Marine Structure: SBEQ 3173 Civil Engineering Construction
Marine Structure: SBEQ 3173 Civil Engineering Construction
MARINE
STRUCTURE
TEMPORARY
STRUCTURE
TEMPORARY STRUCTURE
Temporary structures is a type of
structure that is employed to assist in the
formation of foundations or structures.
Provide working area at foundation level
from which ground and water is excluded
sufficiently to permit safe working.
TEMPORARY STRUCTURE FOR
MARINE WORKS
Temporary
Cofferdams Caissons
Cofferdam
V o l u m e o f w a t e r , v e l o c i t y o f f l o w
& tide levels
A c c e s s i b i l i t y o f s i t e
Cofferdam
Sheet
Rockfill Gravity Cribs Cellular Precast
Piles
Cofferdam
Cofferdam
Cofferdam
Sheet Pile Cofferdam
Box Open
Compresse
Monolithic
d Air
P r e f a b r i c a t e d b o x e s ,
usually in concrete with
sides and bottom, which
are set down on a prepared
base.
T h e b o x i s t h e n f i l l e d w i t h
Box Open
concrete from a massive
foundation for a pier or
similar structure.
U n s u i t a b l e w h e r e
foundations may be subject
to erosion by fast moving
Compresse water but still can be
Monolithic solved by setting the
d Air
caisson on the piled
foundation if the sub-strata
permit the driving of piles.
S t r u c t u r e s w h i c h a r e o p e n
at both top and bottom and
are suitable for foundations
in the water where the sub-
stratum is soft clay or silt
and therefore easily
Box Open excavated.
S u i t a b l e f o r d e e p
foundations in water.
T h e c a i s s o n s i s s u n k b y
grabbing soil through open
wells. When the caissons
Compresse has reached desired depth,
Monolithic
d Air
the bottom is plugged with
a layer of concrete or
ballast.
S u i t a b l e f o r s i n k i n g
foundations in troublesome
ground e.g ground
containing obstacles that
require moving by hand.
T h e c a i s s o n i s p o s i t i o n e d
and sunk and then is
lowered into the soil as the
Box Open soil is removed from within
it.
T h i s m e t h o d i s v e r y
suitable for foundations
which by other methods
might result in the
settlement of adjacent
Compresse structures.
Monolithic
d Air T h e a d v a n t a g e s i n c l u d e s
dry working conditions and
accurate levelling.
S i m i l a r t o o p e n c a i s s o n s
but differ as they are much
heavier.
C o n s i s t o f r e i n f o r c e d
concrete wall of sub-
stantial thickness to
provide sufficient weight to
Box Open prevent overturning.
O f t e n u s e d f o r q u a y w a l l s
which have to resist great
impact forces from ships
coming to berth.
U n s u i t a b l e f o r s i n k i n g
Compresse through very soft deposits
Monolithic
d Air because it would be
difficult to control the
verticality from the
structure.
Positioning of
Caissons
I f t h e c a i s s o n s i s t o b e f o u n d e d i n a r i v e r
or sea, it may be partly constructed in
dry docks and towed to the site.
T h e c a i s s o n a r e t o w e d o u t t o t h e s i t e b y
tugs and are positioned by one of this
following methods:
P i l i n g e n c l o s u r e o r d o l p h i n s
W i r e c a b l e s o r s u b m e r g e d a n c h o r s
A n c h o r e d p o n t o o n e s o r b a r g e s
R a d i o b u o y s a n d b e a c o n s
Cofferdam Caissons
Breakwater Docks
MARINE
STRUCTURE
Jetties Wharf
Benteng Pantai/Laut
Seawall
Breakwater Docks
MARINE
STRUCTURE
Jetties Wharf
Jeti Dermaga
SEA WALL
Sea walls are constructed to resist
encroachment by the sea
It is often incorporated into the
construction of a promenade
Sea walls are constructed in various
materials: masonry blocks, precast
concrete, in-situ concrete etc.
SEA WALL
The design of the wall should minimise
the effect of wave action and prevent the
under-scouring of the foundation.
Concrete blocks with projecting
reinforcement may be used in conjunction
with an in-situ backing
MASONRY SEA WALL PROMENADE
INSITU CONCRETE SEA WALL
PRECAST SEA WALL
DOCKS
Docks may be divided into two types:
DOCKS
A dry dock is a narrow basin or vessel
that can be flooded to allow a load to be
floated in, then drained to allow that
load to come to rest on a dry platform
Dry docks are used for the construction,
maintenance, and repair of ships, boats,
and other watercraft
DRY DOCKS
Dry docks differ in design from wet
docks in that they have to withstand
hydrostatic pressure when the dock is
emptied
The walls of the dock should be
incorporated with the floor to form a
rigid structure and so reduce uplift
DRY DOCKS
The walls are normally massive in-situ
structures which are cast in large, deep
trench excavations
The walls are cast in stages of up to 2
meters thick, with stepped construction
joints
DRY DOCKS
Longitudinal joints should be
constructed at intervals of 15 meters
These joints are essentially construction
joints with bars and should be filled with
bitumen or other sealing compound
DRY DOCKS
The floor of the dock must be strong
enough to distribute a ship’s load without
settlement or undue deflection
If the load encountered are very high, a
piling support may be adopted, both for
supporting a ship’s load and resisting
uplift
Lock entrance gates, normally of steel
construction, may be pivoted or sliding.
DRY DOCKS
DRY DOCKS
DRY DOCKS
DRY DOCKS
A wet dock is a dock where the level of
water in the dock is maintained despite
the raising and lowering of the tide
This makes transfer of cargo easier. It
works like a lock which controls the water
level and allows movement of ships
WET DOCKS
Wet docks are large areas of water
bounded by vertical solid walls against
which vessels tie up
The walls must be impermeable (last long)
to retain the water at high tide level
Locks are provided if entry to the dock
is desired at times other than high tide
WET DOCKS
The walls may be formed by sinking
monoliths to a suitable depth and joining
them together with in-situ concrete
A space of 2 to 3 meters is left between
the monoliths to facilitate jointing and
finishing
Alternatively, the walls may be
constructed with deep diaphragms,
decking being supported by cross-wall
diaphragm
WET DOCKS
WET DOCKS
WET DOCKS
WET DOCKS
WET DOCKS
WHARF
Wharf are berths for shipping which may
retain the surrounding soil or simply
provide mooring facilities
Those constructed to retain soil are
usually mass concrete walls built by
means of caisson or diaphragm walling
WHARF
Open wharf, which provide mooring
facilities at both sides, can be
constructed of piles with concrete decking
An alternative to in-situ concrete and
caisson construction is the use of precast
concrete blocks.
WHARF
WHARF
JETTIES
A jetty is any of a variety of structures
used in river, dock and maritime works.
The forms and construction of these
jetties are as varied as for their uses.
Jetties at the coast that have been
raised and extended, help prevent long
shore drift, so therefore slowing down
beach erosion.
JETTIES
Jetties jut out into the sea, usually at
right angles to the shore line, although T-
shaped and L-shaped jetties are not
uncommon
They are open structures, usually of
steel tubular or hexagonal piling with a
heavy concrete deck
They may be used for offloading heavy
cargoes, in which case the deck may
require extra bracing to the piles
JETTIES
The jetty structure must be
designed to withstand impact loads
and ‘bollard pulls’ from berthing
ships
This is usually accommodated by
r a k i n g p i l e c o n s t r u ct i o n a n d
fendering, the latter to avoid holing
the ship
JETTIES
If the sea bed is a rock formation, the
piling construction will not be
economically produced by normal driving
methods.
Therefore boreholes up to 600 mm
diameter may be bored into the sea bed
and steel or concrete piles grouted in.
JETTIES
JETTIES
JETTIES
JETTIES
JETTIES
JETTIES
JETTIES
JETTIES
BREAKWATERS
Breakwaters or moles are constructed in
the outer harbour area to dampen heavy
waves and swell so as to provide easier
entrance and exit of vessels
They may be constructed with concrete
blocks, rock fill, or a combination of both
BREAKWATERS
The choice of material will depend upon
the conditions of the site:
Depth of
Water
Foundatio
Range of
n
Tides
Condition
Material
Availabilit Weather
y
BREAKWATERS
Vertical-sided breakwaters are suitable
for shallow waters up to 15 meters deep;
working in depths above this proves
difficult for divers who position the block
Where block work is used, a foundation
is prepared by dredging the marine bed
and laying a concrete base
Blocks are lowered by cranes operated
from pontoons and are positioned by
divers.
BREAKWATERS
As with other large marine structures,
caissons are also commonly used for this type
of work and are particularly suited to
construction of breakwaters in deep waters
The caisson fill may be rock, sand or
concrete
Rubble or rock-fill breakwaters are suitable
for both shallow and deep waters
BREAKWATERS
The rock fill should contain heavy
stones, ranging from 1 to 5 tonnes
each in weight, to prevent movement
by wave action
The material is transported and
placed by bottom-opening barges,
some of which have a capacity of
600m3
BREAKWATERS
BREAKWATERS
BREAKWATERS
BREAKWATERS
BREAKWATERS
BREAKWATERS
A four pronged pre-cast concrete
block, the prongs radiating at 120
degree to each other from a
common centre.
Each prong is cylindrical in shape
Tetrapod
Fender Quay
Dolphin
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fenders are used in conjunction
with all the marine constructions
Fender / structures mentioned
They are used to absorb the
kinetic energies produced by
Quay berthing vessels
To achieve the necessary
absorption, they have to be
flexible and may take the form
Bollard of tubes or springs of metal,
rope and plastic
Mooring
Dolphin
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Mooring
Dolphin
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Mooring
Dolphin
Mooring
Dolphin
Fender
Once the mooring line is
attached to the bollard, it is
pulled tight.
Quay On large ships, this tightening
can be accomplished with the
help of heavy machinery called
mooring winches or capstans.
Bollard
Mooring
Dolphin
Fender
Quay
Bollard
Mooring
Dolphin
Fender
Fender
Quay
Bollard
Mooring
Thank
You!