Lecture 04 EE
Lecture 04 EE
ENGINEERING ECONOMICS
Demand Estimation
COST-ESTIMATION TECHNIQUES
Engineering economy studies need estimating the future cash flows
for feasible alternatives of its projects.
Often, the most difficult, expensive, and time-consuming part of an
engineering economy study is the estimation of
i. Costs
ii. Revenues
iii. residual values
iv. and other data pertaining to the alternatives being analyzed.
A decision based on the analysis is economically sound only if
these cost and revenue estimates are representative of what
subsequently will occur.
In an engineering economic analysis, the cost-estimating effort for
that analysis should be an integral part of a comprehensive planning
and design process
Results of cost estimation are used for a variety of purposes,
including the following:
1. Providing information used in setting a selling price for quoting,
bidding, or evaluating contracts
2. Determining whether a proposed product can be made and
distributed at a profit (for simplicity, price = cost + profit)
3. Evaluating how much capital can be justified for process changes or
other improvements
4. Establishing benchmarks for productivity improvement programs
There are two fundamental approaches to cost estimating:
the “top-down” approach and the “bottom-up” approach.
The top-down approach basically uses historical data from similar engineering
projects to estimate the costs, revenues, and other data for the current project
This approach is best used early in the estimating process when alternatives
This method breaks down a project into small, manageable units and estimates
their economic consequences. These smaller unit costs are added together
This approach usually works best when the detail concerning the desired
lifestyle.
For example, whether you own and operate an automobile and live in a “high-
end” apartment off-campus can dramatically affect the estimated expenses during
The WBS serves as a framework for defining all project work elements and
activities.
Figure 3-3 shows a diagram of a typical four-level WBS.
It is developed from the top (project level) down in successive levels of
detail.
The project is divided into its major work elements (Level 2).
These major elements are then divided to develop Level 3, and so on.
For example, an automobile (first level of the WBS) can be divided into
second-level components (or work elements) such as the chassis, drive train,
and electrical system.
Then each second-level component of the WBS can be subdivided further
into third-level elements.
The drive train, for example, can be subdivided into third-level components
such as the engine, differential, and transmission.
This process is continued until the desired detail in the definition and
description of the project or system is achieved.
Different numbering schemes may be used.
The objectives of numbering are to indicate the interrelationships of the work
elements in the hierarchy.
The scheme illustrated in Figure 3-3 is an alphanumeric format.
The Cost and Revenue Structure
The second basic component of the integrated approach for developing cash
flows (Figure 3-2) is the cost and revenue structure.
This structure is used to identify and categorize the costs and revenues that
need to be included in the analysis.
Detailed data are developed and organized within this structure for use with
the estimating techniques of Section 3.3 to prepare the cash-flow estimates.
The life-cycle concept and the WBS are important aids in developing the cost
and revenue structure for a project.
The life cycle defines a maximum time period and establishes a range of cost
and revenue elements that need to be considered in developing cash flows.
The WBS focuses the analyst’s effort on the specific functional and physical
of the structure, as are using the life-cycle concept and the WBS in its
preparation.
The following is a brief listing of some categories of costs and revenues that are
typically needed in an engineering economy study:
2. Labor costs
3. Material costs
4. Maintenance costs
6. Overhead costs
7. Disposal costs
Estimating Techniques (Models)
The third basic component of the integrated approach (Figure 3-2) involves
estimating techniques (models).
These techniques, together with the detailed cost and revenue data, are used to
develop individual cash-flow estimates and the overall net cash flow for each
alternative.
The purpose of estimating is to develop cash-flow projections—not to
produce exact data about the future, which is virtually impossible.
Neither a preliminary estimate nor a final estimate is expected to be exact;
rather, it should adequately suit the need at a reasonable cost and is often
presented as a range of numbers.
Cost and revenue estimates can be classified according to detail, accuracy, and
their intended use as follows:
1. Order-of-magnitude estimates: used in the planning and initial evaluation
stage of a project.
stage of a project.
the study.
Sources of Estimating Data
The information sources useful in cost and revenue estimating are too numerous
to list completely.
The following four major sources of information are listed roughly in order of
importance:
1. Accounting records. Accounting records are a prime source of information
for economic analyses; however, they are often not suitable for direct,
unadjusted use.
2. Other sources within the firm. The typical firm has a number of people and
records that may be excellent sources of estimating information. Examples
of functions within firms that keep records useful to economic analyses are
undertake R&D to generate it. Classic examples are developing a pilot plant
and undertaking a test market program.
The Internet can also be a source of cost-estimating data, though you should
assure
yourself that the information is from a reputable source. The following Web
sites
may be useful to you both professionally and personally.
Selected Estimating Techniques (Models)
The estimating models discussed in this section are applicable for order-of
They are useful in the initial selection of feasible alternatives for further
project.
Indexes
Costs and prices∗ vary with time for a number of reasons, including
(1) technological advances
(2) availability of labor and materials
(3) inflation.
An index is a dimensionless number that indicates how a cost or a price has
changed with
time (typically escalated) with respect to a base year.
Indexes provide a convenient means for developing present and future cost
and price estimates from historical data.
An estimate of the cost or selling price of an item in year n can be obtained by
multiplying the cost or price of the item at an earlier point in time (year k) by
prices. Use of this technique allows the cost or potential selling price of an item
to be taken from historical data with a specified base year and updated with an
index.
This concept can be applied at the lower levels of a WBS to estimate the cost
of equipment, materials, and labor, as well as at the top level of a WBS to estimate