2023.11.14 Daily Work Report PT. GLOBAL

This document provides a progress report on the renovation project at the Chang Shin factory for November 14, 2023. It includes a table tracking the progress of different renovation divisions in meters completed for tasks like installing gutter frames, roofing materials, and scaffolding. It states that 11 workers are assigned across different roles like roof workers and cleaning. A schedule shows that installation of roofing materials and gutters is planned to be completed by December 30th. Location photos are also included to document the current state of renovation areas.

Uploaded by

PasyaHumendru
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
44 views4 pages

2023.11.14 Daily Work Report PT. GLOBAL

This document provides a progress report on the renovation project at the Chang Shin factory for November 14, 2023. It includes a table tracking the progress of different renovation divisions in meters completed for tasks like installing gutter frames, roofing materials, and scaffolding. It states that 11 workers are assigned across different roles like roof workers and cleaning. A schedule shows that installation of roofing materials and gutters is planned to be completed by December 30th. Location photos are also included to document the current state of renovation areas.

Uploaded by

PasyaHumendru
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PT.

LIK -
▣ Renovation Project – CHANG SHIN FACTORY
Times : 8 am – 18.00 pm Times : -

2023-11-14

Progress
Division Unit
Total Before Today Accum. %

ZINCALUM GUTTER 0.4 TCT + ASPALT WATER PROF m1 1,488 0 0 0 0%

GUTTER FRAME ZINCLUM 0.4TCT m1 1,488 130.2 241.8 372 25%

SILICON, RIVET, BOLT SUB MATERIAL m1 1,488 130.2 13.8 144 9.7%

FRP ROOF THICKNESS 1.5T SUSUPUTIH


m1 6,240 0 0 0 0%

FLASING FOR FRP(SAMPING FRP ONLY) 0,3T with


m1 12,480 0 0 0 0%
Water proof type

SCAFOLDING set 20 0 20 20 100%

REMOVE ROOF AND WALL TO INSTALL GUTTER m1 1,488 130.2 241.8 372 25%
PT. LIK -
▣ Renovation Project – CHANG SHIN FACTORY
Times : 8 am – 18.00 pm Times : -

Worker
Division Staff Supir SUM Remark
Roof worker Cleaning operator
Manpower 1 1 7 2 11
Equipment

□ Schedule

6.11 30.12
Devision
0 10 20 30 0 10 20 30
11/06 FINISH 12/30
FRP

11/06 FINISH 12/30


GUTTER
PT. LIK -
LOCATION - Before Today

JJC

JJC – Plan C

JJC - ACC
JJC – Plan B

JJC – Plan A
PT. LIK -
DOCUMENTATION WORK