Group 3 Composite Sections
Group 3 Composite Sections
COMPOSITE SECTIONS
Faculty:
Presented by:
Dr. Senthilkumar R 1.ARUN KUMAR H-203221004
2. CHALLA GANESHSIVAKUMAR - 203221007
3. Kotha Vineeth -203221011
4. Rohit Dhanawade – 203221020
5. Muhammed Riyas KP – 203221015
INTRODUCTION
A composite beam is one whose cross-section consists of two or more elements of different materials ,
acting together while carrying some or all the loads
Composite prestressed concrete consists of precast prestressed beams and cast in situ concrete which
behaves as a monolithic unit under service loads
Tensile zone – high strength concrete
Compression zone – lower strength concrete
Depending on the stiffness, the precast member can be designed to carry the weight of the in situ
concrete or can be propped , so that it carries only its self weight during casting
Composite action achieved by –
1. Roughening of surface of the prestressed unit
2. stirrups protruding from prestressed unit
Differential shrinkage between the concrete cast in situ and prestressed unit –
also helps in monolithic action
Box girder bridge deck with precast webs and bottom flange
and CIP slab; Top: Aerial view, Bottom: Close-up view
ADVANTAGES
An increase in the cross-section area of the section results in higher stiffness of the
Due to the higher stiffness, it reduces the deflection of prestressed composite beams
DISADVANTAGES
Designers need to pay more attention to the design procedures as they are a bit complex
than the usual method. The correct idealization of the actional condition should be done
Due to the composite slab, there will restrain resulting in an increase of prestress losses.
Propped construction
The dead load stress developed in precast pestressed units can be minimized by propping them while
casting the Concrete in situ
Unpropped construction
If the precast units are not propped while placing the in situ concrete , stresses are developed in the
unit due to the unit due to the self weigh of the member and dead weight of the in situ concrete
ANALYSIS OF PRESTRESSED COMPOSITE SECTION
• The analysis of a composite section depends upon the type of composite section, the stages of
prestressing, the type of construction and the loads.
• The type of construction refers to whether the precast member is propped or unpropped during
the casting of the cast in situ portion.
• If the precast member is supported by props along its length during the casting, it is considered
to be propped.
• If the precast member is supported only at the ends during the casting, it is considered to be
unpropped.
• If the precast web is unpropped during casting of the flange, the section does not behave like a
composite section .
• If the precast web is propped during casting and hardening of the flange, the section behaves
like a composite section to carry the prestress and self weight after the props are removed.
Stress profile (i) UNPROPPED type
Stress @ service
The stress profile is extended up to the top of the flange. When the member is
placed in service, the full section carries MLL.
Stress profile (ii) PROPPED type
Stress @ service
The stress profile is extended up to the top of the flange. When the member is
placed in service, the full section carries MLL.
FLEXURAL STRENGTH
• The ultimate strength of the composite prestressed sections in flexure is governed by same principles
used for ordinary prestressed sections
• The prestressed composite section is generally under reinforced
• The compression zone generally consists entirely of insitu concrete of lower compressive strength
• However if the compression zone contains part of precast element then average compressive strength
has to be used
Mu = fpu * Ap(d-0.42xu)
Shear strength of composite sections
According to the American code ACI 318-1989, the horizontal shear stress at the interlace for the ultimate
limit state is computed using the expression
The permissible values of the horizontal shear stress for different types of contact surfaces is specified as:
1. 0.6 N/mm², when ties are not provided and the contact surface of the precast element is free of
laitance and intentionally roughened to an amplitude of 5 mm.
2. 2. 0.6 N/mm², when minimum vertical ties, according to section 8.3.3, are pro vided and the contact
surface is not roughened.
3. 3. 2.5 N/mm², when minimum vertical ties are provided and the contact surface is roughened to an
amplitude of 5 mm.
4. 4. When shear stress exceeds 2.5 N/mm², then shear friction reinforcement is to bedesigned and the
required area of reinforcements is given by
= characteristic tensile strength of the reinforcement
φ =capacity reduction factor having a value of 0.85 for shear computations
u= coefficient of friction having the following values:
The ties consisting of single bars, multiple-leg-stirrups or vertical legs of welded wire-fabric should have a spacing
not exceeding four times the least dimension of the supported element, nor 600 mm, whichever is less.
DESIGN PROCEDURE
• Based on satisfying the allowable stresses under service loads and at
transfer
• Section is then analysed for ultimate loads to satisfy the limit state of
collapse
• Member is also checked to satisfy the criteria of limit states of
serviceability, such as deflection and crack width (for Type 3 members only)
• A trial and error procedure is adopted for the design
the type of composite section and the stages of prestressing need to be
decided first
calculation of the initial prestressing force (P0) and the eccentricity of the
CGS (e) at the critical section
DESIGN STEPS
• Section with precast web and cast-in-place flange
• Considered to be Type 1 member
Step 1. Compute e
• Zero stress at the top of the precast web - economical solution
emax
Stress profile for maximum eccentricity of CGS
C t” ft
ft
Ct ’
CGC’
fb
Cb ’
fb
bw
Composite section Stress profile
ct’ = Distance of the top of the precast web from the CGC’
ct” = Distance of the top of the composite section from the CGC’
cb’ = Distance of the bottom of the precast web (or composite section) from the CGC’
I ’ = Moment of inertia for the composite section
mt mb
ft
fb
where,
A = Area of the precast web
kb = Distance of the bottom kern of the precast web from CGC
kt = Distance of the top kern of the precast web from CGC
or, Pe
• Prestressing force is acting only on the precast web and hence, e is the
eccentricity of the CGS from the CGC of the precast web
Step 4. Estimate Po
a) 90% of the initial applied prestress (Pi) for pre-tensioned members
b) Equal to Pi for post-tensioned members
Pi = Ap(0.8fpk) Ap = Pe / 0.7fpk
• At transfer,
fb
• At service,
ft
ft’
Generally, Shrinkage strain = 100μ (British code BS: ) used for computing shrinkage
stresses, when exact data is not available.
A reasonable estimation of stresses developed due to differential shrinkage may be made
using the following assumptions:
1. the shrinkage is uniform over the in situ part of the section, and
2. effect of creep and increase in modulus of elasticity with age and the component of
shrinkage, which is common to both the units, is negligible.
DIFFERENTIAL SHRINKAGE
Method of Computing Stresses :
1. the in situ cast slab is first allowed to undergo the full amount of differential shrinkage
i.e. strain
Precast element ,
2. Tensile forces of intensity are then applied to each end acting at the centroid of the
cast in situ slab so that the slab is restored to the length of the precast element.
DIFFERENTIAL SHRINKAGE
Precast element
Consequently the uniform tensile stress induced in the in situ concrete is , and the
magnitude of the tensile force is computed as =where
= area of the in situ concrete section
= modulus of elasticity of the in situ concrete
The composite member is in a state of internal equilibrium without any external forces
acting on it. Hence the tensile force must be balanced by the application of a compressive
force of equal magnitude along the same line.
DIFFERENTIAL SHRINKAGE
The compressive force applied at the centroid of the cast in situ slab is equivalent to a
direct compressive force acting at the centroid of the composite section together with a
bending moment which will induce direct and bending stresses in the composite section.
These stresses are superposed on the existing tensile stresses in the cast in situ slab to
compute the final stresses.
+
Cast in situ slab +
-
Equivalent direct compressive force Direct Bending
stress stress
DIFFERENTIAL SHRINKAGE
Precast element +
-
Limits of Deflection :
• The total deflection due to all loads, including the effects of temperature, creep and
shrinkage, should not exceed span / 250.
• The deflection after erection of partitions or application of finishes, including the effects
of temperature, creep and shrinkage, should not exceed span/350 or 20 mm, whichever
is less.
• If finishes are applied, total upward deflection due to prestressing force should not
exceed span/300.
Contributions of members
1 .Krishna Raju, N., Prestressed Concrete, 3rd Edition, Tata McGraw-Hill Publishing Company Ltd.,
1998.
2. NPTEL notes
3. Lin, T. Y. and Burns, N. H., Design of Prestressed Concrete Structures, 3rd Edition, John Wiley & Sons, 1982.
Thank you