Group 1 Cost Estimation Report With Animation
Group 1 Cost Estimation Report With Animation
COST
ESTIMATION
• Approximation of the cost of a program, project, or operation.
• The product of the cost estimating process.
• Has a single total value and may have identifiable component values.
• Often needed to support evaluations of project feasibility or funding
requirements in support of planning.
• Often used to establish a budget as the cost constraint for a project or
operation.
• A problem with a cost overrun can be avoided with a credible,
reliable, and accurate cost estimate.
COST ESTIMATING
COST ESTIMATE
METHODS
METHODS
• The method used for most definitive estimates is to fully define
and understand the scope, take off or quantify the scope, and
apply costing to the scope, which can then be summed to a total
cost.
• Application of best practices helps ensure a high – quality
estimate. “Certain best practices should be followed if accurate
and credible cost estimates to be developed. These best
practices represent an overall process of established, repeatable
methods that result in high-quality cost estimates that are
comprehensive and accurate and that can be easily and clearly
traced, replicated, and updated.”
TYPES OF COST
ESTIMATE
The required level of accuracy coupled with the amount of
information about the project that is available will dictate the type
of estimate that can be prepared. The different estimating methods
are discussed below.
Divide the total length of the fence by the length of one block
Example:
An interior door assembly might include the door, frame, hinges, trim,
doorknob, shims, and nails, and the quantity of each part necessary to
complete the work. When creating a takeoff, you can insert the interior door
assembly instead of each of the individual parts needed. You only need to
then enter the quantity of interior door assemblies needed in the project.
When you compute the takeoff, Contractor determines the total number of
parts needed to complete the door assemblies.
TYPES OF COST
ESTIMATE
ASSEMBLY ESTIMATE
The components are grouped into assemblies, consisting of
items that would be installed together (but not necessarily by the
same trade), and then the assembly is bid as a single component.
Example:
The cost per linear foot for an 8-foot-high interior wall (consisting
of track, metal studs, insulation, drywall, and paint) may be
determined. Then all 8-foot-high interior walls may be bid by the
linear foot rather than by bidding the track, metal studs, drywall,
insulation, and paint separately.
TYPES OF COST
ESTIMATE
ASSEMBLY ESTIMATE
To create an assembly, the estimator determines the
quantity of materials needed for one unit of the assembly, linear
foot of wall in the case of the interior wall. From these
quantities, the cost for materials, equipment, and labor to
construct one unit of the assembly is then determined. This cost
is then used to bid the assembly by multiplying the quantity of
the assembly by the unit cost of the assembly.
ASSEMBLY
ESTIMATE
WALL ASSEMBLY UNIT COST
Length of track = 2 x 1’ = 2’
Number of studs = 1’/16” = 12”/16” = 0 .75 each
Area of insulation = 8’ x 1’ x 15”/16” = 7 .5 sq. ft.
Area of drywall = 2 sides x 8’ x 1’ = 16 sq. ft.
Area of paint = 2 sides x 8’ x 1’ = 16 sq. ft.
ASSEMBLY
ESTIMATE
WALL ASSEMBLY UNIT COST
• SAMPLE PROBLEM 2.1
The costs are as follows:
Solution:
Total = $9,285 + $819 + $30,700 + $61,050 + $1,909 + $26,350 + $5,700 + $28,600 + $6,850 +
$12,000 + $12,288 + $777 + $2,400 + $15,900 + $2,725 + $22,300
SOLUTION:
TYPES OF COST
ESTIMATE
PARAMETRIC ESTIMATES
SOLUTION: