Chapter 06
Chapter 06
Developing a
Project Plan
McGraw-Hill/Irwin Copyright © 2008 by The McGraw-Hill Companies, Inc. All Rights Reserved.
6-2
Developing the Project Plan
The Project Network
A flow chart that graphically depicts the
sequence, interdependencies, and start and
finish times of the project job plan of activities that
is the critical path through the network
o Provides the basis for scheduling labor and
equipment
o Provides an estimate of the project’s duration
o Provides a basis for budgeting cash flow
o Highlights activities that are “critical” and should not
be delayed
o Help managers get and stay on plan
6-3
From Work Package to Network
WBS/Work Packages to Network
FIGURE 6.1
6-4
From Work Package to Network (cont’d)
WBS/Work Packages to Network (cont’d)
6-5
Constructing a Project Network
Terminology
6-6
Constructing a Project Network (cont’d)
Terminology
A B D
Activity-on-Arrow (AOA)
o Uses an arrow to depict an activity D
6-8
Basic Rules to Follow in Developing
Project Networks
Networks typically flow from left to right.
An activity cannot begin until all of its activities are
complete.
Arrows indicate precedence and flow and can cross
over each other.
Identify each activity with a unique number; this
number must be greater than its predecessors.
Looping is not allowed.
Conditional statements are not allowed.
Use common start and stop nodes.
6-9
Activity-on-Node Fundamentals
FIGURE 6.2
6-10
Activity-on-Node Fundamentals (cont’d)
6-11
Network Information
TABLE 6.1
6-12
Koll Business Center—Partial Network
FIGURE 6.3
6-13
Koll Business Center—Complete Network
FIGURE 6.4
6-14
Network Computation Process
Forward Pass—Earliest Times
How soon can the activity start? (early start—ES)
How soon can the activity finish? (early finish—EF)
How soon can the project finish? (expected time—
ET)
Backward Pass—Latest Times
How late can the activity start? (late start—LS)
How late can the activity finish? (late finish—LF)
Which activities represent the critical path?
How long can it be delayed? (slack or float—SL)
6-15
Network Information
TABLE 6.2
6-16
Activity-on-Node Network
FIGURE 6.5
6-17
Activity-on-Node Network Forward Pass
FIGURE 6.6
6-18
Forward Pass Computation
Addactivity times along each path in the
network (ES + Duration = EF).
Carry the early finish (EF) to the next
activity where it becomes its early start
(ES) unless…
The next succeeding activity is a merge
activity, in which case the largest EF of all
preceding activities is selected.
6-19
Activity-on-Node Network Backward Pass
FIGURE 6.7
6-20
Backward Pass Computation
Subtract
activity times along each path in
the network (LF - Duration = LS).
Carry
the late start (LS) to the next activity
where it becomes its late finish (LF)
unless...
The next succeeding activity is a burst
activity, in which case the smallest LF of
all preceding activities is selected.
6-21
Determining Slack (or Float)
Free Slack (or Float)
The amount of time an activity can be delayed
without delaying connected successor
activities
Total Slack
The amount of time an activity can be delayed
without delaying the entire project
Thecritical path is the network path(s) that
has (have) the least slack in common.
6-22
Sensitivity of a Network
The likelihood the original critical path(s)
will change once the project is initiated.
Function of:
o The number of critical paths
o The amount of slack across near critical
activities
6-23
Activity-on-Node Network with Slack
FIGURE 6.8
6-24
Practical Considerations
Network logic errors
Activity numbering
Use of computers to develop networks
Calendar dates
Multiple starts and multiple projects
6-25
Illogical Loop
FIGURE 6.9
6-26
Air Control Project
FIGURE 6.10
6-27
Air Control Project (cont’d)
FIGURE 6.11
6-28
Extended Network Techniques
to Come Close to Reality
Laddering
Activities are broken into segments so the following
activity can begin sooner and not delay the work.
Lags
The minimum amount of time a dependent activity
must be delayed to begin or end
o Lengthy activities are broken down to reduce the delay
in the start of successor activities.
o Lags can be used to constrain finish-to-start, start-to-
start, finish-to-finish, start-to-finish, or combination
relationships.
6-29
Example of Laddering Using
Finish-to-Start Relationship
FIGURE 6.12
6-30
Use of Lags
Finish-to-Start Relationship
FIGURE 6.13
Start-to-Start Relationship
FIGURE 6.14
6-31
Use of Lags (cont’d)
Use of Lags to
Reduce Detail
FIGURE 6.15
6-32
New Product
Development
Process
FIGURE 6.16
6-33
Use of Lags (cont’d)
Finish-to-Finish
Relationship
FIGURE 6.17
Start-to-Finish
Relationship FIGURE 6.18
6-34
Network Using Lags
FIGURE 6.20
6-35
Hammock Activities
Hammock Activity
An activity that spans over a segment of a
project
Duration of hammock activities is determined
after the network plan is drawn.
Hammock activities are used to aggregate
sections of the project to facilitate getting the
right amount of detail for specific sections of a
project.
6-36
Hammock Activity Example
FIGURE 6.21
6-37
Key Terms
Activity Gantt chart
Activity-on-arrow (AOA) Hammock activity
Activity-on-node (AON) Lag relationship
Burst activity Merge activity
Concurrent engineering Network sensitivity
Critical path Parallel activity
Early and late times Slack/float—total and free
6-38
Activity-on-Arrow Network
Building Blocks
FIGURE A6.1
6-39
Activity-on-Arrow Network
Fundamentals
FIGURE A6.2
6-40
Activity-on-Arrow Network
Fundamentals
6-41
Koll Center Project: Network Information
TABLE A6.3
6-42
Partial Koll Business Center
AOA Network
FIGURE A6.3
6-43
Partial AOA Koll Network
FIGURE A6.4
6-44
Partial AOA Koll Network (cont’d)
6-45
Activity-on-Arrow Network
FIGURE A6.5
6-46
Activity-on-Arrow Network
Forward Pass
FIGURE A6.6
6-47
Activity-on-Arrow Network
Backward Pass
FIGURE A6.7
6-48
Activity-on-Arrow Network Backward
Pass, Forward Pass, and Slack
FIGURE A6.8
6-49
Air Control Inc. Custom Order
Project—AOA Network
Diagram
FIGURE A6.9
6-50
Comparison of AON and AOA Methods