Radial, Loop Double and Grid Form Systems
Radial, Loop Double and Grid Form Systems
In this system all the sections/branches of a feeder are fed from a single source in a fixed direction
Load Load Load
Generator
In this it is shown that there are two primary feeders from which further subfeeders supply to there respective loads. If any one of the feeder becomes faulty then supply through that feeder has to cut so no reliability
4
Reasons Suitable size of conductor. Very simple protection schemes. Maintenance easy. Easy fault current calculations. No extra length of line and switching arrangements required. Less capital cost as different sizes of conductors can be used. As no alternative arrangements are necessary so shortest route can be adopted hence cost saving As used in rural areas so large spans can be used which further reduces cost
cheapest system
Reasons In case of fault on a feeder the supply to consumers from those feeders is cutoff and restored on fault removal. Due to passage of total current through the common main section of the feeder, voltage drop(IR) and line losses will be more as compared to the system which facilitates distribution of load currents into two or more paths
It is considered more suitable for the areas with low density of load involving long distances and requiring low degree of availability.
3 2 Distribution Transformer
1 0.4KV
8
If a HT line emanating from a Grid station and covering the load area in shape of a loop, finishes at the same Grid station returning to same breaker or another independent breaker it is called closed loop and the system is called closed loop system. In this system each transformer has two sectinalizers, one on either side of the transformers tap-off point.
Load
In case of fault, breaker at grid station opens. After tracing the fault the faulty section is isolated, and supply to remaining section is restored. The consumers dont have to wait very long till the rectification of the fault as in the case of Radial system. In case of two simultaneously faults, the consumers have to wait much till the rectification of the fault of at least one section. But possibility of two simultaneously faults is less. It is usually preferred that there must be two breakers instead of one.
As compared to radial system the voltage drop and line losses is less.
2.
It requires extra length of loop to complete the loop back to substation. Each transformer has to be provided with two sectionalizers , in absence of which the loop does not serve any purpose. In emergency total load of loop may have to be served from one side of loop, so higher size conductors are required to carry twice the current. Cost increases. Similarly in low load section the load during emergency must be more than 50%. They are used for small loops, If loop size is so large then the fault location time may exceed up to 5 to 6 hours. and if consumers are without electricity for this time then there is no justification to install such a system
Application
It is usually recommended for HIGH density areas where distances are small. preferably for urban areas. This system can be equally useful for rural areas where economy so permits. But to ensure effectiveness, the loop should be of small size.
If fault occurs, the supply of the The effect of fault is limited to whole loop goes off. faulty part, as one circuit breaker operates.
Total loop has to be patrolledThe faulty part of the loop is for fault location. clearly known.
ADVANTAGES
Additional radial feeder is provided side by side to feed the same consumer. Using automatic change over switches. Duplicate feeders. supply system or parallel
Substation Bus
FUSE
TRANSFORMER S LOAD
C.B C.B
C.B
C.B C.B
C.B
C.B C.B
C.B
Merits
Most reliable because normally no possibility of failure of supply and availability is almost 100%. In case of two simultaneous faults, service to the consumers will not be affected at all, or effect will be limited.
Demerits
Applications
The system being the most reliable, and at the same time the most costly, is recommended for the areas of highest priority of supply with very high load density. If the economy for a county is not a problem, this system is considered the most suitable one for urban areas, specially the big cities