CPM Time Analysis Floats
CPM Time Analysis Floats
Sunil kadam
Floats
• Floats means amount of time by which the completion of an
activity can be delayed without delaying the total project
completion time.
• For critical path
• EST=LST and EFT=LFT
• It means we can not delay either start of finish of a critical
activity. Hence there is NO float for critical activity.
• Hence float exists for only Non-Critical Activities
Types of Floats
• Total float: It is the amount of time by which the
completion of an activity can be delayed beyond
the earliest possible finishing time without affecting
total project completion time.
• Total float=(LST-EST) or (LFT-EFT)
• =Lj - Ei - tij
Free float
• It is the amount of time by which the completion of an activity can be
delayed beyond the earliest finishing time without affecting the earliest
possible start of a subsequent activity.
• Free float= Earliest starting time of subsequent activity – Earliest
finishing time of activity ij
• = E j - ( E i+ t ij )
• =( E j - E i ) – t ij
•
Independent float
• It is the amount of time by which the start of an activity can
be delayed without affecting earliest start of subsequent
activity assuming that the preceding activity has finished at
its latest finishing time.
• Independent float =Earliest starting time of subsequent
activity – Latest finishing time preceding activity – t ij
• =( E j - L i ) – t ij
Interfering float