PDF Power Grid On Well Foundation
PDF Power Grid On Well Foundation
to
Power Grid Corporation of India Limited, Gurgaon
D
ate: 8th February 2010
Well Foundations in India
Introduction
⚫ In large parts of India, well foundations are
commonly adopted for bridges
⚫ Design and construction practices have been
progressively streamlined to cater for ever‐increasing
loads and foundation depths
⚫ With the introduction of large spans, the well size
also increases. For Second Hooghly Bridge, 24 m dia
wells have been adopted. The deepest well so for
constructed in India is up to 70 m below WL
Well Foundations in India
Introduction
⚫ Daring efforts are on in different parts of the world
to build bridges on a very large scale
⚫ Even bridges between continents are in
process, America‐ Asia, Europe‐Africa for
example
⚫ In India hundreds of thousands of bridges have
been constructed during the twentieth century
⚫ During the first decade of this century, about
Rs.100,000 cr are expected to be spent on
Bridges
⚫ Foundations cost 50 % or more
Use of Well Foundation
Introduction
⚫ Past Experience making it more reliable and
dependable by virtue of default choice
⚫ Well foundations are more suitable for deep water
where it is difficult to carry construction
equipment like River/Creek Bridges
⚫ Intake Structures, offshore as well as river
⚫ Deep foundation and suitable for alluvial soil
which mainly consist of Sandy
⚫ No special equipment and heavy machineries are
required
Use of Well Foundation
Introduction
⚫ Used in India and Indian Sub‐continent only
⚫ Well Foundation is preferable to pile foundation if it
has to resist large horizontal forces
⚫ Well foundation is more suitable for deep water
where it is difficult to carry construction equipment
⚫ Well Foundation is meant for deep foundation where
the river bed gets scoured and forces need to be
transferred to deeper level.
Pile Foundation Vs Well Foundation
Item Pile Foundation Well Foundation
⚫ Cutting Edge
⚫ Well Curb
⚫ Bottom Plug
⚫ Steining
⚫ Sand Filling
⚫ Top Plug
⚫ Intermediate Plug
⚫ Well Cap
Input Data
dsm 1.34 b
k sf
⚫ This “mean scour depth” is used to calculate
Maximum scour depth to account local scour effect
⚫ For Pier foundations : 2 x dsm from HFL
⚫ For Abutment foundations: 1.27 x dsm from HFL
⚫ Grip Length: The minimum depth of foundation
below scour level is 1/3 rd of Maximum Scour
Depth
Depth of Well Foundation for Rock
Bell
Correction
Side Earth Resistance – F.O.S.
Required 40 kg/meter
Well Curb
⚫ Minimum resistance while being sunk.
⚫ Strong enough to transmit forces from steining to
the bottom plug
⚫ Minimum reinforcement = 72 kg/m3
⚫ Internal angle of curb shall be kept in between 30 degree
to 37 degree.
Well Curb
Well Curb
Well Curb
Bottom Plug
SAND
FILLING
Bottom Plug
Well Cap
Conventional Construction on
General Details
Caisson Aligned at location
First lift of concrete poured
Shifting of
concrete over
Barge
Concrete placing
Build next lift of Caisson
Caisson
Fabrication Yard
Launching of
Caisson
Well Caisson Launching
Sinking in
progress
SECOND HOOGHLY BRIDGE
Enabling works for caisson sinking
JOGIGOPHA BRIDGE
Slipway for Floating Caissons
Jogighopa Bridge
Slipway for Floating Caissons
Jogighopa Bridge
Floating Gantry for Handling Caissons
Floating Caisson being
Towed to Location
Colcrete
arrangemen for
foundation
Jack Down Method
Well Sinking By Jack Down Method
Well Sinking By Jack Down Method
Well Sinking By Jack Down Method
Well Sinking By Jack Down Method
Pneumatic Sinking
Pneumatic sinking
• In this method airtight cover is fixed on dredge hole and compressed air is pumped in, so that water
is pushed out of well up to cutting edge level.
• Men are sent inside to carryout manual excavation. Muck is removed through shaft without
releasing pressure.
. . .Contd.
Sinking
Kali Bridge – Pneumatic Sinking
Kali Bridge – Pneumatic Sinking
Limitations
. . . contd
Limitations
Sinking a Pylon
CASE STUDY
Jogighopa Bridge
CASE STUDY
Jogighopa Bridge
Brahmaputra Bridge, Jogighopa, 2.28 km
3.5 m
1.5 m
50 m
2.5 DRILL PIPE WITH AIR
CONTROL VALVES
m
WORKING PLATFORM
RC PLUG
18
CASING
m
DRILL PIPE STABILIZER
PLAN + 35.00 m
CAISSON STEINING
SAR 6 Y2k
CASE STUDY
Passighat Bridge
Passighat Bridge, Arunachal Pradesh
Well Foundation
design
Boulder
dredged
during
well
sinking
SAR 6 Y2k
Fig: 1 : PASSIGHAT
BRIDGE
LEGEND
Narmada bridge,
Constructability Chandod
Well cap 14 m below
water
4/2/2010
Floating Batching Plant
Concrete cofferdam being towed to location
Cranes for Concreting and Dredging
4/2/2010
Floating arrangement for Batching Plant
Concrete pump and placer boom
GANGA BRIDGE AT PATNA
Floating crane for well sinking
Well sinking by cranes and
grabs
SECOND HOOGHLY BRIDGE
Enabling works for caisson sinking
Correction of Tilt and Shift
Well sinking ;Tilt correction
Concrete Kentledge blocks
Kentledge for Well Sinking
Well sinking ;Tilt correction
Platform for concrete kentledge
Tilt Rectification of Wells
Tilt Rectification of Wells
Tilt Rectification of Wells
Tilt Rectification of Wells
Tilt Rectification Platform for Well Foundation
Tilt Rectification Platform for Well Foundation
4/2/2010
Kandroor Bridge across Sutlej - Badly
tilted well being corrected
SAR 6 Y2k
Kandroor Bridge
SAR 6 Y2k
Select IRC Papers reporting Well
Foundation Problems
⚫ IRC Paper 253 ‐ Rupnarayan Bridge, West Bengal
293 ‐ Bassein Creek Bridge, Mumabi
314 ‐ Godavari Bridge, Maharashtra
328 ‐ Bhakla Bridge, UP
359 ‐ Haldi Bridge, WB
400 ‐ Hasdeo Bridge,
Champa, MP
434 ‐ Tapi Bridge, Idgaon, Maharashtra
464 – Kalyani Bridge, WB
⚫ Indian Highways, Dec 1982, Arjun Khola Bridge,
Nepal
Conclusion