SAP DSN Service PackagingV2

This document provides guidelines for partners to rapidly deploy SAP's Digital Supplier Network solution. It outlines typical project timelines and resource requirements for light, basic, and standard implementations. Light implementations focus on material purchase orders and can take 3-6 weeks. Basic implementations add order confirmations and shipment notices, taking 4-8 weeks. Standard implementations include invoices and additional transactions, requiring 8-13 weeks. The document also describes common consultant roles and a responsibilities assignment matrix to guide project planning.

Uploaded by

smail mahjoubi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
98 views11 pages

SAP DSN Service PackagingV2

This document provides guidelines for partners to rapidly deploy SAP's Digital Supplier Network solution. It outlines typical project timelines and resource requirements for light, basic, and standard implementations. Light implementations focus on material purchase orders and can take 3-6 weeks. Basic implementations add order confirmations and shipment notices, taking 4-8 weeks. Standard implementations include invoices and additional transactions, requiring 8-13 weeks. The document also describes common consultant roles and a responsibilities assignment matrix to guide project planning.

Uploaded by

smail mahjoubi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 11

SAP Digital Supplier Network

Service Packaging & Resourcing Guidelines

March 2020

Internal I Partner
Rapid Deployment Service Offering for SAP Digital Supplier Network

This deck is a guideline based on our experiences selling and implementing SAP Supplier Network with
multiple PARTNERS; in multiple REGIONS; across different INDUSTRIES.

Objectives for this presentation:


 Profiles of consultants
 Provide typical flavors of delivery requested by customers
 Estimated effort estimation and timeline
 Best practices for your Rapid Deployment Services Package:
1-pager, PPTX, SOW

Your SOW should be ready to send on a moments notice!

INTERNAL | SAP AND PARTNER USE ONLY


The Path to the Intelligent Enterprise is paved with Digital

Integration
Native integration with
Supplier S/4 Hana / ECC

Order Advanced
Invoice
Confirmation Shipping Notice Smart
120+ Business
Rules
SAP Supplier Portal
Free
To join & transact on
Purchase Goods Receipt Invoice Remittance Standard Supplier
Order Notice Status Advice
SAP S/4 Hana or SAP ECC Supply Chain
Expandable to 50+ supply
chain transactions

INTERNAL | SAP AND PARTNER USE ONLY


Deployment Methodology

Prepare Explore Realize Deploy

1-3 week(s) 1-3 week(s) 1-5 week(s) 1 week


 Confirm Goals and Scope*  First Connectivity  Customizations /  Production Setup
 Project Team* (Handshake) Extensions  SAP Help Portal
 Technical Checklist*  Design Workshops  User Acceptance Testing
 IT security clearance*  Initial Cloud Integration
Gateway (CIG) and
 SAP access / Install Prep*
Network Configurations
Supplier Enablement Best Practices*
 Supplier Matching*
1. Create a Strategy
Kickoff
Go-Live
2. Create the Communication Plan
*may start prior to kickoff 3. On-the-job training with Customer Champion
INTERNAL | SAP AND PARTNER USE ONLY
Profiles of consultants

Project Manager Functional Consultant Technical Consultant

• Experience with Cloud • SAP functional knowledge • Basis - needed for installation
applications (PO, INV creation, supplier steps (one-off)
creation etc) and / or
added bonus:
and / or • ABAP - for customer exists and
• Knowledge about Supplier BADI
Enablement • Ariba Network knowledge
(business transaction rules, and / or
mobile app knowledge, how • PI/PO profile or CIG knowledge
supplier account looks like,
to perform the mapping
PO print)

INTERNAL | SAP AND PARTNER USE ONLY


Project Timelines

3 most common Scenarios requested by Customers:

Light Basic Standard

 Material PO
 Material PO
 Order Confirmation
Scope  Material PO  Order Confirmation
 Ship Notice
 Ship Notice
 Invoice
Partner Experience Est Deployment Time

1-2 Deployments 6 weeks 8 weeks 13 weeks

3-4 Deployments 4 weeks 5 weeks 10 weeks

5+ Deployments 3 weeks 4 weeks 8 weeks

Service POs recommended to be delivered after go-live

INTERNAL | SAP AND PARTNER USE ONLY


Effort Estimation

Light Scope Basic Scope Standard Scope


Activity Description
Days Days Days
Prepare Gather Data & Kickoff 6 8 8
Explore Ariba Network Account Configurations 1 2 4
Realize System Integration & Testing Support 2 10 16
Realize Admin & User Training 2 2 2
Deploy Go-live Support 1 1 2
Supplier Enablement Strategy, Communication, Testing 6 12 14
TOTAL 12 days 23 days 32 days

Key qualifications to determine scope:


 Documents in scope
 # of Invoices
 # of AP people
 # of suppliers with 100+ transactions
 ERP Backend
 S4 customizations

INTERNAL | SAP AND PARTNER USE ONLY


R = Responsible
A = Accountable
C = Consulted

Delivery Teams RACI Matrix I = Informed

Phase Activity Partner SAP


Prepare Ensure Customer / Partner Ariba Network Account is specified and created as per contract I R

Prepare Provide links to Product Documentation and Downloads for Partner / Customer to consume I R

Prepare Kickoff Project, Review Scope and plan Timing with the Customer R A

Explore Provide Overview of Ariba Network configuration and Technology to Customer R I

Explore Review Standard Approach to Mapping with the customer. R I

Explore For each business process, capture and define any custom mapping required R I

Explore Capture Ariba Network Customizations Required for Purchase Order and Invoice R I

Explore Review Ariba Network Configuration and Capture customer specific requirements R I

Explore Develop Supplier Enablement Plan R I

Realize Build and unit test configuration and custom interfaces for ERP and CIG R I

Realize Build and unit test AN Customizations Required C R

Realize Develop System Test Plan R I

Realize Execute System Test Plan R C

Realize Develop User Acceptance Test Plan R I

Realize Execute User Acceptance Test Plan R C

Prepare production cut over checklist for Ariba activities. Migrate Code to Production. Facilitate transition to Ariba
Deploy R C
Customer Support. Support Customer with major production issues for up to two (2) weeks after Go Live.

INTERNAL | SAP AND PARTNER USE ONLY


Market Message: Our leading Partners are vetted & ready with an SOW

 Partners have “pre-packaged” offerings


 1-pager Brochure
 Standard Deployment Proposal
 SoW Template to be signed

 Implementations starting from $25K

 Standard Deployment is 3 – 12 weeks

 Works with:
 ECC 6
 S/4 Hana Cloud
 S/4 Hana On Prem

 ECC Move – first S4 move for ECC Customers


to Intelligent Enterprise

INTERNAL | SAP AND PARTNER USE ONLY


Call to Action

1. Develop your own Rapid Deployment Service Package:


 1-pager overview
 PPTX with your commercials
 SOW template

2. Nominate your ECC & S/4 Install Base Customers for SAP Digital Supplier
Network to start their Digital Journey

3. Get prepared for the deployment – Consultants to complete the SAP


Digital Supplier Network Consultant Learning Program

INTERNAL | SAP AND PARTNER USE ONLY


Android