Unit I
Unit I
Unit I
09/25/2023
ESTIMATING
09/25/2023
Estimation 2
09/25/2023
To know Present Worth of the Structure.
09/25/2023
Purpose 4
09/25/2023
1. Approximate Estimates
1. Plinth Area Estimate
2. Cubic Rate Estimate
3. Service Unit Estimate
4. Approximate Quantity Method
2. Detailed Estimates
3. Revised Estimate
4. Supplementary Estimate
5. Supplementary & Revised Estimate
6. Annual Repair or Maintenance Estimate
Approximate Estimate 7
09/25/2023
Rough Estimate – Short Time.
Estimate based on Actual Cost of Similar Existing Structure.
Less Skill & Less time is required.
Purpose 8
09/25/2023
To know Feasibility of Project
To obtain Administrative Approval
For Planning the Project
To know Benefit Cost Ratio
Investment – To See Investment is justified or not
09/25/2023
Plinth Area Estimate 9
09/25/2023
The Volume or Cubic Content of the proposed building is
worked out.
Approx. Cost = Volume of the building x Rate per
volume
Length & Breadth @ Floor Level, Height from floor level to
top of roof
For Storeyed Structure Height should be between floor level of
one storey to next higher storey.
Foundation , Pllinth & Parapet above roof not taken into
account.
09/25/2023
Service Unit Method 11
Per Km Highway
Per Meter Bridge
Per Classroom School Building
Per Bed Hospital
Per Liter Water Tanks
Per Seat Cinema
09/25/2023
Approximate Quantity 12
Detailed Estimate
When Original Sanctioned Estimate is exceeded or likely to exceed
by more than 5 %.
When there is material deviation from the original Proposal.
09/25/2023
Supplementary Estimate 17
Detailed Estimate
Additional works are required to supplement the original work.
Further development is required during the progress of the work.
Fresh Detailed Estimate
09/25/2023
Supplementary & Revised 18
Estimate
Work is Partially abandoned & estimated cost of the remaining
work is less than 95% of the original work.
When there is material deviation / Changes in Design- Causes
Substantial Saving in Estimate
Original Estimate is Revised.
09/25/2023
Annual Repair / Maintenance 19
Estimate
Detailed Estimate
Maintain the structure work in proper order and safe condition
Building – White washing , Color Washing, Painting, Minor
Repairs.
Road Works – Patches, Repairs, Repairs of Bridges and Culverts.
09/25/2023
20
Data Required for Preparation of
Estimate
09/25/2023
Data Required For Preparation 21
of Estimates
1. Complete & Fully Dimensional Plans & sections of the
work
09/25/2023
Data Required For Preparation 22
of Estimates
2. Detailed Specifications – Nature, Class & materials to be
used.
3. Rates for Calculating Abstract of Cost. (Approve Ones)
09/25/2023
Item of Work 23
1. Excavation
2. Concrete in Foundation
3. Soling
4. Damp Proof Course
09/25/2023
Item of Work 25
5. Masonry work
6. Arch Masonry Work
7. Lintels over openings
8. RCC Work
09/25/2023
Item of Work 26
09/25/2023
Units of Measurement – Works - Nature, Size and Shape.
09/25/2023
Units of Measurement – 29
Principle
Mass, Voluminous and thick Cubic Units Length, Breadth,
Works Height/ Depth
Shallow , Thin & Surface Works Square Units Length & Breadth
Long & thin work Linear/ Running unit Linear
Measurement
Piece of work, Job work Numbers Numbers
09/25/2023
Units of Measurement 30
09/25/2023
Units of Measurement 31
09/25/2023
Units of Measurement 32
09/25/2023
Important Points 33
Estimates
09/25/2023
Face Sheet
Abstract Sheet
Measurement Sheet
Rate Analysis
Lead & Lift
Provisional Sum
Prime Cost
Contingencies
Work Charged Establishement
09/25/2023
Face Sheet 37
09/25/2023
Cost of each item of work is calculated in a
tabular form from the quantities already computed
and total cost is worked out in Abstract of
Estimate Form
The rates of different items of work are taken as
per schedule of rates or current workable rates or
analysed rate for finished items of work.
Face Sheet 39
09/25/2023
09/25/2023
Measurement Sheet 40
09/25/2023
09/25/2023
Rate Analysis 42
Incidental Expenses
Can’t be classified under any distinct item of sub head
3 to 5% Estimated Cost
Saving – Utilsed for extra item of work
09/25/2023
Work Charged Establishment 51
09/25/2023
54
09/25/2023
55
09/25/2023