CPM and PERT

The document discusses the Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) project modeling techniques. CPM helps project managers plan, schedule, and execute projects effectively by listing tasks, identifying the critical path, creating a critical path diagram, dividing the project into tasks, and estimating task times. PERT is used to determine the time it takes to finish tasks and activities, and helps with proper scheduling and tracking progress. The example shows constructing a project network, performing forward and backward passes to find the critical path, and calculating slack values.

Uploaded by

roan.fairrayos
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views

CPM and PERT

The document discusses the Critical Path Method (CPM) and Project Evaluation and Review Technique (PERT) project modeling techniques. CPM helps project managers plan, schedule, and execute projects effectively by listing tasks, identifying the critical path, creating a critical path diagram, dividing the project into tasks, and estimating task times. PERT is used to determine the time it takes to finish tasks and activities, and helps with proper scheduling and tracking progress. The example shows constructing a project network, performing forward and backward passes to find the critical path, and calculating slack values.

Uploaded by

roan.fairrayos
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 10

CPM/

PERT
Critical Path Method/ Project Evaluation and Review Technique
CRITICAL PATH METHOD
Is a project modeling technique that helps project
managers plan, schedule, and execute their project
effectively.
Example:
• Listing Project Tasks
• Identifying a project’s critical path
• Critical Path Diagram
• Dividing the Project into tasks
• Estimating Tasks
PROJECT
EVALUATION AND
REVIEW
• It is used to identifyTECHNIQUE
the time it takes to finish a
particular task or activity.
• It is a system that helps in the proper
scheduling and coordination of all tasks
throughout a project.
• It also helps in keeping track of the progress, or
lack thereof, of the overall project.
4
Insert Image

FINDING CRITICAL
PATH
• Construct a project network
• Perform forward and backward passes
• Determine project completion time
• Calculate slack values
• State critical path

5
FOR
EXAMPLE:

ACTIVITY A B C D E F G
PREDECESSOR - - A A,B D C,E E
S
EXPECTED 7 9 12 8 9 6 5
TIME Where:
A = activity being described
A ES EF t = activity time
ES= Earliest Start
t LS LF EF= Earliest Finish
LS= Latest Start
LF= Latest Finish
Insert Image

ACTIVITY A B C D E F G
PROJECT PREDECESSORS - - A A,B D C,E E

NETWORK: 7 9 12 8 9 6 5
EXPECTED TIME
(Weeks)

A 0 7 C 7 19 F 26 32
7 12 6
STAR FINIS
T B 0 9 D 9 17 E 17 26 G 26 31 H

9 8 9 5

FORMULA:
A E E • EF= ES + t

S F
Forward Pass = highest
value
• LS= LF – t

t L L
7
Backward Pass = lowest
value
Slack = LS – ES / LF – LF
Insert Image

ACTIVITY A B C D E F G
PROJECT PREDECESSORS - - A A,B D C,E E

NETWORK: 7 9 12 8 9 6 5
EXPECTED TIME
(Weeks)

A 0 7 C 7 19 F 26 32
32
7 2 9 12 14 26 6 26 32 weeks
STAR FINIS
T B 0 9 D 9 17 E 17 26 G 26 31 H

9 0 9 8 9 17 9 17 26 5 27 32

FORMULA:
A E E • EF= ES + t

S F
Forward Pass = highest
value
• LS= LF – t

t L L
8
Backward Pass = lowest
value
Slack = LS – ES / LF – LF
Insert Image

ACTIVITY A B C D E F G
PROJECT PREDECESSORS - - A A,B D C,E E

NETWORK: 7 9 12 8 9 6 5
EXPECTED TIME
(Weeks)

A 0 7 C 7 19 F 26 32
32
7 2 9 12 14 26 6 26 32 weeks
STAR S= 2 S= 7 S= 0 FINIS
T B 0 9 D 9 17 E 17 26 G 26 31 H

9 0 9 8 9 17 9 17 26 5 27 32
S= 0 S= 0 S= 1
S= 0
A E E FORMULA:
• EF= ES + t

S F Forward Pass = highest


value
B- D-E-F= CRITICAL PATH • LS= LF – t

t L L
9
Backward Pass = lowest
value
Slack = LS – ES / LF – EF
Insert Image

SLACK:
• how long the activity can be delayed without extending
or increasing the project completion time.

CRITICAL PATH:
• the longest sequence of tasks that must be completed
to execute a project. The tasks on the critical path are
called critical activities because if they're delayed,
the whole project completion will be delayed.