Ch.4 Load Estimation 2023
Ch.4 Load Estimation 2023
Introduced by
Hani Abdel-Azizi
Ahmed Mohamed
Introduction:
- We estimate the loads to calculate the principle of the project
- Of course, in the design stage, this will be an estimate for the minimum loads, and when we want to calculate the value of the transformer, we will recalculate with the final estimate.
What are the methods of estimating loads?
- Connected load.
- demand factor
- Diversity factor
- load factor
- maximum demand.
Connected Load
- This is calculated in Kilo-Watt (or kW). It's the permissible total Kilo-Watt
provided to a meter based on the devices connected to the meter
Demand factor
It is the ratio of the maximum load demand in an electrical system to the total
sum of loads connected to the system. In other words, it is not normal for you
to operate all the lighting loads at the same time for a building. Rather, it is
normal for only a certain percentage of the total lighting load to work, and it is
less than 100%, and therefore the value of the demand coefficient will be less
than one.
Demand factor for residential building according to IEC.
Illumination: 50% of total connected load. Small appliance
circuits: 100% of rated load for maximum outlet wattage in the
circuit plus 40% of the total connected loads of other outlets in
the circuit.
The diversity factor differs from the demand coefficient in that it is not related to a specific
type of load but is related to the time spacing when operating a group of loads of a different
nature, washing machine loads, lighting.
Type of load Demand factor
Cinemas 0.7 - 0.9
Shops 0.5
Theaters 0.6 - 0.8
Lifts 0.85 - 0.95
Hospitals
Kitchen 0.6
Lifts 1
Laundry 0.6
Sterilization 0.4
Medical equipment 0.6
Industry
Lighting. 1
General purpose equipment 0.4
Semi-continuous operations: paper mills, refineries, rubber, 0.6
Continuous operations: textile mills, chemicals, etc. 0.9
LOAD FACTOR:
Load factor is the actual a mount of kilowatt-hours (kWh) delivered on a system in a
designated period of time , as opposed to the total possible kWh that could be
delivered on a system in a designated period of time .
Egyptian Code:
Total electrical Loads
Total floors loads= Load Density (KVA/100m²) x Build up Area /100 (m²)
For villa
According to Egyptian Code, we will take The load density for ground floor plan
= ground floor plan for first floor plan = 10 (KVA/100m²)
Connect load (kVA)
The ground=20.95
The first =20.92
The floor =19.63
Demand load /Bu (KVA)= Demand factor* Max Demand with spare (KVA)
The ground=17.74
The first =17.71
The floor =16.33
Total Demand load =51.17
P elev.= 15 –25 Kw