6 LN562 - Topic 2.2 TRADITIONAL Cost Modelling
6 LN562 - Topic 2.2 TRADITIONAL Cost Modelling
MODELLING
BSS 512
COSTING & ESTIMATING I
COST MODELLING
It is used at all stages of design and construction process especially during early
forecasting and subsequent control of building cost
They are statistical methods and can only really be attempted if computer-assisted
•
COST MODELLING
APPROXIMATE ESTIMATING
Approximate estimating is the forecasting of the
probable cost of a future project before the building has
been designed in detail and contract particular
prepared. The approximate estimate or probable cost so
produced has two main purpose:
COST MODELLING
COST MODELLING
METHOD OF APPROXIMATE
ESTIMATING
UNIT METHOD
This method is used to estimate the cost of
building whose sized depend upon the units of
accommodation e.g. number of pupils in schools,
number of beds in hospital, number of seats in
cinema, number of car spaces for car parks etc.
COST MODELLING
UNIT METHOD
Application :
The number of units of accommodation may be given by the
building owner or otherwise determined. This number of units is
then multiplied by the unit rate per unit accommodation to arrive at
the approximate cost of the building.
Example :
If from the historical data, i.e. cost information of past projects, the
cost per pupil of schools is RM1,000/= and a proposed school to
accommodate 500 pupils is to be erected, then the approximate cost
of the proposed school will be RM1,000 x 500 = RM500,000, if
the proposed buildings in identical to the building whose unit rate
has been used.
COST MODELLING
Merit or Advantages :
a) A simple method of comparison UNIT METHOD
b) Suitable form of long term estimating for large programmes of similar
buildings where variations in individual buildings will cancel each other out
c) Provides a convenient form of stating a cost limit or budget
Demerit or Disadvantage :
a) A very rough and inaccurate method of estimating which is used mainly to
give an overall rough figure
b) Does not take variations in plan shape, storey height etc. into account
c) Does not help architect in designing as it is difficult to forecast changes in
cost due to changes in specification, design etc.
d) Works which bear no relationship to the number of units of accommodation
like external works, lifts, piling etc need to be measured and priced
separately
COST MODELLING
B
Gross floor area = (L x B) m²
L
COST MODELLING
L
COST MODELLING
1/2
1/2 600 mm
Merit or Advantages :
a)The only merit is that this estimate can be done
quickly
COST MODELLING
a) Calculate the area of the lowest floor and multiply by two that
part which is above ground level and multiply by three the
part (if any) which is below ground level (dimensions to be
taken to the inner faces of external walls)
b) Calculate the area of the roof (to be measured flat in all cases
and to the extremities of the eaves)
COST MODELLING
STOREY ENCLOSURE
METHOD
Application
c) Measure the area of each upper floor and multiply by
two further adjust each upper floor area by multiplying
by a progressive factor of 0.15 (i.e. first floor areas will
be multiplied by 2.15, second floor area by 2.30, third
floor areas by 2.45 and so on)
Basement 3.00
Basement 3.00
COST MODELLING
STOREY ENCLOSURE
METHOD
To the cost so obtained the cost of the following items must be
added where applicable:
i)Site works including roads, paths, drains, service mains and external ducts
ii)The extra cost of foundations that are more expensive than which, would
normally be provided for the type of building concerned
iii)The category of works which is sometimes loosely described as
engineering comprising sanitary plumbing and cold water, hot water, central
air conditioning, electrical installation, gas, compressed air and similar
items, lifts and escalators
iv)Features not general to the structure as a whole, e.g. boiler flues, dormers,
canopies and so on
v)Circular work
COST MODELLING
STOREY ENCLOSURE
METHOD
Advantages
a) The method provides a speed way of estimating which
ostensibly should be more realistic than the other single rate
methods of estimating as it attempts to account for differences
in shape, size and height of buildings. Differences in the price
rates of different buildings will truly reflect differences in
specification
a) The storey enclosure unit rates are seldom published as buildings are
usually not analysed this way so there is not enough data from which
an appropriate unit rate may be chosen. Also a large number of
buildings would have to be analysed before price rates could be used
with assurance
d) The price rate, while linked to areas of the vertical and horizontal planes,
is still an abstraction to a large extent and is not capable of calculated
adjustments for differing specifications and quality standards. With
very little extra effort the measurements for various sections of the
building could be dealt with separately, thus allowing calculated and a
realistic prices to be used
COST MODELLING
APPROXIMATE QUANTITIES
METHOD
Generally regarded as the most reliable method of approximate as it
uses a short cut method of preparing and pricing a bill of quantities.
Application:
The method consists of measuring out the quantities in preparing
bill of quantities but as the estimate has to be prepared in a relatively
short time, short cuts have to be taken. Generally these short cuts
consist of measuring composite item i.e. using one set of dimensions for
a number of items, of ignoring the smaller and labour only items, of
taking dimensions to the nearest six inches and of ignoring all but the
largest deductions. Measurements would be taken gross overall and
doors, windows, roof lights and similar items would be measured as
“extra over”.
COST MODELLING
APPROXIMATE QUANTITIES
METHOD
The pricing of the composite items is based on current prices of measured
rates plus an addition to cover the items not specifically measured.
Preliminaries and contingencies are treated as a percentage addition to
the total.
Example per m² : RM
100mm hardcore 9.50
50mm sand 2.50
Polythene 2.80
150mm concrete @ RM125/m³ 18.75
F42 steel fabric 4.25
50mm screed 4.00
FINANCIAL METHOD
The advantage of this method is that it helps to ensure a
profitable investment for the developer.
The pyramid
Labour, plant
Resources Material, supervision
COST MODELLING