RACI Chart - Communication Pack
RACI Chart - Communication Pack
Communication Pack
WHAT is RACI?
Definitions
Responsible
• Those who do the work to achieve the task. There is at least one role with a participation type of responsible, although others can be
delegated to assist in the work required
Accountable
• The one ultimately answerable for the correct and thorough completion of the deliverable or task, and the one who delegates the work
to those responsible. In other words, an accountable must sign off (approve) work that responsible provides. There must be only
one accountable specified for each task or deliverable
Consulted
• Those whose opinions are sought, typically subject matter experts; and with whom there is two-way communication
Informed
• Those who are kept up-to-date on progress, often only on completion of the task or deliverable; and with whom there is just one-way
communication.
WHY develop RACI?
Key Objectives
1 Activity # 1 C C R I
2 Activity # 2 C A R R
3 Activity # 3 I A I R
4 Activity # 4 I A R R
5 Activity # 5 C A R R
6 Activity # 6 C A R I
7 Activity # 7 I A I R
8 Activity # 8 A A - R
9 Activity # 9 A R I -
HOW we’ll develop RACI?
List down all Activities • Inputs shall be gathered from all layers in Operations
1 currently performed
Hierarchy above Operators & Technicians
MM MTL
8%
R
12% R A 34% A
C
56% C I I
24% 66%
ME MS
2% 2%
6%
R
R A
A
C
C
I I
92% 98%
Post Aspired RACI Implementation
CURRENT RACI : 41 hrs Working Hours in day
16 14
14
12 11
10 8
7
8
6
4
2
0
MM MTL ME MS
15
10 8 7 8 7
6
5
0
MM MTL ME MS Planner
15 12
10 9 9
10 7
5
0
MM MTL ME MS Planner
TIME SPENT ON FIELD
CURRENT RACI : Average 26 % time spent on field
100%
90% 1.70 2.48 3.68
2.48
80%
70%
60%
50% Field Hours
40% Office Hours
5.73 8.45 10.79
5.24
30%
20%
10%
0%
MM MTL ME MS