Unit 4 Mix Proportioning
Unit 4 Mix Proportioning
MIX PROPORTIONING OF
CONCRETE
Concrete Mix Design
Materials cost
• Attention is mainly directed to the cost of materials – particularly
cost of cement and admixtures.
• Cement used should be as minimum as possible (Minimize
cement)
Designing Concrete Mixtures
There are three phases in the development of a concrete mixture:
specifying, designing, and proportioning
Objective of Mix Proportioning
TABLE 3 OF IS 383
Estimation of Fine and Coarse Aggregate Contents
With the completion of procedure all the ingredients have been
estimated except the coarse and fine aggregate content. These quantities
are determined by finding out the absolute volume of cementitious
materials, water and the chemical admixture; by dividing their mass by
their respective specific gravity, multiplying by 1/1000 and subtracting
the result of their summation from unit volume (excluding the volume
of entrapped air). The values so obtained are divided into coarse and
fine aggregate fractions by volume in accordance with coarse aggregate
proportion already determined. The coarse and fine aggregate contents
are then determined by multiplying their volume with their respective
specific gravities and multiplying by 1000.
1.Estimation of coarse aggregate proportion
• Table -3 is for water cement ratio of 0.5, proportion may be suitably adjusted for
other water cement ratio.(@-or+.01 for every change in water cement ratio of .05)
• For given workability ,the volume of coarse aggregate depends upon its nominal
max size and grading zone of fine aggregate.
• Reduce the estimated CA content by 10% if pumping is to be done. It should be
consistent with IS 456
2.Estimation of Fine aggregate Proportion
• Find out the absolute volume of cementitious material, water and chemical
admixture by dividing their masses by their respective specific gravity and multiplying
by 1/1000.
• Subtract the result of summation above from unit volume. Find volume of total
aggregates
• Divide coarse and fine aggregate fractions by volume as per clause 4.4.
• Find CA and FA by multiplying their volumes with respective specific gravities and
multiplying by 1000.
Calculation of aggregate content (FA and CA)
• All the selected materials were collected and checked for any discrepancies.
Cement is checked for lumps, aggregates for moisture content.
After that, cement was also added to the mixer and water is gradually added
and simultaneously the mass is thoroughly mixed for 2 minutes.
Then the concrete mass is poured into the concrete tray. Slump/workability of
concrete is checked using slump cone test.
The cube moulds are oiled to prevent sticking of concrete and ensuring a
smooth surface. Concrete is then poured into the moulds.
After one day, the moulds are opened and the cubes are placed in water pond
for curing till they are tested.
Results and Discussion
Compressive Strength
Test Results
Mix /result M1 M2 M3 M4 M5
7days
28Days
With the use of super-plasticizers, the strength is achieved earlier as compared to mix design not
using Super-Plasticizers. Thus, the target was taken to be 25 MPa for 7 days and 35 MPa for 28
days.
Figure shows the comparison of the compressive strength results
achieved with their respective targets. While M1 and M3
achieved the target strengths, M4 struggled to keep up with the
target which gives a clear indication that presence of too much
water content with plasticizer has an adverse effect on the results.
Meanwhile, M2 and M5 showed satisfactory compressive
strengths that too in early stages of tests advocating the use of
super-plasticizers and clearly showing the benefits.
Cost Analysis
A cost analysis was done for all the five mix proportions and an excel
program was made to compare the costs. The basic costs were taken from
the DAR Civil (Delhi) 2016 for cement, coarse aggregates and sand. For
super plasticizer, the cost incurred for buying the specific brand was
taken. Table 1 shows the costs of constituents of concrete. Table 2 shows
the cost of the mix designs per cubic meter of concrete. Figure gives the
graphical representation of costs of mix design of table 2.
Figure : Graphical Representation of cost Analysis
Table 1: Cost of Materials
FA 1200 1 m3 3.36
CA 1300 1 m3 3.53
While ACI (M2) mix design with super-plasticizer has more cost
than the IS(M5) mix design with super-plasticizer, the IS mix
design showed better results both at the age of 7 days and 28 days
which gives IS mix design a clear edge over the ACI mix design for
both economy and test results.
Now, ACI and IS mix designs for M35 which will give
approximately same strength are compared to M30 mix designs
with super-plasticizer. Though the ACI M35 and IS M35 are more
cost-effective than M2 and M5 respectively, it is anticipated that
they will gain strength later than M2 and M5, thus increasing the
time of construction, but if the time of construction is not
necessary than ACI M35 and IS M35 should be preferred.
Between ACI M35 and IS M35, ACI M35 should be chosen as
ACI mix designs give better results without super-plasticizer.
1. ACI mix design gives better results without super-plasticizers with a small compromise on cost.
2. IS mix design gives better results with PCE based super-plasticizers and gives better results and is also better
economically.
3. Maintaining the same water to cement ratio while using super-plasticizers can lead to poor results as the
super-plasticizers are meant to reduce water content and increase workability. Thus, the mix design with same
water to cement ratio as the initial design using IS mix design failed to show satisfactory results.
4. Water content has a direct relationship with time of setting and strength gained at age of 7 days (initial
strength). Less is the water content, more is the initial strength and satisfactory workability can be attained
with the help of super-plasticizer.
5. PCE based super-plasticizers are a practical choice for gaining more initial strength and speeding up the
construction but are costlier than the counterparts of more design strengths that provide comparable strength
at later stages such as at the age of 28 days.
THANK YOU