LESSON 5 Process Selection Design and Analysis
LESSON 5 Process Selection Design and Analysis
SOLUTION
U= 40/(30x2)=0.67 OR 67%
Solution
The labor utilization at this inspection station is calculated to be 40/(2 × 30) = 67%. If the utilization rate is
85%, we can calculate the target service rate by solving the equation:
85% = 40/(2 × SR)
1.7 × SR = 40
SR = 23.5 printers/hour
Little’s Law
https://youtu.be/2Lx7QtaPDKw
• Flow time, or cycle time, is the average time it takes to complete
one cycle of a process.
• Little’s Law is a simple formula that explains the relationship
among flow time (T), throughput (R ), and work-in-process (WIP ).