Chapter III
Chapter III
Financial Analysis
Contents
1. Objectives of Financial Analysis
2. Pricing Project Costs and Benefits
3. Change in prices
4. Financial ratios
a) Efficiency Ratios
b) Income ratios
c) Creditworthiness ratios
5. Discounted project worth measures
• NPV, IRR, BCR, discounted payback
Financial Analysis
Financial analysis answers the question :
“is the project financially profitable to a given
individual, group or business?
Sources of financing
Financial viability
The Investment Costs of a Project
Initial investment Costs of a project
Land and site Development
Buildings and Civil Works
Plant and Machinery
Technical know-how and engineering fees
Miscellaneous Fixed Assets
Capital issue expenses
Pre-operative Expenses
Provision for contingencies, etc.
Other costs
Sunk costs
Depreciation
Operation Costs of a Project
Direct and indirect costs:
Direct costs are directly attributable to the
production
Indirect costs are incurred to facilitate the
production process but are not the direct inputs of
production.
Variable costs and fixed costs:
Variable costs are costs that vary with the volume
of the product
Fixed costs are costs that do not vary with the
volume of the product.
Cost of production comprises of three main
factors:
Cost of materials,
Labor cost and
Factory overhead
Cost of production = Material cost + labor
cost + factory overhead Total COP
cost.
CoPperUnit
Total Noof Units
Working Capital Estimates
Working capital is the financial requirement needed
to finance the current asset of the balance sheet.
raw materials, supplies and components
temporarily held in stock until usage,
Work-in-process,
finished goods until the time of selling,
accounts receivable until payment made by
the customer, etc.
Net Working Capital = Current Assets –Current
Liabilities
Means of Finance
Government
International organizations
Partially international organizations and
partially government
• Appraise the project from the • Appraise the project from the
view point of an entrepreneurs, view of macro or national
investor or financier. economy or its contribution to
the society.
• Covers only private costs and • It takes into account social costs
benefits and benefits.
• Taxes are treated as costs and • Taxes and subsidies are treated
subsidies as a return. as transfer payments.
Where:
Bt stands for the project benefits in period t
Ct stands for the project costs in period t
r, stands for the appropriate financial or economic
discount rate
n, stands for the number of years for which the
project will operate, i.e. the economic life of the
project
Decision Rule:
• If the NPV is positive, accept the project.
• If the NPV is zero, be indifferent
• If the NPV is negative, reject the project.
• If we compare two or more projects, the
higher the NPV, the better the project is.
Undiscounted Discounted
1 2 3 4 5
Year(t) Costs Benefit Net benefits Discount factors (10%)= Discounted Net Benefits (Net
(Cash flow) 1/(1+0.10)-t Cash Flow) (3)*(4)
(2) – (1)
Disadvantages of NPV
•The NPV method can be employed in selecting from mutually
exclusive projects only when the projects are of the same size.
•The NPV method assumes that funds are reinvested at the cost of
capital
•The cost of capital is assumed to remain constant throughout the
life of the project.
Internal Rate of Return
• The IRR is the rate of discount, which makes
the present value of the benefits exactly equal
to the present value of the costs.
t
Pt t
( Bt C t )
NPV P0 0
t 0 1 R t
t 0 1 R t
Calculation of IRR
If the positive and negative NPVs are close to zero,
a precise and less time consuming way to arrive at
the IRR is using the following interpolation
formula.
PV ( I 2 I1 )
IRR I1
PV NV
Year 1 2 3 4
Cash flow 6000 6000 8000 9000
Try to compute the NPV with 12% discount rate.
= 167
Still the NPV is positive. Try again
with a higher discount rate i.e.
16%.
6000 6000 8000 9000
1.16 20000
(1.16) 2 (1.16) 3 (1.16) 4
= -344
• Thus, it can be concluded that the
IRR is between 15% and 16%
Advantages of IRR
• It gives due consideration for the time value of
money
• It recognizes the total cash flows during the
project life
• It conveys the direct message about the yield on
the project.
Disadvantages of IRR
• It involves tedious work through trial and error
• It assumes that all proceeds are reinvested at the
particular IRR, whereas the NPV approach
assumes reinvestment at the cost of capital.
Benefit Cost Ratio (BCR)
(1 r ) t
t 0
BCR n
Ct
(1 r ) t
t 0
Decision rules:
PV
BCR
I
12500 10000 30000 25000
( ) 50000
(1.12) (1.12) 2 (1.12) 3 (1.12) 4
Decision: ???
Advantages of BCR
• BCR indicates a relative and not absolute
measure of profits i.e. the benefit per dollar (Birr)
of investment.
Disadvantages of BCR
• This method cannot be employed when a
package of smaller projects is to be considered in
relation to a large project.
Discounted Payback Period
To overcome the limitations of the payback
period, the discounted payback period
method has been suggested
The decision is similar with payback
period. The difference is multiplying
each cash flow by discount factor.
Sensitivity Analysis
Measures of project worth are first calculated using
the best estimate of inputs and outputs and the
discount rate. The project decision will be based on
these best estimates.
However, how sensitive is a project in financial
prices and economic values?
There might be:
an increase in construction costs,
an extension of the implementation period
a fall in prices, etc.
51
It is analytical tool to test
systematically what happens to the
earning capacity of the project if
events differ from the estimates made
about them in planning.
The key variables to which sensitivity
analysis could be applied include: skill and
technology requirements, Price of inputs,
Price of output, Operating Costs, Sales
volume and Initial cost outlay.
52
Reworking an analysis to see what
happens under these changed
circumstances is called sensitivity
analysis.
All projects should be subjected to
sensitivity analysis.
In agriculture for example, projects are
sensitive to change in four principal areas:
Price of output and inputs, delay in
implementation, costs overrun & yield.
The application of sensitivity analysis
involves varying one project item at a
time and measuring the effect on project
worth. Because this is easier to interpret
in absolute terms, the project worth
measure generally employed in
sensitivity analysis is the net present
value (NPV).
Thank You!!