INTRODUCTION and Geotechnical Activities
INTRODUCTION and Geotechnical Activities
A typical geotechnical engineering project begins
with a review of project needs to define the required
material properties. Then follows a site investigation
of soil, rock, fault distribution and bedrock
properties on and below an area of interest to
determine their engineering properties including how
they will interact with, on or in a proposed
construction. Site investigations are needed to gain
an understanding of the area in or on which the
engineering will take place. Investigations can
include the assessment of the risk to humans,
property and the environment from natural hazards
such as earthquakes, landslides, sinkholes,
soil liquefaction, debris flows and rockfalls.
A geotechnical engineering then determines and designs the type of
foundations, earthworks, and/or pavement subgrades required for the
intended man-made structures to be built. Foundations are designed
and constructed for structures of various sizes such as high-rise
buildings, bridges, medium to large commercial buildings, and smaller
structures where the soil conditions do not allow code-based design.
Bridges
Retaining Walls
Large Culverts
Roadway Embankments
Buildings
Communication and Light Towers
Miscellaneous Structures
Soil properties
Atterberg Limits
Liquid limit, Plastic limit, and Shrinkage limit. These indices are used for estimation of
other engineering properties and for soil classification
Subsurface exploration usually involves in-situ testing (two common
examples of in-situ tests are the standard penetration test and
cone penetration test). In addition site investigation will often include
subsurface sampling and laboratory testing of the soil samples
retrieved. The digging of test pits and trenching (particularly for
locating faults and slide planes) may also be used to learn about soil
conditions at depth. Large diameter borings are rarely used due to
safety concerns and expense, but are sometimes used to allow a
geologist or engineer to be lowered into the borehole for direct visual
and manual examination of the soil and rock stratigraphy.
A variety of soil samplers exist to meet the needs of different
engineering projects. The standard penetration test (SPT), which uses a
thick-walled split spoon sampler, is the most common way to collect
disturbed samples. Piston samplers, employing a thin-walled tube, are
most commonly used for the collection of less disturbed samples.
More advanced methods, such as ground freezing and the Sherbrooke
block sampler, are superior, but even more expensive.
Surface exploration can include geologic mapping,
geophysical methods, and photogrammetry; or it can be
as simple as an engineer walking around to observe the
physical conditions at the site. Geologic mapping and
interpretation of geomorphology is typically completed
in consultation with a geologist or
engineering geologist.
Geophysical exploration is also sometimes used.
Geophysical techniques used for subsurface exploration
include measurement of seismic waves (pressure, shear,
and Rayleigh waves), surface-wave methods and/or
downhole methods, and electromagnetic surveys
(magnetometer, resistivity, and
ground-penetrating radar).
Surface investigations generally consist of in situ soil and
rock measurements such as those conducted on bedrock
outcrops, geophysical testing, quarry studies, and test pits.
These types of investigations may also include a site visit to
take photographs and determine potential issues. Laboratory
testing is conducted on samples from both surface and
subsurface investigations of both soil and rock.
-Prepare a boring plan for the field crews as a final step in the subsurface investigation
planning process. A complete, detailed, boring plan will help the field crews do their job more
efficiently. Include a plan view to scale of the investigation area that shows the following
items:
1. Existing topography, utilities, and contours
2.Existing Right-of-Way lines
3.Proposed Alignments
.4.Proposed Structures
.5.Proposed Boreholes, CPT Soundings, other In-situ tests with symbols, labels and county
coordinates
6.State Project Number
7.Charge Identifier (CID; used for timesheet and expense purposes) North Arrow
8. Street and highway labels
9.Site Plan (reference to nearest city)
Historical Bridge Plans with Plotted Borings
Pre-Design plans, profiles and cross sections
Historical Geotechnical Reports
Preliminary Bridge Plans and Bridge Surveys
Property Ownership Information
Utility location information
Contour Maps
Hydraulics Report -Hydraulics Report is generated by The
Bridge Office for all bridges and large culverts crossing
waterways. This report will give estimates for channel and
local (pier) scour needed for pile analysis. If there is a large
scour prediction, the engineer should plan to drill deeper
holes to account for the loss of overburden
Foundations
Slab foundations
A variant on spread footings is to have the entire structure bear
on a single slab of concrete underlying the entire area of the
structure. Slabs must be thick enough to provide sufficient
rigidity to spread the bearing loads somewhat uniformly, and
to minimize differential settlement across the foundation. In
some cases, flexure is allowed and the building is constructed
to tolerate small movements of the foundation instead. For
small structures, like single-family houses, the slab may be
less than 300 mm thick; for larger structures, the foundation
slab may be several meters thick.
Basements are a form of cantilever walls, but the forces on the basement
walls are greater than on conventional walls because the basement wall is not
free to move.
Excavation shoring
Shoring of temporary excavations frequently requires
a wall design which does not extend laterally beyond
the wall, so shoring extends below the planned base
of the excavation. Common methods of shoring are
the use of sheet piles or soldier beams and lagging.
Sheet piles are a form of driven piling using thin
interlocking sheets of steel to obtain a continuous
barrier in the ground, and are driven prior to
excavation. Soldier beams are constructed of wide
flange steel H sections spaced about 2–3 m apart,
driven prior to excavation. As the excavation
proceeds, horizontal timber or steel sheeting (lagging)
is inserted behind the H pile flanges.
Earthworks
a. Excavation
Excavation is the process of training earth according to requirement by removing the
soil from the site.
b. Filling
Filling is the process of training earth according to requirement by placing the soil on
the site.
c. Compaction
Compaction is the process by which the density of soil is increased and permeability of
soil is decreased. Fill placement work often has specifications requiring a specific degree
of compaction, or alternatively, specific properties of the compacted soil. In-situ soils
can be compacted by rolling, deep dynamic compaction, vibration, blasting, gyrating,
kneading, compaction grouting etc.
d. Ground Improvement
Ground Improvement is a technique that improves the engineering properties of the
treated soil mass. Usually, the properties modified are shear strength, stiffness and
permeability. Ground improvement has developed into a sophisticated tool to support
foundations for a wide variety of structures. Properly applied, i.e. after giving due
consideration to the nature of the ground being improved and the type and sensitivity
of the structures being built, ground improvement often reduces direct costs and
saves time
Slope stabilization
Slope stability is the potential of soil covered slopes to withstand and undergo
movement. Stability is determined by the balance ofshear stress and
shear strength. A previously stable slope may be initially affected by preparatory
factors, making the slope conditionally unstable. Triggering factors of a
slope failure can be climatic events can then make a slope actively unstable,
leading to mass movements. Mass movements can be caused by increases in
shear stress, such as loading, lateral pressure, and transient forces. Alternatively,
shear strength may be decreased by weathering, changes in pore water pressure,
and organic material.
Several modes of failure for earth slopes include falls, topples, slides, and flows.
In slopes with coarse grained soil or rocks, falls typically occur as the rapid
descent of rocks and other loose slope material. A slope topples when a large
column of soil tilts over its vertical axis at failure. Typical slope stability
analysis considers sliding failures, categorized mainly as rotational slides or
translational slides. As implied by the name, rotational slides fail along a
generally curved surface, while translational slides fail along a more planar
surface. A slope failing as a flow would resemble a fluid flowing downhill.
Offshore geotechnical engineering