Chap. 16
Chap. 16
16
Controlling a Stage
Table of Contents
1. Introduction
2. Purpose & Objective
3. Context
4. Introduction to Activities
4.1 Activity 1: Authorize a Work Package
4.2 Activity 2: Review Work Package Status
4.3 Activity 3: Receive complete Work Packages
4.4 Activity 4: Review the stage status
4.5 Activity 5: Report Highlights
4.6 Activity 6: Capture and Examine Issues & Risks
4.7 Activity 7: Escalate issues and risks
4.8 Activity 8: Take Corrective Action
1) Introduction
•WPs provide a way for the PM to group tasks and control how these are assigned, executed, followed up and
delivered.
•A WP contains the work required to create one or more products or sub-products.
•
•PRINCE2 recommends this Activity for PM:
Check the Stage Plan for the next products to create and the effort required.
The PM will have already examined the PID to understand project controls, quality standards required and
how products should be handed over when complete.
Defining a WP involves gathering the product descriptions and providing other relevant information to the
Team Manager, such as:
o techniques to use,
o Configuration Management requirements,
o maintenance, tolerances,
o key milestones,
o reporting,
o escalation arrangements.
All future WPs in the stage or in the project can use a similar definition of a WPs.
Just change the format as needed.
The PM can then review the WP with the Team Manager, so they understand what needs to be done and accept
it. Then they can be authorized to start.
4.2 Activity 1: Authorize a Work Package
4.2 Activity 2: Review Work Package Status
•This is where the PM reviews the work being performed by the teams.
•The name of this activity is Review Work Package Status, so the PMs review the
work that has been assigned in the WPs.
•The main input file will be the Checkpoint Report created by the Team Manager on
a regular basis.
•The PM will review the Checkpoint Report and can compare it with the Team Plan.
•They will also review entries in the Quality Register to see if products have passed
quality tests and to update the Configuration Items Record where necessary – that
is, to show that a product has been developed, tested and accepted.
•The PM will also update the Stage Plan to show that products have been delivered,
or perhaps to show a delay.
4.2 Activity 2: Review Work Package Status
4.3 Activity 3: Receive complete Work Packages
•The PM ensures that the Teams have completed the work defined in the WPs by
checking the Quality Register and seeing if products have been checked &
approved.
•The PM can then update the Configuration Item Records for each approved product
and update the Stage Plan to show the WP has been completed.
•Then the Stage Plan is updated to show that products in the WP are complete.
•Once these products have been approved, they cannot be changed without using the
change control process.
•This is normal, as the products have been created, tested, approved and accepted.
•The completed products are stored as described in the Configuration Management
Document.
4.3 Activity 3: Receive complete Work Packages
4.4 Activity 4: Review the stage status
•PM reviews what has happened so far and compares it with what is likely to happen.
•This gives an accurate picture of the current progress.
•PM do in this activity, do the following:
Review current stage, check Configuration Management information, check Quality Register for
issues, check Risk Register for new or revised risks, capture and examine issues using the issues
register, and check status of corrective actions if in progress.
If there is an issue or risk that needs to be escalated, or a corrective action that needs to be taken,
the PM will use other activities in the Controlling s Stage Process to do this.
PM check the Benefits Review Plan to see if it needs to be updated and if the products have been
correctly handed over.
Due to the range of tasks carried out in this Activity, the PM update the Risk Register, Issue
Register, Stage Plan, Lessons Log and Issue Report
4.4 Activity 4: Review the stage status
4.5 Activity 5: Report Highlights
4.6 Activity 6: Capture and Examine Issues & Risks
4.7 Activity 7: Escalate issues and risks
Project Managers should escalate an Issue or Risk if they believe that the Issue or the Risk will take
the stage out of tolerance.
An “Exception Report” is used to document the Issue or Risk, but it could take some time to
investigate and gather the required information;
therefore, there are two steps:
•The Project Manager will first send an Early Notification to the Project Board which will be
followed by the Exception Report.
•The early notification can be an email. In some companies, reporting risks or issues may not be the
cool executive thing to do for the Project Manager, especially if you work in an environment where
they like to shoot the messenger.
•the earlier you escalate, the more time is available to implement corrective actions.
4.7 Activity 7: Escalate issues and risks
The PM is able to solve some minor issues and risks on their own and that doesn’t put the stage out
of tolerance.
Taking corrective action is managed by the PM, as they implement the advice usually given by the
Project Board to correct the issue or risk while keeping the stage within tolerance.
Once the corrective actions have been taken, the PM checks the work and updates the normal
documents:
• Issues Register and Issues Report if there is an Issue or update the Risk Register if there is a
Risk.
• They could update the Stage Plan to show extra work done and Configuration Item Records to
show what has changed in a product.
Taking Corrective Action is used when extra work has to be done and the stage stays within
tolerance.
An Exception Plan is used when the Stage will go out of tolerance, so the stage can take much
longer than originally planned.
4.8 Activity 8: Take Corrective Action
thanks for your attention