We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 55
Chapter 6
Allocating Resources to the
Project
MEM 612 Project Management
Introduction • Projects Compete With One Another for Resources – resources that are not consumed – resources that are consumed • Goal of Resource Allocation is to Optimize Use of Limited Supply • Requires making trade-offs – time constrained – resource constrained
MEM 612 Project Management
EXPEDITING A PROJECT
MEM 612 Project Management
The Critical Path Method • Normal Duration Estimates • Normal Costs • Crash Duration Estimates • Crash Costs • Crash Cost Per Day
Normal Duration - Crash Duration
Crash Cost - Normal Cost MEM 612 Project Management Figure 6-1(a) Gantt Chart Crash Problem -- 21-Day Project
MEM 612 Project Management
Figure 6-1(b) AON Network for Sample Crash Problem -- 21-Day Project
MEM 612 Project Management
Figure 6-2 Gantt Chart for 20- Day Solution to Crash Problem
MEM 612 Project Management
MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management MEM 612 Project Management Resource Allocation and the Project Life Cycle Figure 6-20 Project or task life cycles
MEM 612 Project Management
GOLDRATT’S CRITICAL CHAIN
MEM 612 Project Management
Introduction • Similar issues that trouble people about working on projects regardless of type of project – unrealistic due dates – too many changes – resources and data not available – unrealistic budget • These issues/problems related to need to make trade-offs • To what extent are these problems caused by human decisions and practices?
MEM 612 Project Management
Figure 6-21 Three Project Scenarios
MEM 612 Project Management
Table 6-6 Project Completion Time Statistics Based on Simulating Three Projects 200 Times
Scenario 1 Scenario 2 Scenario 3
Average 50.4 51.9 53.4 Std Dev 7.1 6.3 5.3 Max 69.4 72.7 69.3 Min 30.1 36.1 39.3 Median 50.0 51.8 53.1
MEM 612 Project Management
Observations • Average Completion Times • Implications of Assuming Known Activity Times • Shape of the Distribution • Worker Time Estimates • Impact of Inflated Time Estimates • Student Syndrome
MEM 612 Project Management
Multitasking Figure 6-24 Two Small Projects
MEM 612 Project Management
Figure 6-25 Alternative Gantt Charts for Projects A and B
MEM 612 Project Management
Common Chain of Events • Underestimate time needed to complete project – assumption of known activity times and independent paths • Project team members inflate time estimates • Work fills available time – student syndrome – early completions not reported
MEM 612 Project Management
Common Chain of Events continued • Safety time misused • Misused safety time results in missed deadlines • Hidden safety time complicates task of prioritizing project activities • Lack of clear priorities results in poor multitasking
MEM 612 Project Management
Common Chain of Events concluded • Poor multitasking increases task durations • Uneven demand on resources also results due to poor multitasking • More projects undertaken to ensure all resources fully utilized • More projects further increases poor multitasking
MEM 612 Project Management
Reversing the Cycle • Reduce number of projects assigned to each individual • Schedule start of new projects based on availability of bottleneck resources • Reduce amount of safety time added to individual tasks and then add some fraction back as project buffer – activity durations set so that there is a high probability the task will not be finished on time
MEM 612 Project Management
The Critical Chain • Longest chain of consecutively dependent events – considers both precedence relationships and resource dependencies • Project Buffer • Feeding Buffer
MEM 612 Project Management
Figure 6-26 Sample Network Diagram
MEM 612 Project Management
Figure 6-27 Project and Feeder Buffers
MEM 612 Project Management
Copyright Copyright John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in Section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permissions Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages, caused by the use of these programs or from the use of the information herein.