6 TOPIC 3 ESTIMATING Carpenter N Steelworks
6 TOPIC 3 ESTIMATING Carpenter N Steelworks
E S T I M AT I N G
3.1 FORMWORK
NAILS / PAKU
iii) For initial use of formwork - need approx. 0.35 kg for 1 m2 formwork.
iv) LABOUR
Labour Output For Preparing And Removing Formwork :-
POSITION Preparing & Erecting Removing & Storing
(Per m2) (Per m2)
CARPENTER GENERAL GENERAL
LABOURER LABOURER
Wall, Roof and Floor 1.00 hour 0.75 hour 0.75 hour
Beam, Column and 1.50 hour 0.75 hour 0.75 hour
Lintol
Waste
v) Allowance for Waste = 10 % of formwork
Data :
Plywood:
in size: 2.40 m x 1.20 m x 12 mm thick RM 37.00 / sheet
DOOR DOOR
LEAF FRAME
3.0CARPENTER
3.2 TIMBER WORK – DOOR leaf
EXAMPLE 2
STANDARD FLUSH DOOR
850mm x 2050mm x 40mm thick skeleton framed flush door
obtained from United Doors Sdn. Bhd. Code 123 FD. - no
Data :
Standard Flush door RM 70.00 / No.
Labour cost : Carpenter RM 65.00 / day
Labour constant : Installing & fixing door 0.85 hr / m²
Profit : 15%
3.0CARPENTER
ANSWER
RM RM RM
Sub-total Sub-total Total
A Material Cost
Standard door frame 120.00
Nails 0.30 Kg x RM 4.75 1.43
121.43
Add wastages 5% x RM 121.43 6.07 127.50
B Labour Cost
Installing & fixing
door frame
Carpenter 1.00 hr x RM 65.00 8.13 8.13
8 hrs
135.62
C Profit and Overhead
12% x RM 135.62 16.27
6 - 8 mm 10 -12 16 - 20 > 25 mm
dia. mm dia. mm dia. dia.
Straight and bent bar 40 30 20 15
5.0 Table for labour constants / output for PLACING BAR IN POSITION
(For every 1 tonne / 1000 kg bar)
6 - 8 mm 10 -12 16 - 20 > 25 mm
dia. mm dia. mm dia. dia.
Foundation & Concrete
40 30 25 20
bed
Link / stirrup 90 70 60 -
6.0 Tying wire must included in estimating of bar. The quantity of tying wire
needed including hoisting as shown below :-
Table of Tying wire for bar reinforcement Per kg
Diameter of bar (mm) Tying wire for 1 tonne bar (kg)
6 - 12 mm 10
16 - 25 mm 6
32 - 50 mm 5
a) Labour cost
For placing, fixing and cutting the fabric reinforcement, only need General
Worker (no need skilled labour)
b) Table for labour constants / Labour Output for PLACING AND FIXING
IN POSITION Fabric Reinforcement (Hour Per square metre)
Hour per m2
f) Allow 5% for waste of fabric reinforcement and 10% for tying wire
cost.
EXAMPLE 1
Supply, cut and bent on site and Fix Bar Reinforcement
12mm diameter high tensile steel reinforcement in straight and bent bars
in foundation. - kg
Data:
Material prices (including delivery to site)
Reinforcement Bar RM 1700/ tonne
Tying wire RM 2.50/ kg
Labour rates
Bar Bender RM 62.00 / day
Unskilled worker RM 40.00 / day
Labour constant
Unloading and storage 1.5 hours
Cutting and bending 30 hours
Fix and install 30 hours
Diameter of bar (mm) Tying wire for 1 tonne bar (kg)
6 - 12 mm 10
16 - 25 mm 6
32 - 50 mm 5
EXAMPLE 1
RM RM
A Material Cost (per 1000kg) Sub-total Sub-total
Bar reinforcement - 12 mm ø 1,700.00
Add: waste 5% x RM 1700.00 85.00
Tying wire 10 kg x RM 2.50 25.00 1,810.00
B Labour Cost (per 1000kg)
Unloading and storage
Unskilled labour 1.50 hr x RM 40.00 7.50
8
Cutting and bending
Bar bender 30 hr x RM 62.00 232.50
8
Fix/ Install
Bar bender 30 hr x RM 62.00 232.50 472.50
8
2,282.50
C Profit and Overhead Allow 30% x 2,282.50 684.75
Cost / 1000Kg 2,967.25
So, COST / KG = 2,967.25
1000 2.97
EXAMPLE 2
Data:
Data:
Material prices (including delivery to site)
Mortice lockset
RM 65.00 / set
including screw
Labour rates
Skilled RM 80.00 / day
Joiner hour 1.25 hr
Profit 18%
A Material Cost RM
Mortice lockset including screw = 65.00
B Labour Cost
Joiner for jointing & fixing lockset
Plumber = 1.25 hr/set x RM 80.00 = 12.50
8
RM 77.50
C Profit = 18% x RM 77.50 = 13.95
Cost for jointing & fixing LOCKSET / SET 91.45
D.P.C
(brickwall)
EXAMPLE 1
225 mm wide horizontal d.p.c. of single course hessian
based bit. felt to B.S. 743 ref. A lapped 100mm at joints
bedded in c & s (1:3) mortar (measured net - no
allowance made for laps)- m
Data:
Material prices (including delivery to site)
225 mm wide DPC RM 6.90 / m2
Cement sand mortar (1:3) - 20 mm thick RM 117.00 / m3
Labour rates
Bricklayer RM 60.00 / day
Unskilled worker RM 35.00 / day
Scope of work:-
Labour Output:- Bricklayer Unskilled worker
Lay and install 0.04 hours / m3 0.04 hours / m3
Profit 22%
ANSWER
Material Cost Subtotal (RM)
225 mm wide DPC = 225 x RM 6.90 1.55
=
1000
Add: waste & lapping 5% x RM 1.55 = 0.08
20 mm thk cement sand
= 0.02 m RM 117.00 = 2.34
mortar (1:3)
Labour Cost
Supply, fix and laying
Bricklayer = 0.04 hr x RM 60.00 = 0.30
8
Unskilled worker = 0.04 hr x RM 35.00 = 0.18
8
4.44
Profit = 22% x RM 4.44 = 0.98
Total Cost for DPC / m = 5.42
example 2
113 mm wide horizonta l d.p.c. of s ingle cours e he s s ia n ba s e d bitume n fe lt,
la ppe d 100mm a t joints be dde d in C & S (1:1:6) morta r (me a s ure d ne t - no
a llowa nce ma de for la ps ) - m
Da ta :
Ma te ria l price s (including de live ry to s ite )
113 mm wide DPC RM 5.75 / m2
20 mm thick morta r
Ce me nt RM 10.00 / ba g
Sa nd RM 28.75 / m3
Lime RM 4.20 / pa cke t
La bour ra te s
Brickla ye r RM 65.00 / da y
Uns kille d worke r RM 40.00 / da y
Scope of work:-
La bour Output:- Brickla ye r Uns kille d worke r
Mixing morta r 2.25 hours / m3
La y a nd ins ta ll 0.02 hours / m 0.02 hours / m
Profit 20%
ANSWER
1.0 MORTAR COST RM
Material Cost
1 m3 cement = 28 Bag x RM 10.00 = 280.00
1 m3 Lime = 40 packet x RM 4.20 = 168.00
6 m3 sand = 6 m3 x RM 28.75 = 172.50
8 m3 620.50
ADD : Waste = 33.3% x RM 620.50 = 206.81
So, Cost of 8 m3 = 827.31
= RM 827.31
8
:. Cost of 1 m3 = 103.41
Labour Cost
Mixing of concrete
Unskilled worker 2.25 hours x RM 40.00 = 11.25
8
Cost of 1 m3 (1:1:6) mortar = 114.66
2.0 DPC COST
Material Cost Subtotal (RM)
113 mm wide DPC = 113 x RM 5.75 0.65
=
1000
Add: waste & lapping 5% x RM 0.65 = 0.03
20 mm thk cement sand
= 0.02 m RM 114.66 = 2.29
mortar (1:3)
Labour Cost
Supply, fix and laying
Bricklayer = 0.02 hr x RM 65.00 = 0.16
8
Unskilled worker = 0.02 hr x RM 40.00 = 0.10
8
3.24
Profit = 20% x RM 3.24 = 0.65
Total Cost for DPC / m = 3.89