Presentation Pipe Jacking Rev03
Presentation Pipe Jacking Rev03
CONTENTS
1. Sewer Diversion – Layout Plan of N109A and
Longitudinal Section
2. Procedure of Sewer Diversion
3. Pipe Jacking Method
4. Sequence of Pipe Jacking
5. Risk Involved
2
1. SEWER DIVERSION -
LOCATION PLAN OF N109A
3
LYL CONSULTANTS PTE LTD
4
LYL CONSULTANTS PTE LTD
MH37 MH35
MH36
MH33
MH34
MH32 MH31
LEGEND
Jacking Shaft
09/20/2023
Receiving Shaft MH32A
Jacking and Receiving shaft
Jacking Direction
LYL CONSULTANTS PTE LTD
LONGITUDINAL SECTION
6
LYL CONSULTANTS PTE LTD
LONGITUDINAL SECTION
7
LYL CONSULTANTS PTE LTD
SECTION OF CAISSON
09/20/2023 8
LYL CONSULTANTS PTE LTD
9
LYL CONSULTANTS PTE LTD
10
LYL CONSULTANTS PTE LTD
11
LYL CONSULTANTS PTE LTD
12
2. PROCEDURE OF
SEWER DIVERSION
13
LYL CONSULTANTS PTE LTD
14
3. PIPE JACKING METHOD
- MICRO TUNNELING
METHOD
15
LYL CONSULTANTS PTE LTD
16
LYL CONSULTANTS PTE LTD
1. Shield Machine
2. Slurry System
3. Jacking Systems
4. Control System
09/20/2023 17
LYL CONSULTANTS PTE LTD
20
LYL CONSULTANTS PTE LTD
21
LYL CONSULTANTS PTE LTD
22
LYL CONSULTANTS PTE LTD
23
LYL CONSULTANTS PTE LTD
24
4. SEQUENCE OF PIPE JACKING
25
LYL CONSULTANTS PTE LTD
JACKING SHIELD
Step 2: Extend the hydraulic jacks to push the jacking machine into the ground.
JACKING SHIELD
26
LYL CONSULTANTS PTE LTD
RECEIVING SHAFT
FIRST PIPE
JACKING SHIELD
Step 4: Extend hydraulic jacks allowing the jacking shield and pipe to advance simul-
taneously
JACKING SHIELD
27
LYL CONSULTANTS PTE LTD
INTERMEDIATE
JACKING
STATION RECEIVING SHAFT
JACKING SHIELD
Step 6: Extend the hydraulic jacks allowing the intermediate jacking station to push
the pipe and the jacking shield
RECEIVING SHAFT
JACKING SHAFT
JACKING SHIELD
28
LYL CONSULTANTS PTE LTD
JACKING SHIELD
JACKING SHIELD
29
LYL CONSULTANTS PTE LTD
JACKING SHAFT
JACKING SHIELD
Step 10: Extraction of the intermediate jacking station at the receiving shaft
INTERMEDIATE
JACKING
JACKING SHAFT STATION
30
LYL CONSULTANTS PTE LTD
31
LYL CONSULTANTS PTE LTD
32
5. RISKS INVOLVED
33
LYL CONSULTANTS PTE LTD
34
LYL CONSULTANTS PTE LTD
35
LYL CONSULTANTS PTE LTD
36
LYL CONSULTANTS PTE LTD
37
LYL CONSULTANTS PTE LTD
38
LYL CONSULTANTS PTE LTD
39
LYL CONSULTANTS PTE LTD
41
LYL CONSULTANTS PTE LTD
Contingency Measure:
• Stop work
• Inform to project parties and
the agencies.
42
LYL CONSULTANTS PTE LTD
Risk:
Damage to the existing utilities
(Water Pipe and other)
43
LYL CONSULTANTS PTE LTD
Mitigation:
• Install the Instrumentation
of Utility Settlement
Marker and Monitoring for
Existing Utilities.
44
LYL CONSULTANTS PTE LTD
Mitigation:
• Install the Instrumentation
of Utility Settlement
Marker and Monitoring for
Existing Water Pipe.
• Install the Instrumentation
of Water Stand Pipe and
Monitoring for Water Level
(Suggestion).
45
LYL CONSULTANTS PTE LTD
Contingency Measure:
• Stop work
• Inform to project parties
and the agencies.
46
Q&A
47