Estimation of Building
Estimation of Building
PROJECT REPORT
BY
PRASANTH.P
(09B95A0104) SANJEEV.D
(08B91A0114) YASESVI.K
(08B91A0111) RAHUL.A.J
(08B91A0107)
1
1. INTRODUCTION:
It may be noted that the client (or owner) organization and contracting agencies draw up
their own estimates from the information and data available to them. Also, for different
purposes, the required precision in the estimates is different-for example, for budgetary
purposes an owner may be happy with even 10 percent variation, but such an error for a
contractor bidding for the job could be simply disastrous and unacceptable. There is, thus,
a clear difference in perception towards estimation in the client and contracting
organizations. An effort has been made to bring the various issues in client’s estimation
of project cost .
It is obvious that the accuracy of an estimate can be improved once the nature of the
project is clearly defined, and all quantities, quality of material and workmanship.
Logistics etc, are well understood,. Since this is often not the case, ru.0le of thumb and
approximate methods have also evolved, and reference has been made to some of the
more commonly used approaches at appropriate places. For building works, for example,
where as approximate estimates are at times drawn up on the basis of plinth area, floor
area, enclosed volume, length of the wall, etc…,detailed estimates wood require
specifications, program of works, available drawings, materials, manpower and
equipment, productivity, and the indirect costs .
2
ESTIMATE
As a project is proposed and then developed, the estimate preparation and information
will change based on the needs of the Owner/Client/Designer. These changes will require
estimates to be prepared at different levels during the design process with increasing
degrees of information provided. It should also be noted that within each level of estimate
preparation, not all portions of the design would be at the same level of completeness.
For example, the architectural design may be at 80% complete while the mechanical
design is only 50% complete. This is common through the design process, but should
always be noted in the estimate narrative.
The following descriptions constitute the different levels of an estimate. Estimates within
each of these levels may be prepared multiple times during the design process as more
information
Becomes available or changes are made to the scope. As the level of the estimate
increases it will become more detailed as more information is provided; "unknowns" are
eliminated; fewer assumptions are made; and the pricing of the quantities become more
detailed. Contingencies for the aforementioned will be reduced as more design
documentation is produced
COST ESTIMATES
Construction cost constitutes only a fraction, though a substantial fraction, of the total
project cost. However, it is the part of the cost under the control of the construction
project manager. The required levels of accuracy of construction cost estimates vary at
different stages of project development, ranging from ball park figures in the early stage
to fairly reliable figures for budget control prior to construction. Since design decisions
made at the beginning stage of a project life cycle are more tentative than those made at a
3
later stage, the cost estimates made at the earlier stage are expected to be less accurate.
Generally, the accuracy of a cost estimate will reflect the information available at the
time of estimation.
Numerous estimating techniques prevail in the market and these can be categorized in the
following ways:-
6. Conceptual estimates
7. Detailed estimates
Conceptual estimates
Basic parametric sizes are used for the type of building to reach an order of
magnitude estimate. Quantities do not play a large role. Historical Ratios are used to
establish a cost per unit. Basic scopes for trades are established.
4
Detailed Estimate
A detailed estimate is the most accurate form of estimate. This type of estimate is set
up to find out the quantities and costs of everything for a project. These types of
estimates help contractor to complete a construction successfully. A detailed
estimate is arranged in the following two ways :-
(a). Unit quantity method
(b). Total quantity method.
5
The total quantities of each kind or class of material or labor are established and
multiplied by their individual unit cost. The cost of plant, overhead expenses and
profit are decided in the same way. The costs of all the five sub-heads are added to
provide the estimated cost of the item of work.
Uniform at, Master Format, WBS (work breakdown structure) are all integral parts of
providing any of these types of estimates
6
PROCEDURE OF ESTIMATING OR METHOD OF ESTIMATING.
Estimating involves the following operations
1. Preparing detailed Estimate.
2. Calculating the rate of each unit of work
3. Preparing abstract of estimate
2. Specifications.
3. Rates.
4. DRAWINGS
If the drawings are not clear and without complete dimensions the preparation of
estimation become very difficult. So, It is very essential before preparing an estimate.
2. SPECIFICATIONS
a)General Specifications: This gives the nature, quality, class and work and materials in
general terms to be used in various parts of wok. It helps no form a general idea of
building.
b)Detailed Specifications: These gives the detailed description of the various items of
work laying down the Quantities and qualities of materials, their proportions, the method
of preparation workmanship and execution of work.
3. RATES:
For preparing the estimate the unit rates of each item of work are required.
7
FLOW CHART COMPLETE ESTIMATE:
Most of people think that the estimate of a structure includes cost of land,
Cost of materials and labour, but many other direct and indirect costs included and is
shown below.
8
LUMPSUM:
9
METHODS OF TAKING OUT QUANTITIES:
The quantities like earth work, foundation concrete, brickwork in plinth and
Superstructure etc., can be workout by any of following two methods:
a) Long wall - short wall method
b) Centre line method.
c) Partly centre line and short wall method.
10
TYPES OF ESTIMATES
DETAILED ESTIMATE:
The preparation of detailed estimate consists of working out quantities of various
items of work and then determines the cost of each item. This is preparedin two stages.
i) Details of measurements and calculation of quantities:
The complete work is divided into various items of work such as earth
Work concreting, brick work, R.C.C. Plastering etc., The details of measurements
are taken from drawings and entered in respective columns of prescribed
proforma. the quantities are calculated by multiplying the values that are in numbers
column to Depth column as shown below:
11
ii) ABSTRACT OF ESTIMATED COST:
The cost of each item of work is worked out from the quantities that already computed in
the details measurement form at workable rate. But the total cost is worked out in the
prescribed form is known as abstract of estimated form. 4%of estimated Cost is allowed
for Petty Supervision, contingencies and Unforeseen items.
13
per IS 3861-1966, the following areas include while calculating the plinth area of
building.
Types of Estimates
a) Area of walls at floor level.
b)Internal shafts of sanitary installations not exceeding 2.0m2, lifts, air-conditioning
ducts etc.,
c)Area of barsati at terrace level: Barsati means any covered space open on one side
constructed on one side constructed on terraced roof which is used as shelter during rainy
Season.
d) Porches of non cantilever type.
Areas which are not to include
a) Area of lofts.
b) Unenclosed balconies.
c) Architectural bands, cornices etc.,
d) Domes, towers projecting above terrace level.
e) Box louvers and vertical sun breakers.
b)Cubical Contents Method: This method is generally used for multistoried buildings.
It is more accurate that the other two methods viz., plinth area method and unit base
method. The cost of a structure is calculated approximately as the total cubical contents
(Volume of buildings) multiplied by Local Cubic Rate. The volume of building is
obtained by Length x breadth x depth or height. The length and breadth are measured out
to out of walls excluding the plinth off set. The cost of string course, cornice, corbelling
etc., is neglected. The cost of building= volume of buildings x rate/ unit volume.
c)Unit Base Method: According to this method the cost of structure is determined by
multiplying the total number of units with unit rate of each item. In case schools and
colleges, the unit considered to be as 'one student' and in case of hospital, the unit is 'one
bed'. the unit rate is calculated by dividing the actual expenditure incurred or cost of
similar building in the nearby locality by the number of units.
14
DETAILED ESTIMATION
15
s.no Item Length Height/de EXPLANATOR
no breadth pth quantity
(L) YNOTES
(B) (H)
Earth work
1. excavation for 1 1089.74 0.5 544.87m3
total plinth area
Earth work
3 excavation For 19.34m3
compound walls 1x 1 128.89 0.3 0.5
Total earthwork
4 excavation
quantity 1217.68 m3
Earth work in
filling 437.5m3
5. Footings 1x 28 2.5 2.5 2.5
a). Earth work
filling For footings
size(2.5Mx2.5M)
216 m3
b). Earth work 1x 8 3 3 3
filling For footings 653.5 M3
size
(3Mx3M)
17.5 m3
6. P.C.C bed(1:3:6) 1x 28 2.5 2.5 0.1
For
(2.5mx.25m)
7.2 m3
P.C.C bed(1:3:6) 1x 8 3 3 0.1
For (3mx3m)
16
S.no Particulars of No Length Breadth Height/ Quantity EXPLANATO
items and details depth RYNOTES
of works m m m m3
7 R.C.C(1:2:4)
FOOTINGS
Footing
size
(2.5mx2.5m 1x 28 2.35 2.35 0.6 92.78m3
)
a) 1x 28 0.914 0.914 0.6 14.03m3
1STFooting
8.
c).3rd footing
c).3rdfooting
11 R.C.C Plinth
beam (1:2:4). for 1x35 0.3 0.3 2 6.3m3
Compound wall
R.C.C columns
(1:2:4). for
compound wall
17
Ground floor
Plinth beams(1:2:4) :
18
R.C.C COLUMNS (1:2:4)
COLUMNS SIZE
C1 , C 2 , C 3 , C 4 , C5 0.23 x 0.6 m
C 6 , C7, C 8 0.23 x 0.76 m
C9, C10, C11, C12, C13 , C14, C15 0.3 x 0.76 m
Ground Floor (Columns)
s.no item No. length breadth height quantity Total
quantity
1 C1 1x 7 0.6 0.23 3 2.89 m3
10 C10
1x 2 0.6 0.3 3 1.1 m3
11 C11
1x 2 0.6 0.3 3 1.1 m3
12 C12
1x 3 0.6 0.3 3 1.62 m3
13 C13
1x 3 0.6 0.3 3 1.62 m3
14 C14
1x 2 0.6 0.3 3 1.1 m3
15 C15
1x 1 0.6 0.3 3 0.54 m3
Total 16.88 m3
quantity
19
R.C.C Beams (1:2:4):
S.no item No. length breadth height quantity Total
2 B6a,b6c,b6e,
b7a,b7b,b7c, b7e,b7f 1x 2 26.92 0.23 0.6 7.43 m3
4
Beams at lift b4 1x 4 2 0.23 0.45 0.83 m3
Beam at entrance
5 Of lift 1x 2 2 0.23 0.6 0.55 m3
b5c,b5e,(9’’x23’’)
L=2m
20
8 Beam B3b 1x2 3.83 0.23 0.6 1.06 m3
9 Beam
B10a,B11a 1x2 9.75 0.23 0.45 2.1 m3
10 Beam
B11b,B11a 1x2 9.75 0.23 0.6 2.7 m3
Total R. c. c 43.76m3
beams(1:2:4) quantity
21
R. C. C Slab (1:2:4)
22
First floor block A
HEIGHT/ QUANTITY
LENGTH EXPLANATORY
S.N ITEM NO BREDTH DEPTH
m NOTES
O m m3
m
Brick masonry
Construction of
superstructure
with c:m 1:6 pro
all round the
1 block-A 1.00 40.62 0.23 2.70 25.23m3
C/W between
2 living & bed room-
1,2
Living& M.B.R,
kitchen 2.00 9.68 0.11 2.70 5.75 m3
C/W BETWEEN
KITCHEN
3. &BALCONY 1.00 3.55 0.11 2.70 1.05 m3
C/W between
toilet-2
4. &living/dining 1.00 3.00 0.11 2.70 0.89 m3
short walls of
5. toilet2(x-direction) 2.00 4.00 0.11 2.70 2.38 m3
C/W BETWEEN
6. TOILET-2 1.00 2.41 0.11 2.70 0.72 m3
C/W of WIDE
7.
BALCONY& 1.00 1.50 0.23 2.70 0.93 m3
Living room
both SIDE WALL
8.
BETWEEN 2.00 3.86 0.11 2.70 2.29 m3
TOILET-1(X-
DIRECTION)
23
Total B.M in
9 block A without
deductions 39.24 m3
EXPLANATORY
s.no item no length breadth depth quantity NOTES
10) DEDUCTIONS
M.D 1 1.1 0.30 2.00 0.66m3
a)
D 3 0.90 0.11 1.80 0.53 m3
b)
D1 5 0.75 0.11 1.80 0.74 m3
c)
W 3 1.20 0.23 1.20 0.99 m3
d)
W1
1 0.90 0.23 1.20 0.25 m3
e) W2
1 0.70 0.23 0.90 0.14 m3
f) W3
1 0.80 0.23 0.90 0.17 m3
g) V
2 0.90 0.23 0.50 0.21 m3
h) V1
i) 1 0.80 0.23 0.50 0.09 m3
B.M DEDUCTION
AT OPENINGS
11)
Deduct B.M at outer
side of balcony at
A kitchen 1 3.58 0.23 2.90 2.39 m3
24
s.no no length breadth depth quantity EXPLANATORY
item NOTES
25
R.C.C COLUMNS (1:2:4)
COLUMNS SIZE
C 1 , C5 0.23 x 0.6 m
C7 , C 8 0.23 x 0.76 m
C9, C10, C11, , C13 , 0.3 x 0.76 m
6 C10
1x 1 0.76 0.3 3 0.684m3
7 C11
1x 1 0.76 0.3 3 0.684m3
8 C13
2x 1 0.76 0.3 3 1.368 m3
Total 5.572m3
quantity
26
R.C.C Beams (1:2:4):
S.no item No. length breadth height quantity Total
1
All round the block-A 1x 1 41.84 0.23 0.6 5.774 m3
Beam B3b
3 1x1 3.83 0.23 0.6 0.53m3
Beam
4 B10a,B11a 1x1 9.75 0.23 0.45 1.01 m3
Beam
5 B11b,B11a 1x1 9.75 0.23 0.6 1.35 m3
Total R. c. c
6 beams(1:2:4) quantity 9.584 m3
27
R. C. C Slab (1:2:4)
28
S.no Item No. Length Breadth Height Quantity
m m m m2
Deductions
MD 1 1.1 - 2 2.2 m2
D 3 0.9 - 1.8 4.86 m2
D1 5 0.75 - 1.8 6.75 m2
W 3 1.2 - 1.2 4.32 m2
W1 1 0.9 - 1.2 1.08 m2
W2 1 0.7 - 0.9 0.63 m2
W3 1 0.8 - 0.9 0.72 m2
V1 2 0.9 - 0.5 0.9 m2
V2 1 0.8 - 0.5 0.4 m2
Total deductions 452.622-21.86=430.76 m2
Plastering with cement
mortar(1:6) net 430.76 m2
quantity
29
TWO COATS WITH ALL HYDRAULIC LIME WHITE WASHING
s.n Item no length breadth Depth/ quantity EXPLANATO
o height RY
NOTES
1.
All round the
1 41.83 - 3 125.5m2
block -A
short wall-1
M.D wall (inside) 1 3.353 - 3 10.06 m2
30
s.n Item no length Breadth Depth/ Quantity EXPLANATO
o (L) (B) Height (Q) RY
NOTES
(D)
Deductions 1 1.1 - 2 2.2 m2
MD
D 3 0.9 - 1.8 4.86 m2
D1 5 0.75 - 1.8 6.75 m2
W 3 1.2 - 1.2 4.32 m2
W1 1 0.9 - 1.2 1.08 m2
W2 1 0.7 - 0.9 0.63 m2
W3 1 0.8 - 0.9 0.72 m2
V1 2 0.9 - 0.5 0.9 m2
V2 1 0.8 - 0.5 0.4 m2
= Total white washing for walls without deductions- Total deduction quantity
31
White washing for ceiling
s.no Item no length Breadth Depth/ Quantity EXPLANATORY
(L) (B) Height (Q) NOTES
(D)
Net quantity of white washing for block A=white washing for walls +white washing for
ceiling
32
Net quantity of white washing for block A=327.51+223.447=550.96m2
Flooring in block A
Quantity of
floor area in 90.4 m2
block A
33
Doors , windows and ventilators
EXPLANATORY
no length breadth depth quantity NOTES
s.no item
10)
M.D 1 1.2 0.30 2.00 0.66m3
a)
D 3 0.90 0.11 1.80 0.53 m3
b)
D1 5 0.75 0.11 1.80 0.74 m3
c)
W 3 1.20 0.23 1.20 0.99 m3
d)
W1 1 0.90 0.23 1.20 0.25 m3
e)
W2 1 0.70 0.23 0.90 0.14 m3
f)
W3 1 0.80 0.23 0.90 0.17 m3
g)
V 2 0.90 0.23 0.50 0.21 m3
h)
i) V1 1 0.80 0.23 0.50 0.09 m3
34
First Floor Block B
Construction of
superstructure
with B.M in c:m
1:6 pro
5.
c/w between 1 3.4 0.11 2.7 1 m3
bedroom and
M bed room
35
Deductions
6. Brick work at
balcony 1 5.2 0.23 1.9 2.27m3
B.M b/w
7. drawing& 1 2.92 0.11 2.7 0.87m3
dining(openin
g)
8. 1 1.64 0.11 2.7 0.49m3
Opening
Between
dining
&wash room
Deduction of
doors&
windows 1 1.1 0.23 2 0.5 m3
36
R.C.C COLUMNS (1:2:4)
COLUMNS SIZE
C1, C2, C4 0.23 x 0.6 m
C9,C12,C15 0.3 x 0.76 m
C12
1x 1 0.76 0.3 3 0.684 m3
C15
1x 1 0.76 0.3 3 0.684m3
TOTAL
NET 3.3 m3
QUANTITY
OF R.C. .C
COLUMNS
37
R.C.C BEAMS (1:2:4)
TOTAL 7.0 m3
NET
3. QUANTITY
OF R.C.C
BEAMS
R. C. C Slab (1:2:4)
38
PLASTERING WITH CEMENT MORTAR 1:6 PRO FOR BOTH
INSIDE AND OUT SIDE FOR BLOCK B
2 Drawing
1 16.6 - 3 49m2
3
Kitchen 1 11.2 - 3 33.6m2
4
Dining 1 12.48 - 3 37.44m2
39
s.no item No. length Breadth height quality Explanatory
notes
Toilet in
8 M bedroom 1 7.4 3 22.2m2
-
10 c/w between
dining and 1 4.39 - 3 26.34m2
bedrooms
11. Total
quantity of 408.09m2
plastering
without
deduction
40
s.no item No. length Breadth height quality Explanatory
notes
Deductions
1 4.95 - 2.2 10.89m2
at balcony
4.95m
Deduction at
door,
1 window,
ventilator
2
Main door 1 1.1 - 2 2.2m2
3
Door 2 0.9 - 1.8 3.2m2
4
Door1 3 0.75 - 1.8 4.05m2
5
Window 1 1.5 - 1.2 1.8m2
6
Window1 3 1.2 - 1.2 4.32m2
7
Window2 1 0.9 - 1.2 1.08m2
8
Window3 1 0.9 - 0.6 0.54m2
Deduction 28.534m2
quantity
=379.56 m2
41
White washing 2coats inside and outside
1 Same as 379.56m3
plastering
Above
white washing
for ceiling
-
Kitchen 1 3.4 2.2 7.48m2
Dining
1 3.5 2.74 - 9.6m2
Wide
balcony 1 1.22 4.95 - 6.04m2
1 -
Bed room 3.62 3.2 11.59m2
-
m.bed room 1 4.34 3.2 13.89m2
-
toilet at m.bed
room 1 2.13 1.22 2.6m2
-
toilet ceiling
1 2.48 1.22 3.03m2
above b/w -
dining
&bedroom 1 3.27 1.22 3.87m2
White washing
Above ceiling 74.4 m2
42
PAINTING FOR BLOCK B
Explanatory
notes
s.no item No. length Breadth height quality
All round
the block B 1 36.3 - 3 108.9m2
out side
Drawing
1 16.6 - 3 49m2
1 12.48 - 3 37.44m2
Dining
1 6.7 - 3 20.1m2
Toilet -1
7.4
Toilet in 1 - 3 22.2m2
M bedroom
1 7.85
Balcony - 3 23.55m2
Deductions
at balcony
4.95m 4.95 - 2.2 10.89m2
43
Deduction at
door,
window,
ventilator
M.D
1 1.1 - 2 2.2m2
D 2 0.9 - 1.8 3.2m2
D1 3 0.75 - 1.8 4.05m2
W 1 1.5 - 1.2 1.8m2
W1 3 1.2 - 1.2 4.32m2
28.534m2
Deduction
quantity
44
painting for
ceiling
painting 74.4 m2
Above
ceiling
45
Flooring for block B
4 -
Bed room 3.62 3.2 - 11.6m2
-
5 M bed room 4.35 3.2 - 13.92m2
-
6 Wide balcony 1.11 4.84 - 5.4m2
-
7 Toilet-1 2.13 1.22 - 2.6m2
8 Toilet-2 -
[attached bath 4.34 3.2 - 13.99m2
room]
46
Detailed estimation of water over head tank
FOR SIDE
WALLS 4 5.4 0.15 2 6.48 M3
FOR
4. COVER(TOP)S 1 5.6 5.6 0.1 3.14 M3
LAB
Deduct for man 1 0.6 0.6 0.1 0.036 M3
hole
Net quantity of
R.C.C for over 3.104 M3
head tank
47
Detailed estimation of R.C.C STAIR CASE
Brick masonry in CM
2 (1:5)
thread and rises 2 x 10 1 1/2(0.25+0.1 4.0 m3
0.25 0.15 5)
Plastering with CM
3 (1:4) , 12 m thick
(a) Thread and Rise 2 x 10 1 (0.25+0.15) 8.00 m3 8.50 m3
48
ABSTACT ESTIMATION
49
AS PER S.S.R 2011-2012
LABOUR CHARGES
8 I CLASS MASSON HEAD/DAY 375
9 II CLASS MASSON HEAD/DAY 250
10 MAN MAZDOORS HEAD/DAY 200
11 WOMAN MAZDOORS HEAD/DAY 200
12 MIXING CHARGES 40
50
LEAD STATMENT
Tu COST
Laed Blast Signo Cees rn Rat FOR
INTIAL rate ing rage s Ov e
TYPE OF COST CONSU
S.NO MATERIAL per in Char chrge Char er At source
IN RS MER IN
Rs. ges s ges ta site (Rs)
x
51
CUM-UNIT RATES
RR masonry in CM (1:6) prop using with hard Granite stone for
foundation and basement.
1)
Cement masonry second sort in CM (1:6) prop using with hard Granite
2) stone for basement.
52
Brick masonry in CM (1:6) Proportion using second class bricks for super
3) structure
R.c.c work (1:2:4) mix using 20 mm guage Hg metal for columns ,beams, slabs,
footings
4) and sunshades. For C.C(1:2:4) we are preparing a supplementary data and
including cost and conveyance of all material and seignorage charges .Etc,
complete 1 cu.m
53
C.C 1:4:8 mix using 40 cm gauge. Hg metal , including cost and conveyance. All
5) materials and labour charges and seig : etc,. Complete per 1 cu.m.
54
Painting best synthetic enamil paint 3 coats over a primary
6) coat to new wood work including cost of all materials and
labour charges and seig. Charges etc. complete for 10 sq.m
55
Flooring with marbles stone slabs for 25 cu.m. thick over a bed of sand 3
7) inches. Thick and pointed with cm (1:3) including cost and conveyance
charges and seign charges etc.,
56
8)
Pointing with cm (1:3) to
shah bad stones slab
flooring including cost
and conveyance. All
material and labour
charges and segn
charges.
A 0.02 cu.m Cost of sand 603 / cu.m
B 0.02 cu.m Hand mixing charges 40 / cu.m 603 12.06
C 0.48 No.s Brick layer 1st class 300/ each 40 0.8
D 0.12 No.s Brick layer 2ndclass 250 / each 300 144
E 0.50 No.s Men mazdoors 200 / each 250 30
F 1.10 No.s Women mazdoors 200/ each 200 100
g 0.01 cum Cost of cement 8400 / each 200 220
8400 84
590.86
Plastering
9) with C.M
(1:6)
proportio
n
0.92 cu.m Cost of sand 603 / cu.m 603 554.76
0.17 cu.m Cement 8400 / cu.m 8400 1428
0.50 No.s Masons 1st class 375 / each 375 187.5
0.40 No.s Masons 2ndclass 250 / each 250 100
0.35 cu.m Mixing mazdoors 40/ each 40 14
2.10 No.s Men mazdoors 200 / each 200 420
3.00 No.s Women mazdoors 200 / each 200 600
3304.26
57
PERCENTAGE OF STEEL IN R.C.C WORK
Ground
floor
Ground floor
FORMULA
58
ABSTACT ESTIMATION
TOTAL
QUAN UI PE AMOUN
S.NO ITEMS RATE AMOUNT
TITY NT R T
IN Rs
GROUND FLOOR
1217.6 340950.
1 EARTH WORK EXCAVATION m3 280 m3
8 4
2 earth work filling 653.5 m3 150 m3 98025
2861 70668.6
3 C.C. BED (1:4:8) 24.7 m3 m3
.08 76
FOUNDATION WITH R.C.C 5140 848008.
4 164.97 m3 m3
(1:2:4) .38 4886
BASEMENT WITH C.R.S
5 11.6 m3 150 m3 1740
MASNORY (1:6)
STEEL REQUIRED IN R.C.C
3910
6 WORK (HYSD)(A) ground 21.18 T T 828138
0
floor
FLOORING WITH ANDOOR 101.67
7 m3 100 m3 10167.2
STONES 2
21,97,697.76
FIRST FLOOR-BLOCK-A
59
6,94,600.42
FIRST FLOOR-BLOCK-B
60
SERVICE CHARGES
61
ABSTACT (TOTAL)
SERVICE CHARGES
TOTAL 18884350.77
62
DRAWINGS
63
PLAN
64
BEAM FRAMING AND BEAM NUMBERS DETAILS
65
COLUMNS DETAILS
66
67
BIBLIOGRAPHY
STANDARD CODES
1. I.S 456-2000
2. NATIONAL BUILDING CODES(NBE)
ESTIMATING
COSTING
68