0% found this document useful (0 votes)
88 views

Chapter 7 - Monitoring and Controlling The Project

Monitoring and controlling the project involves collecting project data, comparing actual performance to the plan, and taking actions to align performance with the plan. This forms a closed-loop process that continues throughout the project. Key aspects of monitoring and controlling include identifying elements to monitor and control, designing the monitoring system, collecting and analyzing performance data, reporting performance, and taking control actions when needed to keep the project on track. Earned value management is a common technique used to quantitatively measure project performance and identify variances from the plan.

Uploaded by

Aung Khaing Min
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views

Chapter 7 - Monitoring and Controlling The Project

Monitoring and controlling the project involves collecting project data, comparing actual performance to the plan, and taking actions to align performance with the plan. This forms a closed-loop process that continues throughout the project. Key aspects of monitoring and controlling include identifying elements to monitor and control, designing the monitoring system, collecting and analyzing performance data, reporting performance, and taking control actions when needed to keep the project on track. Earned value management is a common technique used to quantitatively measure project performance and identify variances from the plan.

Uploaded by

Aung Khaing Min
Copyright
© © All Rights Reserved
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 41

CHAPTER (7)

MONITORING AND
CONTROLLING THE PROJECT

7-1
Monitoring and Control
• Monitoring is the collection, recording, and
reporting of project information
• Control uses the monitored data to bring actual
performance into agreement with the plan
• Monitoring and control are the opposite sides of
project selection and planning
– Project selection dictates what to monitor
– Project planning identifies the elements to be controlled

7-2
Plan-Monitor-Control Cycle
• The plan–monitor-control cycle constitutes a
“closed loop” process
– Continues until the project is completed
• With complex projects, there is a temptation to
minimize the planning–monitoring–controlling
effort so that “real work” can be done
– It is these projects that need the planning–monitoring–
controlling process the most

7-3
Project Authorization and Expenditure
Control System Information Flow

Figure 7-1
7-4
Designing the Monitoring
System
• Identify special characteristics of scope,
cost, and time that need to be controlled
– Specific performance characteristics should be
set for each level of detail in the project
• Real-time data must be identified to
measure achievement against the plan
• It is important to avoid the tendency to
focus on easily collected data

7-5
Data Collection and Reporting
• Once data to monitor has been decided,
mechanisms to collect this data must be designed
• Analysis is used to transform data into information
• A number of questions come up:
– Should we use special forms?
– Should data be collected before/after milestones?
– Should time and cost data be collected at the same
time?

7-6
Data Collecting
Data to be collected exist in one of following five formats:
1) Frequency counts: Talley of occurrence (eg., accident free days)
2) Raw numbers: Actual amounts are used, to compare with planned
amount (eg., dollars spent, hours required)
3) Subjective numeric ratings: subjective estimates of some quality
offered by specialists (eg, ranksings of performance)
4) Indicators and surrogates: Use when no direct measure (eg, to
measure customer service level, use no. of salesperson / years of
experience)
5) Verbal characterizations: Use when no other variables to measure
(eg., to measure team spirit, use verbal characterizations)

7-7
Data Analysis
• Data analysis techniques
– Simple aggregation
• Averaging, for example
– Fitting statistical distribution functions to the
data
– Curve fitting
• Significant differences from the plan should
be flagged
7-8
Data Analysis Examples

Figures 7-2, 7-3, 7-4


7-9
Reporting and Report Types
• Routine performance reports
– Project status reports
– Time/Cost reports
– Variance reports
• Avoid periodic or routine reports
• Not all stakeholders need to receive same information
• Electronic media makes it possible to customize
information for difference audiences
• Reports should be timed to allow control to be exercised
before completion of the task in question

7-10
Report Types
1. Routine
– Status, progress, and forecast reports
2. Exception
– A report used for special decisions or unexpected
situations where affected team members need to be
made aware, and the change itself documented
3. Special analysis
– The results of a special study which documents a
particular opportunity or problem within the project
itself

7-11
Additional Report Benefits
• They provide the mutual understanding between
stakeholders in a project
• They help communicate the need for coordination
among those working on project
• They establish and maintain a communication
network for global projects
• Reports can communicate information about
changes to a project
• They help maintain the visibility of the project
• They improve motivation

7-12
Meetings
• Many reports are delivered at meetings
• Meetings range from regular, highly
formalized and structured sessions to
informal, off-the-cuff get-togethers
– Presentations
– Question and answer sessions
• Meetings must be well run to be effective

7-13
Meeting Guidelines
• Meetings should be used primarily for group decision
making, not for mere progress reports
• Distribute written agenda in advance of meeting to ensure
that all attendees are properly prepared for the meeting
• For a crisis meeting, restrict discussion to that issue
• Meeting should take minutes
– Avoid attributing remarks to individuals in the minutes
• Avoid excessive formality
• If meeting is held to address specific crisis, restrict
meeting to this issue alone

7-14
Virtual Reports, Meetings, and
Project Management
• The Internet can be used to communicate and
report about the project’s status
– Irrespective of the location of the project team
members
• Software programs allow the project manager to
utilize the organization’ local area network or
intranet
• Virtual project teams have members spread
worldwide
7-15
Earned Value
• The earned value (EV) of a task or project is the
budgeted cost of the work actually done
– It is calculated by multiplying the budgeted cost of the
task by the percentage completion of the task
– Process is more difficult than it sounds
• Budgeted cost of a task is clear
• Percentage of completion is not
• The percent of a task’s budget actually spent is not
good indicator of percent completion

7-16
Conventions Used to Estimate
Progress on Tasks
• 50-50
– Task is listed as 50% complete when initiated and the remaining
50% added when task is completed
• 100%
– The task is 100% complete when finished … and zero percent
before that
– projects will always appear to be “behind schedule”
• Ratio of cost (or time) expended to cost (or time) budgeted
– Neither is an accurate estimator of percentage completion
• These conventions are meant for application only to
individual tasks on a project, not to the project as a whole

7-17
Earned Value Chart

Figure 7-5
7-18
Two Simple Rules for Variances
1. A negative variance is bad and a positive
variance is good
2. The spending and schedule variances are
calculated as the earned value minus some
other measure

7-19
Variances
• Cost/Spending variance
– Earned value (EV) – actual cost (AC)
• Schedule variance
– Earned value (EV) – planned cost (PV)
• CPI (cost performance index)
– Earned value (EV)/actual cost (AC)
• SPI (schedule performance index)
– Earned value (EV)/planned cost (PV)

7-20
Example
• Work on a project was expected to cost
$1,500
• Workers were originally scheduled to finish
today
• However, as of today…
– Actually spent $1,350
– About 2/3 finsished

7-21
Various Variances Visually

a: Positive schedule variance, negative spending variance


b: Negative schedule variance, negative spending variance

Figure 7-6 c: Negative schedule variance, positive spending variance

7-22
Calculations for Example

7-23
Additional Items of Interest
• Estimated remaining cost to completion
– ETC = (BAC – EV) / CPI
• ETC: estimated cost to completion
• BAC: budget at completion
• EV: earned value
• CPI: cost performance index
• Estimated total cost at completion
– EAC = ETC + AC
• EAC: estimated at completion
• ETC: estimated cost to completion
• AC: actual cost

7-24
Additional Calculations for Example
• BAC = 1500
• EV = 1500 (2/3) = 1000
• CPI = .74 (calculated earlier)
• AC = 1350
• ETC = (BAC – EV) / CPI
= (1500 – 1000) / .74
= 676
• EAC = ETC + AC
= 676 + 1350 = 2026

7-25
Microsoft Project Status Report for
DVD Project

Table 7-1
7-26
Project Control
• Control, the act of reducing differences between
the plan and actuality
• It is the final element in the planning-monitoring-
controlling cycle
• It is to no avail if actions are not taken when
reality deviates significantly from what was
planned
• Control is a difficult task
– It involves human behavior
– Problems are rarely clear cut so the need for change
and redirection is also fuzzy

7-27
Purposes of Control
1. Stewardship of organizational assets
– Physical asset control
– Human resources management
– Financial control through the use of accounting tools
2. Regulation of results through the alteration of
activities
– This step involves taking action when reality deviates
from plan
– It includes both mechanistic and human elements

7-28
Purposes of a Control System
• Primary purpose is to correct errors
– Not to identify and punish the guilty
– Managers must realize that the past cannot be changed
• Control the investment, subject to diminishing
returns
• Consider impact on creativity and innovation
• The control system should employ the lowest
degree of hassle consistent with accomplishing its
goals

7-29
Primary Mechanisms by which
Project Manager Exerts Control
1. Process reviews
• An analysis of the process of reaching the project
objectives
2. Personnel assignment
• Control can also be exercised through personnel
assignments based on past productivity
3. Resource allocation
• Resources are usually allocated to the more
productive or important tasks and this can
significantly influence the attainment of project
results

7-30
Common Mistakes
• Emphasizing short-run results at the expense of
long-run objectives
• Excessive control directed to specific objectives
can result in sacrificing other project objectives
• Across-the-board cuts in resource allocations tend
to reward those who have already overspent or
over hired while penalizing the frugal and efficient
• Focusing on certain items for control can distract
the attention of team members from other, equally
important items

7-31
Control System Components
• Sensor
– Its purpose is to measure any aspect that one wishes to control
• Standard
– The control system must have a standard of items to measure
against
• Comparator
– Compares the output of the sensor with the standard
• Decision maker
– To decide if the difference between what is measured and the
standard is large enough to warrant attention.
• Effector
– If some action is required to reduced the difference, the effector
must then take action

7-32
Types of Control Systems
• Cybernetic control systems
– A control system that uses all five components of a
control system
– Also known as steering controls
• Go/no-go controls
– A predetermined standard must be met for permission
to be granted to continue
• Post-control (post-performance reviews)
– Applied after the project has been completed
– Purpose is to allow future projects to learn from past
project experience

7-33
Tools for Control
• Some already covered
– Variance analysis
– Trend projections
– Earned value
• Critical ratio
– Indicates when a task is becoming unacceptable
• When the ratio drops below one
– CR = (actual progress/scheduled progress)  (budgeted cost/actual cost)

7-34
Critical Ratio Calculations

Table 7-3
7-35
More Tools for Control
• Control chart
– Any measure can be plotted and tracked on a
control chart
– Control limits set by project manager
• Benchmarking
– Make comparisons to “best in class” practices
across organizations, or divisions, or even
departments within an organization

7-36
Two Sample Control Charts

Figures 7-9 and 7-10


7-37
Scope Creep and Change Control
• Midcourse changes to a project must be
controlled
– Called scope creep
• The later changes are made to a project, the
more difficult and costly they become
• All projects face change
• The best approach is a well-controlled,
formal process for change

7-38
Purpose of Change Control System
• Review all requested changes
• Identify all impacts
• Translate impacts into performance, schedule, and
cost
• Evaluate the benefits and disadvantages
• Have appropriate person accept or reject
• Communicate accepted changes
• Ensure changes are implemented properly
• Prepare report

7-39
Rules for Controlling
Scope Creep
• Include a change control system in every project
contract
• Require all changes be introduced by a change
order
• Require approval in writing by the client’s agent
and senior management
• Consult with project manager prior to preparation
of change order
• Amend master plan to reflect changes

7-40
THANK YOU

7-41

You might also like