Introduction QSE
Introduction QSE
8. Supplementary Estimate
This is fresh detailed estimate in addition to the original
sanctioned estimate prepared when additional works are deemed
necessary during the progress of a work to supplement the
original works. The abstract of cost should show the amount of
the original sanctioned estimate as well as the supplementary
amount of the original sanctioned estimate as well as the
supplementary amount for which sanction is required.
9. Complete estimate
The estimate which includes, in addition to the cost of
construction, the cost of land, the expenses towards
surveying, preparation of plans and estimates, legal
assistance, registration of documents, payment of taxes and
service charges , etc…. Is called complete estimate.
10. Sub estimate
Sub estimate are being prepared for each and every such
items in detail to ensure and see that the expense towards
these items do not exceed the corresponding provisions
already made in the original estimate.
TERMINOLOGY
1. Contingencies – Indicates incidental expenses of
miscellaneous character which cannot be classified under any
distinct item. (3% to 5% of the estimated cost is provided total
low for contingencies)
2. Work-charged Establishment – Work-charged employees
are temporary staff whose services are terminated at the
expiry of sanctioned period but usually one month notice is
given. (1.5% to 2% of the estimated cost is added)
3. Tools and Plants – Normally contractor has to arrange tools
and plants. (1% to 1.5% of estimated cost is provided)
4. Centage charges or Departmental charges – Also known as
Supervision charges for works. To meet the expenses of
establishment, designing, planning, supervision etc. (10% to
15% of the estimated cost) . When engineering department
takes up work of other department.
5. Sub-Head items of work – Works like earthwork, concreten
work, brick work etc. Under each sub head there are different
items of work.
6. Sub-Work – Large project may consist of small buildings.
Detailed estimate of each sub-work is prepared separately.
7. Schedule of Rates – It is a list of rate of various items of works
maintained by engineering department under the name “ Schedule
of Rates Book ”. “Road Metal Rate Book ” is also maintained by
PWD.
8. Administrative Sanction/ Approval – It is the formal
acceptance by the department concerned of the proposal. After the
approval, design, estimates etc. are prepared and There after
execution of work.
9. Expenditure Sanction – It represents allotment of money to
meet the expenditure. It is usually accorded by Finance
Department.
10. Technical Sanction – It is the sanction of the detailed
estimate, design calculation, quantities of work etc. Technical
sanction is accorded by engineering department and execution
of work is carried out thereafter.
11. Quantity Survey – It means estimating of quantities of
different items of works.
12. Plinth Area – It is the built up covered area of a building
measured at floor level of any storey by taking external
dimensions of the building at the floor level.
13. Floor Area – It is obtained after deducting area of walls
from the plinth area of building. It should include: Door and
other openings Intermediate pillars and supports.
14.Circulation Area – It is the floor area of verandahs,
passages, corridors, balconies, staircases, lift etc. which are used
for movements of persons using the building. It is further
classified into Horizontal and Vertical .
15. Carpet Area – It is the useful area of the building. It is
determined after deducting :
•Circulation Area
•Sanitary Accommodations
•Kitchen, Pantry, Stores
•For office building approximate 60% to 75% of plinth area
•For residential buildings approximate 50% to 65% of plinth
area
16. Site Plan – Plan showing orientation of building,
boundaries of
land, position of roads, drains, sewer line, water pipelines and
adjoining plots of lands. North direction is also shown on one
corner of site plan)
17. Layout Plan – Plan showing proposed buildings,
structures etc. showing their locations, size and orientations.
Roads, drains, pipe lines , electric lines, parks etc are shown.
The boundary, main approach roads and adjoining areas are
also indicated.
18. Index Plan – Plan is usually drawn for Roads, Irrigation,
Water supply etc. It shows alignment with position of culverts,
main outline of whole work to give idea of the project
For big project it is drawn with much small scale and is known
as key plan