Putting The Project Pieces Together Project Planning Training
Putting The Project Pieces Together Project Planning Training
Agenda Items
Introduction
Planning
Training Goals
Understand:
what planning is/is not where and when to start to adapt or tailor planning shortening the planning time what the project plan represents process and supporting materials
3
Project Approach
Project Manager
(marionette)
vs.
Project Management Approach (participatory)
4
Devising and maintaining a workable scheme to accomplish the business need that the project was undertaken to address.
Level of Activity
Execute
Plan
Close Initiate Control Finish Time
6
Start
Planning Objectives
Agreements on:
Scope Objectives Work activities Estimates Resources required Roles & responsibilities How to change & update the plan
8
Importance / Lessons
Straying from original goals, Inadequate resourcing Repetitive meetings - on what needs done Frustration - poorly defined, communicated, and coordinated work activities Issues not understood or related Decisions repetitively re-opened or readdressed
Input to Planning
Product Description Project Charter Historical Information Organizational Policies Constraints Assumptions
10
Supporting Detail
11
Process Flexibility
On most projects:
planning steps are the same the time spent and outcomes are flexible
High Formality
Complex Project
Simple Project
Loose Formality
12
TC = 3
BC = 5
Result - Potential High Complexity
13
14
5. Define and Sequence Activities (WBS) 6. Estimate Activity Durations & Determine Resource Needs (WBS)
14. Identify Risk & Create Risk Response Plan (Risk Mgmt Plan)
15
All the work, and only the work required Scope Statement - agreement of what is and is not Includes: primary objectives (products/deliverables) major deliverable milestones assumptions constraints completion criteria
16
4. Change Management
Management of changes to the primary objectives and major deliverables milestones.
The plan should include agreements of:
1. Change acceptance/expectations 2. How changes will be evaluated 3. How change will be managed
17
Manage
Plan Execute Control Close
Rqmts
Assess Determine Analyze Propose
Build
Construct
Deliver
Install Train
Test Validate
Integrate
Assess Current System Review Scope Analyze New Requirements Determine & Review GAPS Adjust Requirements
18
Examples WBSs
Example - WBS/How? Hierarchy Diagram Format
Project
2 1 M ANAGEM ENT 1 .1 I n it ia t e 1 .2 P la n 1 .3 E x e c u t e 1 .4 C o n t r o l 1 .5 C lo s e R E Q U IR E M E N T S 2 .1 A s s e s s 2 .2 D e t e r m in e 2 .3 A n a ly z e 2 .4 P r o p o s e 2 .5 .. D E S IG N 3 .1 E n g in e e r 3 .2 S p e c if y 3 .3 . 3 .4 .. B U IL D 4 .1 C o n s t r u c t 4 .2 T e s t 4 .3 V a lid a t e 4 .4 I n t e g r a t e D E L IV E R 5 .1 I n s t a ll 5 .2 T r a in 5 .3 .. 5 .4 ..
M anage
Plan Execute Control Close
Rqmts
Assess Determine Analyze Propose
Design
Engineer Specify
Build
Construct
Deliver
Install Train
Test Validate
Integrate
1. Write First draft of policy. 2. Review with team/manager. 3. Make changes as needed. 4. File notice w/Secretary of the State (SOS) 45 days before effective date. 5. Formally review policy analysts and advocates. 6. Make changes as needed. 7. Update program manuals and forms to reflect changes. 8. Submitted to the SOS by 5:00pm the day before it is to be effective.
List Format
19
Examples of Sequencing
Assess Current System Review Scope Analyze New Requirements Determine & Review GAPS Adjust Requirements
20
Quality Assurance
Quality Plan
Quality Control
9. Develop Schedule
determining start and finish dates for tasks and assigning resources
May Jun Jul Aug Sep Oct Nov
24
Define Resources
Define Dependents
Define Deliverables
25
Decem ber Janua 11/12 11/19 11/26 12/3 12/10 12/17 12/24 12/31
Initiate Product Description & Benefits Charter Project Proposal Approved Plan Scope Statement Work Plan Contract/Procurement Plan QA Plan Risk Plan Project Plans Approved Execute Requirements Analysis Design Coding Testing Maintenance Controls Status Reporting Change Management Communication Mgmt Closing Evaluation Maintenance Turn-over
9/18
9/27
Terminology This is a schedule or Gantt chart, not a WBS, not the project plan
26
& external labor (hrs,rates) refined during the materials course of the project , supplies definitive just prior contracts to construction special costs Estimate ROM + or - 50% Definitive + or - 20%
27
Intermediate + or - 30%
4 Business Analysts
3 Contract Developers
28
what, and how much, Actual solicitation how and when, is part of execution how to manage solicitations, selection, contract administration, and closeout
Procurement documents:
SOW
30
risks w/high effect and impact planning for risk mitigation or contingency
in requirements Design errors and omissions Roles and responsibilities misunderstood Poor estimates or unsupported estimates Insufficiently skilled staff Impossible timeframes
31
for example:
initial draft - reflects generic skills and duration final plan - reflects specific resources and dates
32
Hardcopy Binders
PMO Project Management Guide
33
34
35