ECBC Project Requirements
ECBC Project Requirements
ECBC Cell
Contents
Section 4: Envelope
Section 5: Heating Ventilation & Air Conditioning
Section 6: Service Hot Water & Pumping
Section 7: Lighting
Section 8: Electrical Power
No Interference:
O/U – Shaded (Natural/Artificial)/Well
11 Condenser
Ventilated Area/Closest to I/U.
Soft water to use
IS 15558
4 Fuel Equipment Efficiency
Thermal Efficiency – 80%
2 Motors IS 12615
All the parameters mentioned in the red font are mandatory and can not be avoided. If anyone
from the prescriptive parameter is avoided, simulation method is required to comply with the
Punjab ECBC.
For the energy simulation/energy modelling below software can be used to show the
compliance.
1. Equest
2. IES
3. Design Builder with Energy Plus
4. Trace
Energy modelling report along with he compliance form is required to submit while
approval/sanctioning application.
THANKS