (safety boot)
iii)Hearing protection
iv)Eye protection
v)Hand and arm protection
vi)Respiratory protection
vii)Fall arrester and safety harness
Enforcement
When work is found not to comply with the Regulations,
Building Control Officer will request that it is altered
or removed to put things right. Hopefully, this will be
done but if not, then Building Control Officer may serve
a legal notice to the building owner requiring him to do
so.
Normally the notice will give 28 days to rectify the work.
Enforcement is rare as, normally, common sense prevails.
Building Control Officer is, after all, merely ensuring that
building is a safe and healthy place to live, work or visit.
Therefore final inspection is important before
contractors leaves the job. Any problems can then be
quickly and efficiently put right.
35
Enforcement
Completion certificates can be issued on
satisfactory completion of works.
Compliance to approved plans, nuisance,pollution
are under the purview of Local Authority
safety and health policy, committee, SHO,SSS are
under the purview of DOSH
Contractor registration and green card under the
purview of CIDB
36