0% found this document useful (0 votes)
49 views14 pages

Avantika RB

This document provides an overview and summary of the author's one month internship experience observing the construction of an 8-story residential building. It describes the company and construction project, materials and equipment used, construction processes for columns, beams, slabs and stairs. It also discusses problems encountered like leakage in formwork and honeycombing in columns, and recommendations to address safety and quality testing. The author concludes they gained valuable practical experience in construction management and applying their engineering knowledge.

Uploaded by

Mansi Rathi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
49 views14 pages

Avantika RB

This document provides an overview and summary of the author's one month internship experience observing the construction of an 8-story residential building. It describes the company and construction project, materials and equipment used, construction processes for columns, beams, slabs and stairs. It also discusses problems encountered like leakage in formwork and honeycombing in columns, and recommendations to address safety and quality testing. The author concludes they gained valuable practical experience in construction management and applying their engineering knowledge.

Uploaded by

Mansi Rathi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 14

INTERNSHIP

By : Avantika Rajendra Bodhare


CONTENTS
• Introduction
• Objectives
• Company overview
• Construction materials and equipments
• Construction process
• Problems and solution
• Recommendation
• Conclusion
INTRODUCTION
• In this presentation I will try to present my one month practical experience
of the construction work of a 8 storied residential building .
• I observed the construction of building.
• Here I have focused on mainly footing, column, stair, beam and slab
construction
OBJECTIVES
To orient us with the practical Civil Engineering works.
To allow me to apply my theoretical knowledge into practical fields.
To let us gaining practical experience.
To let us understand the planning, design, drawing of construction.
 
COMPANY OVERVIEW
• COMPANY NAME : - RAKESH BACHHAV ASSOCIATION

• COMPANY ADDRESS :- Shantamadhav sankul 4th floor , microcircle,


tidke colony, Nashik 422002
• SITE ADDRESS :- Digha talav ,Navi Mumbai
Airoli 400708
ABOUT OUR PROJECT
• Our project name :-Genetic mayabee
• Property details :-8 storied residential, 2400sq ft
• Building facing :-North
• Building storied :-8 storied
• Structural designer :- Mr. Darshan Shetty Sir
CONSTRUCTION MATERIAL
MATERIAL
 Cement
 Fine aggregate

Local sand
Local sand
CONSTRUCTION MATERIAL (CONT.)
Materials
 HYSD Bars
 20mm down brick chips –slab stair
 20mm down graded stone-column

Fig : Reinforcement
bar

Fig : Stone chips Fig : Brick chips


Construction of column

 Column casting :
• Mixing by Mixer Machine
• Mixing Ration 1:1.5:3
• Using Vibrator
• Cement grout spread
• Cement ,Sylhet sand and stone
• Water- cement ratio :0.40
• 4’-4” column casted
Fig : column casting
CONSTRUCTION OF STAIR

• First timber planks fixed


• Runner attached with timber
• Bamboo props support the Runner .

Fig : stair shuttering and using jute fabric


PROBLEM AND SOLUTION
• Problem -1 : During the column casting , liquid of concrete mix came out from the
form of column due to leakage in formwork or improper shuttering of column.
• Solution : We alert the labour about the leakage on the column shutter and said to
used just tap properly which can protect on shutter.
• Problem 2 : Safety should be the first condition in a construction work wearing
helmet and pant is not safer .
• Solution : We talk with them and make aware about the safety at construction site .
PROBLEM AND SOLUTION
• Problem 2 : Column C-3, after removing the shuttering there are honeycomb
on the column which can occur due to improper vibration.
• Solution : We suggest the labor to fill the honeycomb by cement paste.Then
they filled the place by cement paste and make plain by rubbing the jute tap.
• Problem 3 : In a beam FB-2 , stirrups spacing is changed and being some
transverse during the placement of beam
• Solution : We inform the labour about it and then they rebind the ties
maintaining the correct spacing.
RECOMMENDATION
• During our practicum period we are face some problems are our
recommendations are :
• The management should aware of safety. A little training and care can
prevent accident in the project.
• Company should need to do some test like slump test, cylinder test etc.
Some test like this can ensure the strength able construction.
CONCLUSION
• I have supervised beam , slab, stair and column construction work. After
supervising I had learned about beam, slab, stairs and column construction
and achieved practical experience. We have also learned construction
management. It was an awesome experience dealing with different type of
people at construction site . It seems to me that the practical knowledge is
the most essential to be efficient engineer.
• I tried to give my full efforts as train engineer overall the internship
program laid sound foundation for me to start my career.

You might also like