17 Fabuary 2023

The document provides a progress report for the construction of a new technical office and one-story storage building on part of Lot PT 771 in Rompin, Pahang, Malaysia. As of February 17, 2023: - The overall physical progress was 31%, slightly ahead of the planned 30% progress. - Structural works were on track at 77% completion while external infrastructure works were ahead of schedule at 27% complete. - Other trades such as architectural, landscape, electrical and mechanical works had not yet commenced. The report includes photos showing ongoing construction activities and lists submittals, requests for information, and temporary material approvals related to the project.

Uploaded by

siti nur fatihah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
100 views43 pages

17 Fabuary 2023

The document provides a progress report for the construction of a new technical office and one-story storage building on part of Lot PT 771 in Rompin, Pahang, Malaysia. As of February 17, 2023: - The overall physical progress was 31%, slightly ahead of the planned 30% progress. - Structural works were on track at 77% completion while external infrastructure works were ahead of schedule at 27% complete. - Other trades such as architectural, landscape, electrical and mechanical works had not yet commenced. The report includes photos showing ongoing construction activities and lists submittals, requests for information, and temporary material approvals related to the project.

Uploaded by

siti nur fatihah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 43

WORK PROGRESS

CADANGAN MEMBINA
BANGUNAN PEJABAT TEKNIKAL &
STOR 1 TINGKAT DI ATAS
SEBAHAGIAN LOT PT 771, MUKIM
ROMPIN, DAERAH ROMPIN,
PAHANG DARUL MAKMUR

17 FEBRUARY 2023
OVERALL PHYSICAL PROGRESS MITIGATION PLAN
STATUS DATE PLANNED ACTUAL [+] / [-] % DURATION
(DAY)

06 JANUARY 2023 25% 25% 0% 0 DAY

03 FEBUARI 2023 27% 27% 0% 0 DAY

17 FEBUARI 2023 30% 31% 1% 6 DAY

Slidesgo Urban Pl
TRADE BREAKDOWN PHYSICAL
PROGRESS AS OF 17 FEBUARI 2023
TASK PLANNED ACTUA [+] / [-]
L %

Preliminaries 100 % 100 % 0%

TNB Temporary Gang Store, Surau, Toilet & Guard Post 100 % 100 % 0%

Contractor & Consultant Cabin, Meeting Room, Toilet & Site Guard Security Post 100 % 100 % 0%

Construction Stage For New Technical Office & Gang Store 20 % 23 % 3%


TASK PLANNED ACTUAL [+] / [-] %
Structural Works 77% 77% 0%

Architectural Works 0% 0% 0%

External & Infra Works 0% 27% + 27%

Landscape Works 0% 0% 0%

Electrical Works 0% 0% 0%

Mechanical Works 0% 0% 0%

Finishes 0% 0% 0%
PROGRESS LAST 2 WEEK
● OVERALL SITE AT VIEW 1 & VIEW 2
● OVERALL SITE AT VIEW 3 & VIEW 4
● Rebar and formwork fabrication at toilet area
● Rebar and formwork fabrication at roof beam phase 1
● Rebar and formwork fabrication at roof beam guard house
● Rebar and formwork fabrication at roof beam refuse chamber
● Concrete toilet slab
● Concrete roof beam phase 1
● Concrete roof beam for guard house and refuse chamber
● Setting out and excavation foundation for covered parking
● Excavation and levelling for sewerage pipe
● Repair floor surau at temporary gangstore.
● Installation structure awning at temporary gangstore.
SUBMITTAL FORM

Trade Total Code A Code B Code C Pending


Submit Reply

Arch 9 5 4 - -

C&S 12 10 2 - =-

M&E 1 1 - - -

Total 22 16 6 - -
APPROVED

PENDING APPROVAL

REF SUBMITTAL FORM REJECTED

PENDING RESUBMISSION

SUBMITTAL CHECKLIST
Item Submittal Submission Status Approval Submission Date Consultant's Feedback Date

MATERIAL SUBMISSION
1. Temporary cabin A-Approved 22/3/2022 29/3/2022
2. B-Comment
Organization chart 7/4/2022 12/4/2022
3. Traffic management plan A-Approved 14/4/2022 25/4/2022
4. Hanson cube test report for 7 days A-Approved 7/4/2022 8/4/2022
5. Reinforcement Bars B-Comment 24/3/2022 4/4/2022
6. BRC A-Approved 24/3/2022 4/4/2022
7. Workprogram B-Comment 7/4/2022 new 21/5/22 12/4/2022 new 27/5/22
8. Hanson cube test report for 28 days A-Approved 26/4/2022 26/4/2022
9. Roof structure fabricator A-Approved 2/7/2022 5/8/2022
10. Geotechnical submission A-Approved 4/6/2022 13/7/2022
APPROVED
PENDING APPROVAL

REF SUBMITTAL FORM REJECTED

PENDING RESUBMISSION

11. Method statement concrete A-Approved 17/7/2022 21/7/2022


12. Sample rebar test B-Comment 20/7/2022 21/7/2022
13. M&E company profile A-Approved 11/8/2022 25/8/2022
14. Rebar test plan A-Approved 8/8/2022 12/8/2022
15. SHE Plan B-Approved 29/8/2022 2/9/2022
16. PQP plan A-Approved 29/8/2023 28/9/2022
17. Steel bar and Rebend A-Approved 29/9/2022 3/10/2022
18. PBT AND MT work B-Comment 29/9/2022 29/9/2022
19. Roof thrust A-Approved 20/7/2022 5/8/2022
20. Sub-contractor M&E A-Approved 11/8/2022 25/8/2022
21 Slab concrete 7days & 28 days A-Approved 31/10/2022 3/11/2022
22 Test report premix AC14 A-Approved 11/29/2022 16/12/2022
REQUEST FOR INFORMATION FORM

TRADE TOTAL SUBMISSION FEEDBACK

ARC

C&S 1 26/7/2022

M&E

GEO 1 12/8/2022

TOTAL 2 -
SUBMISSION REQUEST FOR INFORMATION

NO ITEM SUBMISSION DATE FEEDBACK DATE

1 Geotechnical Submission 25/7/2022 26/7/2022

2 Changing rebar T8 links to 11/8/2022 12/8/2022


R8
MATERIAL APPROVAL FORM
Trade Total Code A Code B Code C Pending
Submit Reply

Arch 30 30 - - -

C&S 13 12 - - 1

M&E 30 23 7 - -

MAF 10 10 - - -
(TEMPORARY)
ID 1 - - - 1

Total 84 75 7 - 2
TEMPORARY MATERIAL APPROVED
PENDING APPROVAL

(MAF) REJECTED
PENDING RESUBMISSION
TEMPORARY MATERIAL CHECKLIST
Item Material Submission Manufacturer/Brand Ref. Number Submission Consultant's Resubmissi Consultant's Remarks
Date Feedback Date on Date Feedback Date
MATERIAL SUBMISSION
1. Temporary cabin Ming yuan cabin LSE/KLG/009/2022 22/3/2022 29/3/2022
2. Roofing materials( Hoarding ,roof KHP Roofing (M) Sdn Bhd LSE/KLG/019/2022 24/3/2022 29/3/2022
temporary cabin and gangstore) Approved
(Approved -
thickness 0.35 TCT
Roof color- Garvity
Grey
Hoarding color-
Esther blue
3. Coldwater Upvc(- UPVC Class 7 Bina Plastic Industries LSE/KLG/ Approved product
20,25,32, 40 & 50 mm) Sdn Bhd 031/2022REV02 11/4/2022 13/4/2022 brand
4. Polyethene tank(RT 2.0CB) Weida marketing Sdn
Bhd
LSE/KLG/
032/2022REV01 11/5/2022 13/5/2022
5. Sewarage Pipe-upvc Bina Plastic Industries
Sdn Bhd 1. Please highlight
LSE/KLG/033/2022 12/4/2022 13/4/2022 pipe size that be
use for this
development.
2. Please
confirm this
material under
sewerage or
internal sanitary
services.
TEMPORARY MATERIAL (MAF) APPROVED
PENDING APPROVAL
REJECTED
PENDING RESUBMISSION

6. Waterproofing(sikatopseal Sika Kimia Sdn Bhd


109 MY ,Sikagrout 215,
Sikalastic 110)
LSE/KLG/
043/2022 23/4/2022 29/4/2022
7. Washing basin(TOILET) INNO Ceramitec
Sdn .Bhd LSE/KLG/
049/2022 29/4/2022 17/5/2022
8. Water closet(TOILET) INNO Ceramitec
Sdn .Bhd LSE/KLG/
050/2022 29/4/2023 17/5/2023
9. Homo floor tiles(TOILET) GUOCERA
Floor - Calais
LSE/KLG/ Grey / Wall -
055/2022 11/5/2022 11/5/2022 Calais Bone
10. Concrete paving main Sunway Paving
entrance Solutions LSE/KLG/
104/2022 4/8/2022
PERMANENT MATERIAL APPROVED
PENDING APPROVAL
(ARCHITECT ITEMS) REJECTED
PENDING RESUBMISSION
ARKITEK SUBMITTAL CHECKLIST

Item Material Submission Manufacturer/Brand Ref. Number Submission Date Consultant's Resubmission Consultant's Remarks
Feedback Date Date Feedback Date

MATERIAL SUBMISSION

1 Strip Ceilling DML LSE/KLG/072/2022 4/6/2022 14/6/2022

2 Primaflex ceiling MST Marketing Sdn Bhd LSE/KLG/071/2022 4/6/2022 14/6/2022

3 Fire door THI Hardware sdn Bhd LSE/KLG/041/2022 22/4/2022 22/4/2022

4 Door Window Frame THI Hardware sdn Bhd LSE/KLG/042/2022 22/4/2022 22/4/2022

5 Sanitary ware and fittings Johnson suisse LSE/KLG/066/2022 5/7/2022 18/7/2022

6 Roller shutter SKB Shutters Manufacturing LSE/KLG/ 2/7/2022 18/7/2022


082/2022(REV01)
7 Mineral fibre ceiling panel Knauf LSE/KLG/ 2/7/2022 7/7/2022
068/2022(REV01)
8 Paint material Interior Jotun LSE/KLG/070/2022 4/6/2022 5/7/2022

9 Paint material exterior Jotun LSE/KLG/069/2022 4/7/2022 5/8/2022

10 Operable wall details Great year wall Sdn Bhd LSE/KLG/064/2022 26/5/2022 1/6/2022
PERMANENT MATERIAL APPROVED
PENDING APPROVAL
(ARCHITECT ITEMS) REJECTED
PENDING RESUBMISSION

Floor harderner Sika kimia Sdn Bhd LSE/KLG/065/2022 30/5/2022 1/7/2022


11

Sand cement brick Enrich Multitrade Sdn Bhd LSE/KLG/040/2022 16/8/2022 2/7/2022
12

Chain link TET TAFA Fence and Mash LSE/KLG/091/2022 16/8/2022 17/8/2022
13

Security fence TET TAFA Fence and Mash LSE/KLG/107/2022 16/8/2022 17/8/2022
14

Rainwater downpipe Bina Plastic Industries Sdn Bhd LSE/KLG/063/2022 23/5/2022 2/7/2022
15

court paint Atles Industries Sdn. berhad LSE/KLG/125/2022 30/8/2022 9/2/2022


16

Aluminium folding door Aluminium & glass sdn bhd LSE/KLG/126/2022 2/9/2022 2/9/2022
17

18 Clay Bricks Ming Thai Brick Sdn Bhd LSE/KLG/040/2022 22/4/2022 17/5/2022

Homo Tiles Guocera LSE/KLG/056/2022 9/5/2022 11/5/2022


19
PERMANENT MATERIAL APPROVED
PENDING APPROVAL
(ARCHITECT ITEMS) REJECTED
PENDING RESUBMISSION

Raised floor panel eleva LSE/KLG/067/2022(REV01) 14/6/2022


20 11/15/2022

21 Casement window and Top Hung Reliance Home Sdn Bhd LSE/KLG/073/2022(REV01) 7/6/2022 14/6/2022 resubmit(20/12/2022)
window

22 Roof covering Ns bluescope malaysia sdn. LSE/KLG/122/2022 15/10/2022 25/10/2022


bhd

23 Waterproofing Sika Top Seal Sika Kimia Sdn Bhd LSE/KLG/043/2022(REV01) 23/4/2022 17/5/2022 Resubmit(19/10/2022)

24 Polythena damp proof Substantial Avenue resources LSE/KLG/121/2022(REV01) 17/9/2022 9/29/2022 Resubmit(26/9/2022)

25 Sanitary fitting permanent building Johnson Suisse LSE/KLG/066/2022 8/5/2022 8/17/2022

26 Fascia cladding KAWA LSE/KLG/150/2022 11/30/2022 16/12/2022


KIM NOE THYE INDUSTRIES
27 AAC BLOK SDN BHD LSE/KLG/135/2022 1/12/2022 16/12/2022

28 Roofing r700 KAWA LSE/KLG/163/2022 20/12/2022 21/12/2022

29 DYNASPEC SDN BHD PARSEC LSE/KLG/165/2022 21/12/2022 21/12/2022

30 PGF INSULATION SDN BHD ECOWOOL LSE/KLG/164/2022 21/12/2022 21/12/2022


APPROVED
PERMANENT MATERIAL PENDING APPROVAL

(C&S ITEMS)
REJECTED
PENDING RESUBMISSION

C&S SUBMITTAL CHECKLIST


Consultant's Resubmission Consultant's
Submission
Item Material Submission Manufacturer/Brand Ref. Number Date Feedback Date Feedback Date Remarks
Date

MATERIAL SUBMISSION
1. Salt glazed ware drain 230mm CnG United trading LSE/KLG/054/2022 15/4/2022 - -
11/5/2022
2. Precast concrete manhole G-Cast Concrete Sdn LSE/KLG/042/2022 20/5/2022 23/5/2022 Approved
Bhd product brand
3. Crusher run Kuari Endau Rompin LSE/KLG/045/2022 26/4/2022 27/4/2022 Approved
Sdn Bhd product brand
4. Premix Rompin Premix Sdn LSE/KLG/046/2022 26/4/2022 23/5/2022 Subject with
Bhd comments
5. VCP for manhole Sunway Vcp Sdn Bhd LSE/KLG/054/2022 20/5/2022 23/5/2022
6. Anti termitte Precintct sc LSE/KLG/120/2022 17/9/2022 22/9/2022
7. Roof temporary KHP Roofing (M) Sdn
LSE/KLG/019/2022 10/4/2022 13/5/2022
Bhd
8. Sika floor- Sika Kimia Sdn Bhd LSE/KLG/065/2022 30/5/2022 1/6/2022
APPROVED
PERMANENT MATERIAL PENDING APPROVAL

(C&S ITEMS)
REJECTED
PENDING RESUBMISSION

9. LSE/KLG/
Operable wall Great year Sdn Bhd 26/5/2022 1/6/2022
064/2022
10. LSE/KLG/
Concretepaving blocks SUNWAY 4/8/2022 5/8/2022
104/2022
11. HUME Concrete Sdn LSE/KLG/ 5/12/2022
RC U- drain Bhd 075/2022 6/9/2022

12 precast concrete box culvert OKA Concrete Sdn LSE/KLG/ 11/10/2022 5/12/2022
Bhd 145/2022

13 Septic tank 25PE ECOSEPT LSE/KLG/ 17/2/2023


178/2023
PERMANENT MATERIAL
APPROVED
PENDING APPROVAL

(M&E ITEMS) REJECTED


PENDING RESUBMISSION

M&E SUBMITTAL CHECKLIST

Submission Consultant's Resubmission Date Consultant's


Item Material Submission Manufacturer/Brand Ref. Number Remarks
Date Feedback Date Feedback Date

MATERIAL SUBMISSION
1. Cold Water supply Upvc BBB brand LSE/KLG/031/2022 11/4/2022 27/4/2022 Approved product
brand
2. Water tank storage Weida LSE/KLG/076/2022 7/6/2022 13/6/2022 Approved product
brand
3. Switch socket Schneider LSE/KLG/084/2022 14/6/2022 14/6/2022 resubmit
4. Emergency light PNE LSE/KLG/079/2022 14/6/2022 18/7/2022
5. Weatherproof fitting Schneider LSE/KLG/071/2022 18/7/2022 18/7/2022
6. LED flood lights Schneider LSE/KLG/072/2022 13/7/2022 18/7/2022
7. HDPE pipe PN 12.5 LSE/KLG/ resubmit(24/9/22)
Bina Plastic 053/2022(REV2) 20/8/2022 25/8/2022
8. Fire extinguisher Eversafe LSE/KLG/ 20/8/2022 25/8/2022 resubmit(24/9/22)
110/2022(REV1)
9. Booster pump EBARA LSE/KLG/102/2022 20/8/2022 25/8/2022
10. Sewarage Upvc brown and fittings Bina Plastic LSE/KLG/ 23/8/2022
031/2022(REV01) 25/8/2022
PERMANENT MATERIAL
APPROVED
PENDING APPROVAL

(M&E ITEMS) REJECTED


PENDING RESUBMISSION
11. 20 A DP Switch socket C/W Neon Schneider LSE/KLG/077/2022 21/7/2022 25/8/2022
Light
12. Schneider
30/9/2022
Gang switch LSE/KLG/080/2022 20/7/2022
13.
30/9/2023
PVC Electrical cable Universal LSE/KLG/079/2022 21/7/2022
14.
10A gang switch LSE/KLG/078/2022 20/7/2022 30/9/2024
Schneider
coment
15. 13A switch socket outlet LSE/KLG/075/2023 18/7/2022 30/9/2025
(METALCLAD TYPE) Schneider
16.
13A 250V switch socket LSE/KLG/076/2022 21/7/2022 30/9/2022
Schneider vivice
17.
VCP straight pipes Sunway VCP Sdn Bhd LSE/KLG/044/2022 25/4/2022 26/4/2022

18.
Polyethylene Tank for temporary Weida LSE/KLG/ 11/5/2022 13/5/2022
toilet. 032/2022(REV01)

19. Inno WC1012 Water Closet


INNO Ceramitec Sdn. Bhd LSE/KLG/050/2022 29/4/2022 17/5/2022

20.
Washing Basin WB2002 INNO Ceramitec Sdn. Bhd LSE/KLG/049/2022 29/4/2023 17/5/2023

21.
28 PE Septic Tank for Temporary Mui Fatt Marketing Sdn
Cabins Bhd LSE/KLG/034/2022 12/5/2022 17/5/2024
PERMANENT MATERIAL
APPROVED
PENDING APPROVAL

(M&E ITEMS) REJECTED


PENDING RESUBMISSION

22.
LSE/KLG/ 10/6/2022 resubmit(20/10/2022) coment
LED tubes T8 Phillips 072/2022(REV01) 7/6/2022
23.
LSE/KLG/ resubmit(18/10/2022)
AC wall mounted and ceilling Daikin 093/2022(REV02) 9/8/2022 28/10/8/2022
24. Submersible pump EBARA LSE/KLG/ 20/8/2022 28/10/2022
101/2022(REV01) resubmit(19/10/2022)

25. LSE/KLG/
Brass stop cock City 096/2023(REVO1) 2/8/2022 17/10/2022 resubmit(15/10/2022)

26. LSE/KLG/
Gate valve V&G 2/9/2022 17/10/2022 resubmit(15/10/2022)
097/2024(REV02)
27. 13A switch socket outlet (hand LSE/KLG/
drayer) Schneider 074/2022(REV01) 18/7/2022 30/9/2022 resubmit(18/10/2022) coment

28.
LSE/KLG/ 12/10/2022 resubmit(18/10/2022)
Wall fan KDK 080/2022(REV01) 14/6/2022
29.
LSE/KLG/ 12/10/2022 resubmit(19/10/2022)
Industrial wall fan 081/2022(REV01) 14/6/2022
30. LSE/KLG/129/2022
Grease interceptor 15/10/2022 28/10/2022 coment
Frosco
APPROVED
PERMANENT MATERIAL (ID PENDING APPROVAL

ITEMS)
REJECTED
PENDING RESUBMISSION

Submission Consultant's Resubmissio Consultant's


Item Material Submission Manufacturer/Brand Ref. Number Feedback Remarks
Date Date n Date Feedback Date

MATERIAL SUBMISSION

Zenpro furniture Zenith Project Sdn bhdLSE/KLG/127/2022 9/2/2022


1        
SHOP DRAWING FORM

Trade Total Submit Code A Code B Code C Pending Reply

Arch 2 2 - - -

C&S 3 1 1 - 1

M&E 1 - - - 1

MAF - - - - -

Total 6 3 1 - 2
APPROVED

REF SHOP DRAWING PENDING APPROVAL


REJECTED
PENDING RESUBMISSION

Consultant's
Item Drawing Submission Ref. Number Submission Consultant's Resubmission
Date Feedback Remarks
Date Feedback Date
Date

MATERIAL SUBMISSION

1 Temporary Cabin Shop


Drawing LSE/RP/SD01 23/4/2022 27/4/2022
2 Awning at septic tank and 5/9/2022
covered parking LSE/RP/SD02 30/8/2022
3
Wash through LSE/RP/SD03 30/8/2023 5/9/2022
-Pdf revice
4 M&E shop drawing 11/1/2023 drwg 5/1/23 -
Resubmit
LSE/RP/SD04 3/2/23
5 Awning and porch 11/10/2022 2/2/2023
LSE/RP/SD05
6 Main building and geng 11/10/2022 13/2/2023 2/2/2023
store LSE/RP/SD06
PROGRESS NEXT 2 WEEK
1. Concrete column phase 2 ( 17/2/23 – 23/2/23)

2. Concrete pad footing for covered parking ( 17/2/23 – 22/2/23)

3. Concrete slab for badminton court (24/2/23)

4. Installation formwork roof beam phase 2 (24/2/23 – 3/3/23)

5. Installation brickwork at refuse chamber and guard house (21/2/23 – 3/3/23)

6. Installation of sewarage pipe (VCP PIPE)


SAFETY

• PPE
• HOUSEKEEPING
• HYGIENE (toilet)
• SWP WORKING AT HEIGHT
• ACCIDENT PREVENTION (SLIPS, TRIPS & FALL)
SAFETY
WALKABOUT
FINDING
- BAD HOUSEKEEPING
SAFETY
• EXPOSE TO SHARP OBJECT ( SLIPS,TRIPS & FALLS )
SAFETY
THANK YOU