Integrated Solid Waste Management For Kairana, Thana & Shamli Nagar Palika, U.P
Integrated Solid Waste Management For Kairana, Thana & Shamli Nagar Palika, U.P
PRESENTED BY:
MAX ION TECHNOLOGIES, DELHI
POPULATION DETAILS (2011-19) & SOLID WASTE GENERATION
Aerobic composting occurs when C/N <50, moisture (40-50%) . Matured waste has C/N of 20-25 forwarded for
screening
PROPOSED PROCESSING & DISPOSAL PLAN
3. MONSOON SHED : The digested material from windrow pad is moved to monsoon shed for
drying.
4. MECHANICAL SIEVING:
The dried material is then fed into a rotary trammel fitted with dual mesh (25MM and 4mm holes). Final compost
of 4mm size is obtained. Rejects from the trammel sent to land fill.
NON BIODEGRADABLE WASTE ( REFUSED DERIVED FUEL)
The non bio degradable waste is segregated and forwarded to RDF peletization.
AREA RERQUIREMENTS FOR PROCESSING UNIT
The non bio degradable waste is segregated and forwarded to RDF pelletization.
A. Assumptions
Initial Waste Generation (2020) 35.6 TPD
Bulk Density of the material 0.8 T/mcube
B. Dimensions of Site
Depth of Landfill 3.00m
Total Volume required 24,305.6 M cube
Length 101.27 m
Width 80.0 m
Slope 1: 2.5
Landfill Area required for Kairana Nagar Palika 8101.87 Sq m
Landfill Area Required for Thana Bhawan Nagar 3800 sq m
Palika
The Landfill bottom shall be lined with 900mm of mineral sealing system of clay of permeability K<
10^(-9) m /s. Overlaid with 2.0mm of HDPE layer and protected by Geotextile Layer of 2000 gsm. And
on the top a 300mm gravel layer for leachate percolation.
SPECIFICATIONS FOR LANDFILL SITE
The Landfill bottom shall be lined with 900mm of mineral sealing system of clay of permeability K<
10^(-9) m /s. Overlaid with 2.0mm of HDPE layer and protected by Geotextile Layer of 2000 gsm. And
on the top a 300mm gravel layer for leachate percolation.
CUMULATIVE AREA REQUIREMENTS
S.No Name of Site Total Area Required (sqm)
1 Kairana Nagar Palika 12,201
2 Thana Bhawan Nagar Palika 5,800
3 Shamli Nagar Palika 15,761
CAPITAL COST ESTIMATION ( PART-A: PLANT &
MACHINERY)
Name of Unit / Component Capital Cost for Kairana Capital Cost for Thana Capital Cost for
S.No Bhawan Shamli
1 Weigh Bridge ( 30MT) 12,50,000 12,50,000 12,50,000
7 Vehicles
C Consumables
1 Microbial Cultures 800000
2 Hose Pipes 50000
3 Showels 23000
4 Plastic Pots 54000
5 HDPE Bags 157000
TOTAL 42,76,000
NET CAPITAL & ANNUAL O&M COSTS