Hrms PP
Hrms PP
goals-based
issues-based
What data does each business area need to access and manage?
What are the specific challenges that each business area faces
in managing its HR processes and data?
Reduced costs
Improved compliance
2.4. Define a potential projects
Project Objective
Project Scope
Project Budget
Project Team:-
• Project Manager
• HR Business Analyst
• Systems Analyst
• Software Developer
• Technical Support Engineer
2.5. SELECT IT PROJECTS
Human Resources in Project Management focus on Project
Team recruitment, organization and management until the
end of a given project. Its role starts from defining core
competencies which are going to be needed, to team building
and motivation.
• Workday
• SAP Success Factors
• Oracle HCM Cloud
• ADP Workforce Now
• Benefits
• Rippling
• Monday.com
• Eddy
• Factorial
4. Statement of the Problem
A statement of the problem for an HRMS is a
clear and concise description of the challenges
that the organization is facing with its current
HR processes and systems. The statement of
the problem should be specific and
measurable, and it should identify the root
cause of the challenges.
5. SCOPE OF THE PROJECT
The scope of a Human Resource Management System (HRMS) is
the range of HR processes and functions that the system will
support. The scope of an HRMS can vary depending on the size
and needs of the organization
• Recruitment
• Onboarding
• Payroll
• Time and Attendance
• Performance Management
• Training and Development
• Employee Data Management
Geographical coverage
The geographical coverage of an HRMS refers to the regions or
countries where it can be used. Some HRMS systems are designed
for global use, while others are only designed for use in specific
regions or countries. It is important to choose an HRMS system
that can support the geographical needs of your organization.
TIME
TIME stands for time and motion studies.
TIME studies can be used to analyze and optimize HR processes.
This can lead to improved efficiency and effectiveness of the HR
department. TME studies can also be used to identify areas where
the HRMS system can be improved.
Theories
There are a number of theories that can be applied to the design
and implementation of HRMS systems. Some of the most
common theories include:
Systems theory
Contingency theory
Requirements gathering
System configuration
Data migration
User training
Testing
9.2. Budget plan HMR
9.2. Budget plan HMR
The human resources budget refers to the funds that HR
allocates to all HR processes enterprise-wide. The HR budget
will include funds allocated to hiring, salaries, benefits, talent
management, training, succession planning, workforce
engagement, and employee wellness planning.
9.2.1. How do you prepare an HR budget?
There are some steps you can take and best practices you can
apply which will make the planning of your HR budget more
effective.
Steps 1 – Define your business goals.
Step 2 – Review past budgets.
Step 3 – Analyze and forecast your workforce needs.
Step 4 – Prepare your HR budget based on data.
Step 5 – Plan for the best and worst-case scenarios.
Step 6 – Consider investments as business builders.
Step 7 – Have realistic expectations.
Step 8 – Get it approved.
9.2.2. Why do you need to plan your HR budget?
Planning an HR budget is just as necessary as costing any
other area of operations; in fact, it’s at the heart of why your
organization thrives.
The main reasons why you need to start thinking about
your HR budget in advance are to:
Managing the costs of human capital
Ensuring HR operational efficiency
Achieving organizational success
Have a seat at the decision-making table
There are different costing methods of our projects
• The total cost in our project is: $425560
1. Rough order magnitude (ROM): In ROM our cost range
between $319170 to $744730.
2. Budgetary estimate cost that range between $383004 to
$531950.
The definitive cost range between $404282 to $468116.
EV, CV, SV, CPI, SPI of our project
The total cost budgeted to complete the project
$425560.our project completed in 2 months. After 15 days
we have completed 20% of the project at the total expense
of $100, 000, the planned completion should have been
25%.
Given: Budget at complete (BAC) =$425560
Actual cost (AC) =$100000
Planned value (PV) =planned completion (%)*BAC)
=25%*425560 =$106390
Earned value (EV) =percent completed (%)*BAC
=20%*425560 =85112
Cost variance (CV) =EV-AC =85112-100,000 =-14888
Schedule variance (SV) =EV-PV =85112-106390 =-21278
Cost performance index (CPI) =EV/AC =85112/100000
=0.85112
• Schedule performance index (SPI) =EV/PV =85112/106390
TRAFIC LIGHT STATUS FOR OUR PROJECT
• The overall projects traffic light status
• Average=CPI+SPI/2 =0.85112+0.8/2 =0.82556(It is BAD)