BUS1040 Lecture Week 5
BUS1040 Lecture Week 5
Week 5
Remember:
-Please Sit with Your Project Teams
-Hand-in your teams “Signed” Team Contract at the end of the class
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
How to Create a Plan - Continued
Step #3 - Creating the Action Plan
• Ensure that the deliverable or output for each work package is defined
• For the tasks in each work package, identify the relevant data (I.e. time, equipment, materials)
• List the personnel and organizations responsible for each task
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
The Project Planning Phase
Project Project Goal:
Definition Planning Create a plan for WHO,
“WHAT” Will We “HOW” Will We
is doing WHAT,
Achieve? Deliver The “WHAT”? by WHEN
• Needs Assessment •Deliverables
•Value Proposition •Work Packages
(WBS)
•Authorization
(Charter) •Project Plan Deliverables:
•Stakeholders •Timeline •Project Plan
•Requirements
(Schedule) •Product Plan
(Stakeholder Goals) •Budget
(Schematic)
•Project Scope •Final Budget
•Documentation:
Project Definition
Document
Approaches to Planning
1. Waterfall Planning
Sequential Process, where progress is seen as flowing steadily
downwards (like a waterfall) through the project phases
Approaches to Planning
http://project-management-knowledge.com/definitions/c/critical-path/
Calculating the Length of a Project
Assuming a project involves 3 tasks, all starting on the same day
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Example: Constructing a Network Diagram
The Data: (Collected after completing your Work Package or Work Breakdown Structure)
Step #1 –From the “Start”, identify the Tasks that do not have any Predecessor Activities
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Example: Constructing a Network Diagram
Step #2 –Build on the tasks that depend on the completion of these tasks.
Continue to build on the tasks that depend on the completion of these tasks.
When completed, make sure that the project is closed off at a single “END”
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Example: Constructing a Network Diagram
Step #3 – Add in the times required to complete each task.
The Critical Path is then defined as the path with the longest duration from Start to End
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Example: Constructing a Network Diagram
Example:
How many weeks do we have to open this business?
Example: Constructing a Network Diagram
Step #4 – Calculate Slack for activities which do not appear along the Critical Path
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
Example: Constructing a Network Diagram
“Slack” or “Float” Time
Total float is the duration of delay allowed within the project which
will not interfere with the projected completion date
http://project-management-knowledge.com/definitions/t/total-float/
Participation Assignment (2%)
The following is an actual previous midterm exam question that focused on networks, critical paths and
slack times. Complete individually and hand-in before the end of class
Why is it important?
• Consistent framework for planning, scheduling, monitoring,
and controlling the project
• Illustrates the interdependence of all tasks, work packages,
and work elements
• It indicates the times when specific resources must be
available to work
• It determines an expected project completion date
• It identifies so-called critical activities that, if delayed, will
delay the project completion time
• It identifies activities with slack that can be delayed for
specific periods without penalty
Project Management: A Managerial Approach – Samuel J. Mantel, Jr. & Jack R. Meredith. Fourth Edition
For Next Week