Eltek Rectifier Commissioning Guide
General Objectives
To be familiarize into Eltek Commissioning
Set properly the standard parameters Activate some features incorporated into Eltek rectifier system Tools Needed
Laptop PowerSuite software Printer cable LAN cable Accessing Eltek Rectifier System Access via LAN cable Set Laptop IP Address into 192.168.10.21/24
Open PowerSuite software
Accessing Eltek Rectifier System Click Connect Button Accessing Eltek Rectifier System Choose Network Set the needed parameters Accessing Eltek Rectifier System Select Log In Type 3 as password Accessing Eltek Rectifier System Successfully Connected Commissioning Proper: System Voltage Levels Click System Voltage Levels Commissioning Proper: System Voltage Levels Set the following Reference: 2.25*+ Boost: 2.35*+ Rectifier Standby: 1.85 Battery Disconnect: 1.8 Battery Reconnect: 1.9666 Rectifier OSV limit: 2.4583 *-depends on the battery specs + specs for Sacred Sun and Narada Commissioning Proper: Alarms Overview Click Alarms Overview Commissioning Proper: Alarms Overview Defined the Alarms that need to be monitor Commissioning Proper: Alarms Overview Set the Alarms into their specific Alarm output number Battery High Voltage: Alarm Output 1 Rectifier Failure: Alarm Output 2 Mains Fail: Alarm Output 3 Battery Low Voltage: Alarm Output 4 Load MCB Fail: Alarm Output 5 Battery MCB Fail: Alarm Output 5 High Temperature: Alarm Output 6 Symmetry Fault: Alarm Output 6 Commissioning Proper: Mains Click Mains Number of Phases: 2 Commissioning Proper: Mains Click MainsPhase 1 Click MainsVolt 1 Commissioning Proper: Mains Set the following Check Enable Major High: 270 Minor High: 270 Minor High: 185 Major High: 185 Alarm Group: Mains Fail Apply then Ok Commissioning Proper: Mains Click MainsPhase 2 Click MainsVolt 2 Commissioning Proper: Mains Set the following Check Enable Major High: 270 Minor High: 270 Minor High: 185 Major High: 185 Alarm Group: Mains Fail Apply then Ok Commissioning Proper: Rectifier Click Rectifier Click Rectifier Error Commissioning Proper: Rectifier Set the following Check Enable Major alarm: 1 Minor alarm: 1 Alarm Group: Rectifier Alarm Apply then Ok
Repeat process for RectComm
Error Commissioning Proper: Rectifier Click the Configuration Tab Number of rectifiers: X Check the Suppress.. Walk in time: Long time OSV limit: 2.4583 Apply then Ok
X- actual rectifier module
installed Commissioning Proper: Rectifier Click the Efficiency Tab Enable efficiency manager Rectifier-off delay: 10 Shuffle time: 2 Apply then Ok Commissioning Proper: Load Click LoadBank 1 Click LoadFuse 1 Commissioning Proper: Load Set the following: Click Enable Alarm Group: Load MCB Fail Apply then Ok Commissioning Proper: Battery Click Battery Click Status Tab Click Battery Voltage Commissioning Proper: Battery Set the following Click Enable Major High: 57 Minor High: 57 Alarm Group: High Voltage Minor Low: 48 Major Low: 48 Alarm Group: Low Voltage Apply then Ok Commissioning Proper: Battery Click Battery Click Status Tab Click Battery Temp Commissioning Proper: Battery Set the following Click Enable Major High: 35 (40*) Minor High: 30 (35*) Alarm Group: High Temp Apply then Ok
*-for outdoor type
Commissioning Proper: Battery Click Battery Click Status Tab Click LVBD Commissioning Proper: Battery Set the following Click Enable Disconnect Voltage: 43.2 Reconnect Voltage: 47.2 Apply then Ok Commissioning Proper: Battery Click Battery Click Configuration Tab Number of banks: 1 Number of Strings: 4 Description: Battery installed date: today Capacity AH: 180 Commissioning Proper: Battery Click Battery Enable Temp comp Reference voltage: 2.25 Reference temp: 25 Temp slope: 3 (Eltek std) Min comp voltage: 2.1* Max comp voltage: 2.35*
*-depends on battery specs
Commissioning Proper: Battery Click Battery Click Current Limitation Enable Current Limitation Enable string current limit Set Current Limit: 72(Indoor) , 60(Outdoor) Apply then Ok *-current limit always 10% of total battery capacity Commissioning Proper: Battery Click Currents Click BattCurrent1.1 Commissioning Proper: Battery Click General Tab Click Enable Apply then Ok Commissioning Proper: Battery Click Fuses Click BattFuse1.1 Commissioning Proper: Battery Click General Tab Click Enable Alarm group: Battery MCB Fail Apply then Ok Commissioning Proper: Battery Click Temperatures Click BatteryTemp1.1 (only BatteryTemp1.1 will be configure) Commissioning Proper: Battery Click General Tab Click Enable Major High: 35(Indoor),40(Outdoor) Minor High: 30(Indoor),35(Outdoor) Alarm group: High Temperature Apply then Ok Commissioning Proper: Battery Click Symmetries Configure all SymmVolt 1.1 to 1.4 Commissioning Proper: Battery Click General Tab Click Enable Major alarm: 1.5 Minor alarm: 1.5 Alarm group: Symmetry Fault Apply then Ok Repeat process for 1.2 to 1.4 Commissioning Proper: Battery Click BattMonStr.1 Configure all BattMonSym1.1 to 1.4 Commissioning Proper: Battery Click General Tab Click Enable Major alarm: 1.5 Minor alarm: 1.5 Alarm group: Symmetry Fault Apply then Ok Repeat process for 1.2 to 1.4 Commissioning Proper: Power System Click Power System Modify: Site Name: Responsible: name of personnel THANK YOU!!!