Module-3 Capital Budgeting
Module-3 Capital Budgeting
• Example:
(1) Setting up of factories.
(2) Installing a machinery.
(3) Increase in production capacity.
Why are CB decisions are important?
(1) Long term growth and effects
(2) Large amount of funds involved
(3) Risk involved
(4) Irreversible decisions.
Types of CB decisions
(I) On the basis of firm’s existence
A. Replacement decisions
Replacing fixed assets due to expiry of its economic life.
B. Modernisation decisions
Replacing fixed assets due to its technological obsolescence.
C. Expansion decisions
Increasing existing production capacity.
D. Diversification decisions
Commencing new product/service lines.
Types of CB decisions…….continued
(II) On the basis of decision situation
where,
Average Investment = ½ (Original cost – Salvage Value) + Salvage Value+ Working Capital
Rule:
Accept the project if ARR is greater than and equal to minimum acceptable rate of
return.
Q1. Calculate Average rate of return of project:
Annual Earning after tax
Year Annual EAT
1 35,000
2 40,000
3 30,000
4 35,000
Note:
In case of Equal Annual Cash Inflows
Sol:
Q3. Calculate payback period:
Cost of project is Rs.1,00,000
Life of project is 5 years
Following are Cash flow after tax:
Year CFAT
1 20,000
2 30,000
3 35,000
4 15,000
5 20,000
Q4. Calculate payback period:
Cost of project is Rs.1,50,000
Life of project is 5 years
Following are Cash inflow after tax:
Year CFAT
1 30,000
2 40,000
3 35,000
4 35,000
5 40,000
Q5. Calculate payback period: Payback period = 3 years , (2,50,000-1,85,000) *12
Cost of project is Rs.2,50,000 1,00,000
Life of project is 5 years
Following are Cash flow after tax:
Year CFAT Cum CFAT
1 40,000 40,000
2 60,000 1,00,000
3 85,000 1,85,000
4 1,00,000 2,85,000
5 1,25,000 4,10,000
Q6. Calculate payback period:
Cost of project is Rs.5,00,000
Life of project is 5 years
Following are Cash flow after tax:
Year CFAT
1 1,00,000
2 1,20,000
3 1,40,000
4 2,00,000
5 1,50,000
We have studied two non
discounting capital budgeting
techniques: ARR and Payback
Period.
Lets study discounting techniques. Present value
factor table will be used.
Discounted Payback Period
• It is the period within which the entire cost of the project is expected
to be completely recovered by way of discounted cash inflows.
Q1. Calculate discounted payback period:
Cost of project is Rs.50,000
Life of project is 5 years
Cost of capital is 10 %. (Discounting rate)
Following are Cash inflow after tax:
Year CFAT
1 20,000
2 25,000
3 30,000
4 35,000
5 50,000
Q2. Calculate discounted payback period:
Cost of project is Rs.1,00,000
Life of project is 5 years
Cost of capital is 10 %
Following are Cash inflow after tax:
Year CFAT
1 25,000
2 50,000
3 75,000
4 100,000
5 50,000
Q3. Calculate discounted payback
period:
Cost of project is Rs.5,00,000
Life of project is 5 years
Cost of capital is 10 %
Following are Cash inflow after tax:
Year CFAT
1 1,25,000
2 1,00,000
3 1,75,000
4 2,00,000
5 2,50,000
Net Present Value
• It is very important capital budgeting technique.
• It is defined as the difference between present value of cash inflow
and present value of cash outflow.
NPV = PVCI-PVCO
where, NPV is Net present value of project.
PVCI = Present value of Cash Inflow
PVCO= Present value of cash outflow.
Project B
Cost of project = 8,50,000
Year CFAT
1 1,50,000
2 2,50,000
3 2,20,000
4 1,75,000
5 2,80,000
Profitability Index
• It is defined as the ratio of present value of cash inflow and present
value of cash outflow.
PI = PVCI
PVCO
where, PI is Profitability Index.
PVCI = Present value of Cash Inflow
PVCO= Present value of cash outflow.
• Internal rate of return is the rate of return earned on the initial investments
made in the project.
Where,
L = Lower Discounting rate
H= Higher discounting rate
NPVL = Net present value at lower discounting rate
NPVH = Net present value at higher discounting rate
IRR = Internal rate of return