Pee14-M Module 8 - Pert CPM
Pee14-M Module 8 - Pert CPM
Module 8
PERT / CPM
CONTENTS:
I. Introduction to Project Management
II. PERT
III. Key Concepts of PERT
IV. Advantages of PERT
V. Limitations of PERT
VI. CPM
VII. Key Concepts of CPM
VIII. Advantages of CPM
IX. Limitations of CPM
X. Comparison Between PERT and CPM
XII. Conclusion
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
PERT / CPM
II. PERT
Program Evaluation and Review Technique was developed in the late 1950 by
the US Navy submarine missile programme and was applied in 1958.
PERT is a statistical tool in project management that shows the time taken by
each component of project and the total time required for its completion.
PERT breaks down the project into events, activity, and lays down their proper
sequence relationship and duration in the form of network.
PERT is a technique representing project plan in network.
This is represented in a graphic form known as Network Diagram.
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
EXAMPLE OF PERT
A Gantt chart using Microsoft Project
Since Saturday and Sunday are not work days and are thus excluded from the
schedule, some bars on the Gantt chart are longer if they cut through a weekend.
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
EXAMPLE OF PERT
In the following example there are seven tasks, labeled A through G. Some
tasks can be done concurrently (A and B) while others cannot be done until their
predecessor task is complete (C cannot begin until A is complete). Additionally,
each task has three time estimates: the optimistic time estimate (O), the most likely
or normal time estimate (M), and the pessimistic time estimate (P). The expected
time (TE) is computed using the formula (O + 4M + P) / 6.
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
EXAMPLE OF PERT
Creating network diagram by hand or by using diagram software
2 Types of Network Diagram
1. Activity on Arrow (AOA) – The duration is denoted on arrow
connecting diagram nodes
2. Activity on Node (AON) – In such diagram, the information about the
task duration is denoted in the diagram node and each task is represented in the
form of rectangle with definite set of fields.
- Easier to create and interpret.
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
EXAMPLE OF PERT
A Network Diagram using Microsoft Project
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
VI. CPM
The critical path method (CPM) is a technique where you identify tasks
that are necessary for project completion and determine scheduling flexibilities. A
critical path in project management is the longest sequence of activities that must
be finished on time in order for the entire project to be complete. Any delays in
critical tasks will delay the rest of the project.
CPM revolves around discovering the most important tasks in the project
timeline, identifying task dependencies, and calculating task durations.
CPM was developed in the late 1950s by Morgan R. Walker and James E.
Kelley Jr. as a method to resolve the issue of increased costs due to inefficient
scheduling. Since then, CPM has become popular for planning projects and
prioritizing tasks. It helps you break down complex projects into individual tasks
and gain a better understanding of the project’s flexibility.
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
PERT / CPM
Task B is dependent on A
Task C is dependent on B
Tasks C and D can run in parallel
Task E is dependent on D
Task F is dependent on C, D, and E
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
PERT / CPM
EXAMPLE OF CPM
An Electrical Engineering project has various tasks related to designing and implementing an
electrical system.
Here are the activities, durations, and dependencies:
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
TASK A
TASK B
1. Create a Network Diagram (4 Days)
TASK C
(3 Days)
TASK D
(6 Days)
TASK E TASK F
(7 Days) (8 Days)
TASK G
(5 Days)
TASK H
(4 Days)
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
TASK A
TASK B
2. Calculate Early Start (ES) and Early Finish (EF) (4 Days)
PERT / CPM
TASK A
TASK B
2. Calculate Early Start (ES) and Early Finish (EF) (4 Days)
PERT / CPM
TASK A
TASK B
2. Calculate Early Start (ES) and Early Finish (EF) (4 Days)
TASK H
(4 Days)
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
TASK A
TASK B
3. Calculate Late Start (LS) and Late Finish (LF): (4 Days)
PERT / CPM
TASK A
TASK B
3. Calculate Late Start (LS) and Late Finish (LF): (4 Days)
PERT / CPM
TASK A
TASK B
3. Calculate Late Start (LS) and Late Finish (LF): (4 Days)
TASK H
(4 Days)
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
TASK A
TASK B
In this example, the critical path is (4 Days)
TASK E TASK F
(7 Days) (8 Days)
TASK G
(5 Days)
TASK H
(4 Days)
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
XI. CONCLUSION
In conclusion, both PERT and CPM are valuable tools in the project
manager's toolkit. The selection between them should be based on the specific
needs and uncertainties of the project at hand, with a focus on effective
communication, adaptation, and strategic decision-making throughout the project
lifecycle.
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
PERT / CPM
REFERENCES:
1. Introduction to project management, “Project Smart”, (n.d.),
https://www.projectsmart.co.uk/lifecycle-and-methodology/introduction-
project-management.php
2. The importance of Project Management (with examples), (n.d.),
https://www.indeed.com/career-advice/career-development/importance-of-
project-management
3. What is Pert in project management?, “Versatile & Robust Project
Management Software”, (n.d.). https://www.wrike.com/project- management-
guide/faq/what-is-pert-in-project-management/
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
REFERENCES:
4. Project Evaluation Review Technique (PERT), Corporate Finance
Institute, (2023, October 16),
https://corporatefinanceinstitute.com/resources/management/project-
evaluation-review-technique-pert/
• 5. Wikimedia Foundation, (2023, October 2), Program evaluation and
review technique, Wikipedia,
https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique#
:~:text=The%20program%20evaluation%20and%20review,activities
%20( A%20through%20F)
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
REFERENCES:
6. Asana, T., (2021, October 16), Use critical path method (CPM) for
Project Management [2023] • asana, https://asana.com/resources/critical- path-
method
7. GeeksforGeeks, (2020, March 2), Advantages and disadvantages of
critical path method (CPM), GeeksforGeeks.
https://www.geeksforgeeks.org/advantages-and-disadvantages-of-critical- path-
method-cpm/
THANK YOU!
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
ASSIGNMENT:
Apply the PERT and Create a Network Diagram for the following tasks below.
Consider a project in electrical engineering where a team is tasked with designing and
implementing an electrical control system for a manufacturing plant. The project has several tasks,
and there is uncertainty regarding the duration of each task. Create a PERT analysis for this
project, including calculations and a network diagram.
1. Identifying the Tasks
Project Planning:
Task 1: Define project requirements
Task 2: Create system design specifications
Task 3: Plan resource allocation
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
ASSIGNMENT:
Apply the PERT and Create a Network Diagram for the following tasks below.
Hardware Development
Task 4: Design electrical circuits
Task 5: Procure necessary components
Task 6: Assemble control panels
Software Development
Task 7: Develop control algorithms
Task 8: Program microcontrollers
Task 9: Test and debug software
Testing and Integration
Task 10: System integration and testing
Task 11: Client acceptance testing
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
ASSIGNMENT:
Apply the PERT and Create a Network Diagram for the following tasks below.
2. Estimate Time
PEE14-M MANAGEMENT OF ENGINEERING PROJECTS
PERT / CPM
ASSIGNMENT:
Apply the PERT and Create a Network Diagram for the following tasks below.
3. Dependency
Task Dependency Explanation
This task can start independently as it
Define Project Requirements None involves outlining the project's
requirements.
Design specifications depend on the
Create Design Specifications Define Project Requirements (Task 1)
finalized project requirements.
Resource allocation planning is based on
Plan Resource Allocation Define Project Requirements (Task 1)
project requirements.
Circuit design is guided by the system
Design Electrical Circuits Create Design Specifications (Task 2)
specifications.
Components procurement depends on the
Procure Necessary Components Design Electrical Circuits (Task 4)
finalized circuit designs.
Control panel assembly requires the
Assemble Control Panels Procure Necessary Components (Task 5)
components to be available.
Algorithm development is based on the
Develop Control Algorithms Create Design Specifications (Task 2)
system specifications.
Microcontroller programming is based on
Program Microcontrollers Develop Control Algorithms (Task 7)
the control algorithms.
Testing and debugging depend on the
Test and Debug Software Program Microcontrollers (Task 8)
programmed software.
Plan Resource Allocation (Task 3), Integration and testing require resources,
System Integration and Testing Assemble Control Panels (Task 6), assembled control panels, and tested
Test and Debug Software (Task 9) software.
Client acceptance testing is the final step
Client Acceptance Testing System Integration and Testing (Task 10) after system integration and testing are
completed.