SWD Rev 3
SWD Rev 3
TEAM MEMBERS
UNDER THE GUIDANCE OF
ABINASH KUMAR V -822719103001 Dr. PL.SENTHILKUMAR Ph.D.
PARTHIBAN S - 822719103030 Asst. Prof in Civil Engg
HARIHARAN D - 822719103315
INTRODUCTION
______________________________
02 Runoff Calculation
04 Estimation
05 Construction
C = coefficient of runoff
i = intensity of rainfall in mm/hour.
A = drainage area in hectares.
RUNOFF COEFFICIENT
___________________________________________
The whole quantity of rain water that falls over ground does not reach the sewer
lines or drains. A portion of it percolates in the ground, a portion evaporates, a
portion is stored in ponds and ditches, and only the remaining portion of rain
water reaches the drains and sewers. The runoff coefficient is a fraction which is
multiplied with the quantity of total rainfall, to determine the quantity of rain
water which will reach the sewers. After continuous rainfall for some time, the
ponds and ditches are filled up and the atmosphere becomes nearly saturated,
therefore the runoff coefficient mainly depends on the characteristics of ground
surface as porosity, wetness, ground cover etc.
RUNOFF CALCULATION
___________________________________________
Roofs 30 0.9
C = 0.505
RUNOFF CALCULATION
___________________________________________
Q = 0.7 m3/sec.
The discharge of stormwater which will reach the drain is 0.7 m3/sec.
SIZING OF THE DRAIN
___________________________________________
It was estimated from quantification that the peak discharge from the catchment area is 0.7 m 3/sec. Using Manning’s
equation, determining the best hydraulic cross-section for a rectangular channel.
Q = VA
Q =1/n x R x S x A-------(2)
2/3 1/2 0.7 = 1/0.014 x (y/2)2/3 x (0.03)1/2 x 2y2
y =0.3 m
For the best hydraulic section for rectangular drain
b = 2y and R = y/2 b = 2 x 0.3 = 0.6 m
Cross-sectional area of the drain (A) = by It is necessary to provide freeboard of at least 1Feat
(0.3m)
Substituting b = 2y into the area formula;
Cross-sectional area of the drain (A) = (2y) y = 2y2 Therefore,
Breadth = 0.6 m
SIZING OF THE DRAIN (Cont.)
_______________________________________________________
GEOTECHNICAL DESIGN
Given the information above, designing the drain wall and base requirements assuming
fcu = 20 N/mm2, fy = 450 N/mm2, cover to the reinforcements = 40 mm, diameter of the
reinforcements = 12 mm and thickness of the walls and base = 200 mm.
DIMENSIONS OF THE DRAIN
GEOTECHNICAL DESIGN – Cont.
WALL PRESSURE CALCULATIONS Wall 2
Active pressure at top of drain wall = qKa =5x0.33 =1.65 KN/m2
Active earth pressure Ka = 1- sin ɸ /1+ sin ɸ Active pressure at base of drain wall= qKa + Ka 2
Ka = 1- sin30°/1 = sin30° =1.65+(0.33x18x0.8)
Ka = 0.333 = 6.402 KN/m2
Wall 1 Passive pressure at top of drain wall = 0
Active earth pressure at top of drain wall = qKa =15x0.33 Passive pressure at base of wall = γwZ
= 4.95 kN/m2 = 9.8x0.6 =5.88KN/m2
Active pressure at base of the drain wall = qKa + Ka γ2 Net pressure at base of the wall = 6.402-5.88
= 4.95+4.752 = 0.522 kN/m2
= 9.702 kN/m2 Total vertical load (N)
Passive pressure at the top of the wall =0 Walls (WWS) =2 x (0.2 x 0.6 x 24) = 5.76 kN/m
Passive pressure at the base of the wall = γwZ = (99.8x0.60) Base (wb) =1x 0.2 x 24 = 4.8 kN/m
= 5.88 kN/m2 Wall (ww) = 0.3 x 0.6 x 9.8 = 1.764 kN/m
Net pressure at base of the wall =9.702-5.88 Total vertical load wws + wb + ww (N)
=3.822 kN/m2 N = 5.76 + 4.8 + 1.764
N = 12.324 kN/m
GEOTECHNICAL DESIGN – Cont.
Horizontal forces on drain walls due to surcharge load and RESISTANCE TO SLIDING
backfill Frictional force (Ff) = µN
Wall 1 = qKaZ + (0.5 x KaγZ x Z) – (0.5 x γwZ x Z) = 0.5 x 12.323
= (15 x 0.333 x 0.8) + (0.5 x 4.752 x 0.8) – (0.5 x 5.88 x 0.8) = 6.162 kN/m
= 3.996 + 1.901 – 2.352 Factor of safety =Ff/PA
= 3.545 kN/m =6.162/2.581
Wall 2 = qKaZ + (0.5 x KaγZ x Z) – (0.5 x γwZ x Z)
=2.387 >1.5
= (5 x 0.333 x 0.8) + (0.5 x 4.752 x 0.8) – (0.5 x 5.88 x 0.8) The FOS 2.3871.5.
therefore, the drain is very safe from sliding.
= 1.415 + 1.901 – 2.352
= 0.964 kN/m
Net horizontal force (PA) = 3.545 – 0.964 = 2.581 kN/m
GEOTECHNICAL DESIGN – Cont.
BEARING CAPACITY CHECK CHECK:
Bending moment about the centerline of the base D/6=1/6=0.167m Since eD/6, there is no tension in the drain base.
M = (w2 x 0.4) + (3.545 x 0.8/3) - (w1 x 0.4) - (0.964 x 0.8/3) Minimum pressure in the drain base (qmax)
V =(1.4 x 3.545)
V = 4.963 kN/m
= 0.032 N/mm2
=0.242
Since V< VC, no shear reinforcement required.
STRUCTURAL DESIGN - BASE
qmin = 8.183 kN/m2 = 8.183 x 1.4
On investigating the maximum design moment at point B
= 11.45 kN/m2
qmax =16.46 kN/m2 = 16.46 x 1.4 Water = 1.97kN/m
On investigating the maximum design moment at point, A Earth pressure = (11.45 x 11.2 x (1.2x2) + (23.04-11.45) x 1.2 x 0.5
x (2x1.2/3))
Water = 1.4 (9.8 x 0.3 x 0.8 x (0.8 / 2 + 0.2))
= 1.97 kN/m = 13.34kNm/m
Base = 1.4 (24 x 0.2 x 0.8 (0.8 / 2 + 0.2))
Net moment = 13.34-1.97-3.21=8.61kNm/m
= 3.21 kN/m
Earthwork pressure = (11.45 x 1.2 (1.2/2)) + (23.04-11.45) x 1.2 Since net moment at B > moment at A, we adopt 8.61 kNm for
x 0.5 x (1.1/3) design.
= 11.02 kN/m
Net moment = 11.02-3.21-1.97 = 5.84 kN/m
STRUCTURAL DESIGN - BASE
SHEAR CHECK
FLEXURAL DESIGN
K = M / (fcubd2) = (8.61 x 102) / (20 x 1000 x 155)2 Calculating the maximum shear force at any section of the drain base
Water = 1.4 x 9.8 x 0.3 x 0.8 = 3.29 kN/m
= 0.0017 < 0.15
Base = 1.4 x 24 x 0.8 = 5.37 kN/m
Ia = 0.5 + (0.25-k/0.9)0.5
Earth pressure = 0.5 x (23.04 -11.45) x 0.8 = 13.79kN/m
= 0.5 + (0.25-0.0017/0.9)0.5
Net shear force = 13.796-3.29-5.37
= 0.99
= 5.136kN/m
Since 0.99 > 0.95, Ia=0.95
Shear stress v = v/bd = (5.13 x 1000) / (100 x 155)
As, req = M / (0.95fy x Ia x d) = 0.033 N/mm2
Shear strength vc = 0.632 x (100AS/bd)1/3 x (400/d)1/4 x
=8.61x10 /(0.95x450x0.95x155)
6
(fcu x 25)1/3
=136.82mm2/m
= 0.632 x (100x420)/(100 x155))1/3 x
Asmin =(0.13bh)/100=0.13x1000x200/100 (400x155)1/4 x (20/25) 1/3
=0.48N/mm2
=260mm2 v < vo; 0.33 < 0.48
Provide 12mm bars @ 300mm c/c (As, prov=420mm2/m)
Since v < vc , No shear reinforcement required.
DETAILING
THANK YOU !